Maintenance Work Instruction Code: 4141 1YR INSP PIPELINES

UT TRAIN 1 STOP
Revision # 0
Issue Date 2023-10-19
Next Revision Date TBD
PV-P-PRM-001-0 Page 1 of 5

4141 YEARLY INSP PIPELINES UT TRAIN 1 STOP

Assigned Dept: 135 PV area: 4141 Main Work Center: 10RL-TAB


(PM6;CBM) (PRPDM)
Frequency: 1 YR Time to Complete: 18 hours Shutdown Required: YES
□ An open work permit Open Permit #: ____________
This work is covered by:
□ A new work permit Permit Board #: ____________

SAFETY INSTRUCTIONS & INFORMATION


** Complete an FLRA **
• Complete a proper walk around before entering any work
area when conducting the workplace exam.
• Note all hazards and conditions fixed on the workplace
examination template.
• Report all hazards that could not be fixed to your
immediate supervisor.
• Exercise your ‘Stop Work’ Authority if conditions are not
suitable for working.
• Do NOT conduct a task or operate equipment you are not
trained and proven competent on.
• Review any JSA’s with all personnel involved with this job.

Acceptance:

I have reviewed the work permit and carried out the required risk assessment. I have received the
necessary training and have been deemed competent to accomplish safely and correctly the required
tasks associated with this work instruction.

Accepted by: __________________Signature: ______________ Date:(yyyy-mm-dd) ____________


Maintenance Work Instruction Code: 4141 1YR INSP PIPELINES
UT TRAIN 1 STOP
Revision # 0
Issue Date 2023-10-19
Next Revision Date TBD
PV-P-PRM-001-0 Page 2 of 5

Documents and References:

PV-P-PRM-101-X_Process Plant Work Permit_revX_PVDC_date


PV-P-PR-031-X_Process Plant Field Level Risk Assessment_revX_PVDC_date
PV-P-PRO-xxx-0_Process Plant Job Hazard Analysis_revX_PVDC_date

Document Register
Register identification Type Location Retention period
Maintenance Planning Permanent.
Process Plant MWI Register Copy/filing cabinet
office Latest version is kept.
Permanent:
Livelink Electronic IT server
All versions are kept.
Permanent
RCMCost Electronic IT server
Latest version is kept
Revision History

Revision Date (yyyy-mm-dd) Description of changes and/or modifications


Maintenance Work Instruction Code: 4141 1YR INSP PIPELINES
UT TRAIN 1 STOP
Revision # 0
Issue Date 2023-10-19
Next Revision Date TBD
PV-P-PRM-001-0 Page 3 of 5

Task Details
PV3-4141-AUT0150-PIP (PIPELINES AUT0150)
Not Not
Task Description OK
OK Complete
Observations
Realizar una medición de espesores por ultrasonido
longitudinal (UT) en la tubería de alimentación lado norte de
la autoclave 150, notifique si hay condiciones inaceptables
para su operación, registre las medidas capturadas y
complete el reporte. Planos isométricos: (4141-10-PPS-114-
2205-6SF8E8-01) / (4141-10-PPS-115-Ti12-6TMIE8-01). /
Perform a longitudinal ultrasonic thickness measurement □ □ □
(UT) on the north side feed pipe of autoclave 150, notify if
there are unacceptable conditions for operation, record the
captured measurements and complete the report. Isometric
drawings: (4141-10-PPS-114-2205-6SF8E8-01) / (4141-10-
PPS-115-Ti12-6TMIE8-01).
Realizar una medición de espesores por ultrasonido
longitudinal (UT) en la tubería de alimentación lado sur de la
autoclave 150, notifique si hay condiciones inaceptables
para su operación, registre las medidas capturadas y
complete el reporte. Planos isométricos: (4141-10-PPS-119-
2205-6SF8E8-01) (4141-10-PPS-120-Ti12-6TMIE8-01). /
Perform a longitudinal ultrasonic thickness measurement □ □ □
(UT) on the south side feed pipe of autoclave 150, notify if
there are unacceptable conditions for operation, record the
captured measurements and complete the report. Isometric
drawings: (4141-10-PPS-119-2205-6SF8E8-01) (4141-10-PPS-
120-Ti12-6TMIE8-01).
Realizar una medición de espesores por ultrasonido
longitudinal (UT) en la tubería de descarga lado norte de la
autoclave 150, notifique si hay condiciones inaceptables
para su operación, registre las medidas capturadas y
complete el reporte. N7.4 - Planos isométricos: (4141-10-
PPS-3969-Ti12-6TMiE8-HC3). / Perform a longitudinal □ □ □
ultrasonic thickness measurement (UT) on the north side
discharge piping of autoclave 150, report if there are
unacceptable conditions for operation, record the captured
measurements and complete the report. N7.4 - Isometric
drawings: (4141-10-PPS-3969-Ti12-6TMiE8-HC3).
Realizar una medición de espesores por ultrasonido
longitudinal (UT) en la tubería de descarga lado sur de la
autoclave 150, notifique si hay condiciones inaceptables
para su operación, registre las medidas capturadas y □ □ □
complete el reporte. Planos isométricos: (4141-10-PPS-123-
Ti12-6TMIE8-01/02). / Perform a longitudinal ultrasonic
thickness measurement (UT) on the south side discharge
Maintenance Work Instruction Code: 4141 1YR INSP PIPELINES
UT TRAIN 1 STOP
Revision # 0
Issue Date 2023-10-19
Next Revision Date TBD
PV-P-PRM-001-0 Page 4 of 5

piping of autoclave 150, notify if there are unacceptable


conditions for operation, record the captured measurements
and complete the report. Isometric drawings: (4141-10-PPS-
123-Ti12-6TMIE8-01/02).
Maintenance Work Instruction Code: 4141 1YR INSP PIPELINES
UT TRAIN 1 STOP
Revision # 0
Issue Date 2023-10-19
Next Revision Date TBD
PV-P-PRM-001-0 Page 5 of 5

Line Ref # Observations - Notes - Comments

Spares, PPE & Special Tools


Spares description Times used in this PM

PPE & Special Tools Times used in this PM

Work Instruction - Final Comments

Additional Resources:

Actual Hours: Date:


Sign off: ____________________________________