1) What is the material cost of the part assuming that the cuttings are remelted
and the cost of mild steel is $6.25 per pound? What is the material cost of
the part assuming that the cuttings are not remelted?
The material cost of the part assuming that the cuttings are remelted and the cost of
mild steel is 6.25 per pound is 32 dollars. The material cost of the part assuming
that the cuttings are not melted would be 6.25*6.99=$43.72
Mass: 3.732 lb
a) The material cost of the part assuming that the cuttings are remelted
and the cost of aluminum 6061 is $0.62 per pound is $2.16. Unmelted its
17.558*.62=$10.89.
b) The mass of the material lost in a typical machining process is
17.558-3.482= 14.076lbs
c) the cost of the lost material based on your calculations
above?$10.89-$2.16=$8.73
d) 400*12ft^2/171.890 in^2 = 335 parts can be painted with one gallon of
paint that covers 400 ft2
e) You can either loft or extrude and cut in order to create the same part using
different processes.
Model 4 – Pipe Support
a) The material cost of the part assuming that the cuttings are remelted and the
cost of soft yellow brass is $13.50 per pound is $43.58. Unmelted would be
6.07*13.50=$81.95.
b) The mass of the material lost in a typical machining process is
6.07-3.228=2.84lbs.
c) The cost of the lost material based on your calculations above is
2.84(13.5)=$38.37
d) Another process that could be used to create this part is molding the shape.