Professional Documents
Culture Documents
id
SKRIPSI
Disusun Oleh:
i
library.uns.ac.id digilib.uns.ac.id
DAFTAR ISI
HALAMAN JUDUL................................................................................................ i
HALAMAN PERSETUJUAN SKRIPSI................................................................ ii
ABSTRAK ............................................................................................................. iv
ABSTRACT ............................................................................................................ v
PRAKATA ............................................................................................................. vi
DAFTAR ISI ......................................................................................................... vii
DAFTAR TABEL ................................................................................................... x
DAFTAR GAMBAR ........................................................................................... xiii
DAFTAR LAMPIRAN ........................................................................................ xiv
PENDAHULUAN ................................................................................ 1
1.1 Latar Belakang ......................................................................................... 1
1.2 Rumusan Masalah .................................................................................... 3
1.3 Batasan Masalah ....................................................................................... 3
1.4 Tujuan Penelitian ...................................................................................... 4
1.5 Manfaat Penelitian .................................................................................... 4
TINJAUAN PUSTAKA DAN LANDASAN TEORI .......................... 5
2.1 Tinjauan Pustaka ...................................................................................... 5
2.2 Landasan Teori ....................................................................................... 10
2.2.1 Value Engineering........................................................................... 10
2.2.2 Analisis Stabilitas Lereng ............................................................... 16
2.2.3 Analisis Rembesan Bendungan ....................................................... 19
2.2.4 Program GeoStudio ......................................................................... 21
METODE PENELITIAN ................................................................... 23
3.1 Jenis Penelitian ....................................................................................... 23
3.2 Tempat Penelitian ................................................................................... 23
3.3 Proses Penelitian..................................................................................... 24
3.3.1 Tahap Persiapan .............................................................................. 24
3.3.2 Data Penelitian ................................................................................ 24
3.3.3 Teknik Pengumpulan Data .............................................................. 25
vii
library.uns.ac.id digilib.uns.ac.id
viii
library.uns.ac.id digilib.uns.ac.id
ix
library.uns.ac.id digilib.uns.ac.id
DAFTAR TABEL
Tabel 2.1 Metode Paired Comparison Indeks, Sukma, B. (2011) ........................ 13
Tabel 2.2 Metode Paired Comparison Bobot, Sukma, B. (2011) ......................... 14
Tabel 2.3 Matriks Analisis Fungsi, Sukma, B. (2011) .......................................... 15
Tabel 2.4 Klasifikasi Faktor Keamanan menurut Ray dan De Smedt (2009) dalam
Hardiyatmo (2018) ................................................................................................ 17
Tabel 2.5 Analisis Stabilitas Lereng (SNI 8064:2016, Tabel 1) ........................... 18
Tabel 3.1 Cost Breakdown Structure .................................................................... 27
Tabel 3.2 Rincian Item Pada Alternatif Desain .................................................... 34
Tabel 4.1 Cost Breakdown Analysis RAB Proyek Rehabilitasi Bendungan Lalung
............................................................................................................................... 40
Tabel 4.2 Cost Breakdown Analysis Pekerjaan Tanah .......................................... 41
Tabel 4.3 Rincian Item Pada Ketiga Alternatif Desain ......................................... 45
Tabel 4.4 Analisis Harga Satuan Pekerjaan Galian Tanah ................................... 48
Tabel 4.5 Analisis Harga Satuan Pekerjaan Galian Tanah Kedalaman > 4 Meter 49
Tabel 4.6 Analisis Harga Satuan Pekerjaan Dump Truck Mengangkut Material
Dari Borrow Area Ke Lokasi Pekerjaan Dengan Jarak 5 Kilometer .................... 49
Tabel 4.7 Analisis Harga Satuan Pekerjaan Tambahan Biaya Angkut Dump
Truck Dengan Jarak Angkut Lokasi Pekerjaan Dengan Jarak Lebih Dari 5
Kilometer............................................................................................................... 50
Tabel 4.8 Analisis Harga Satuan Pekerjaan Timbunan Tanah Dari Borrow Area 51
Tabel 4.9 Analisis Harga Satuan Pekerjaan Galian Tanah Kedalaman 2 – 4 Meter
............................................................................................................................... 52
Tabel 4.10 Analisis Harga Satuan Pekerjaan Dump Truck Mengangkut Material
Dari Borrow Area Ke Lokasi Pekerjaan Dengan Jarak 5 Kilometer .................... 52
Tabel 4.11 Analisis Harga Satuan Pekerjaan Tambahan Biaya Angkut Dump
Truck Dengan Jarak Angkut Lokasi Pekerjaan Dengan Jarak Lebih Dari 5
Kilometer............................................................................................................... 53
Tabel 4.12 Analisis Harga Satuan Pekerjaan Pemadatan Tanah Di Lokasi
Pekerjaan ............................................................................................................... 53
Tabel 4.13 Analisis Harga Satuan Pekerjaan Lapisan Sirtu Tebal 30 cm ............. 54
Tabel 4.14 Analisis Harga Satuan Pekerjaan Galian Sirtu dari Sungai ................ 55
Tabel 4.15 Komposisi pekerjaan Dump Truck mengangkut material atau hasil
galian sejauh 1 km ................................................................................................. 56
Tabel 4.16 Komposisi pekerjaan Tambahan biaya angkut Dump Truck dengan
jarak angkut lokasi pekerjaan jarak > 1 km .......................................................... 57
Tabel 4.17 Komposisi pekerjaan Pemadatan sirtu di lokasi pekerjaan ................. 58
Tabel 4.18 Komposisi pekerjaan lapisan batu kosong/rip rap .............................. 59
Tabel 4.19 perhitungan volume galian tanah pada desain awal proyek rehabilitasi
bendungan lalung .................................................................................................. 60
x
library.uns.ac.id digilib.uns.ac.id
Tabel 4.20 perhitungan volume timbunan tanah pada desain awal proyek
rehabilitasi bendungan lalung ............................................................................... 61
Tabel 4.21 perhitungan volume galian tanah pada alternatif desain proyek
rehabilitasi bendungan lalung ............................................................................... 62
Tabel 4.22 perhitungan volume timbunan tanah pada alternatif desain proyek
rehabilitasi bendungan lalung ............................................................................... 63
Tabel 4.23 perhitungan volume pekerjaan lapis sirtu tebal 30 cm pada alternatif
desain proyek rehabilitasi bendungan lalung ........................................................ 64
Tabel 4.24 perhitungan volume pekerjaan lapisan batu kosong pada alternatif
desain proyek rehabilitasi bendungan lalung ........................................................ 65
Tabel 4.25 perhitungan volume galian tanah pada alternatif desain proyek
rehabilitasi bendungan lalung ............................................................................... 66
Tabel 4.26 perhitungan volume timbunan tanah pada alternatif desain proyek
rehabilitasi bendungan lalung ............................................................................... 67
Tabel 4.27 perhitungan volume galian tanah pada alternatif desain proyek
rehabilitasi bendungan lalung ............................................................................... 68
Tabel 4.28 perhitungan volume timbunan tanah pada alternatif desain proyek
rehabilitasi bendungan lalung ............................................................................... 69
Tabel 4.29 perhitungan volume pekerjaan lapis sirtu tebal 30 cm pada alternatif
desain proyek rehabilitasi bendungan lalung ........................................................ 70
Tabel 4.30 perhitungan volume pekerjaan lapisan batu kosong pada alternatif
desain proyek rehabilitasi bendungan lalung ........................................................ 71
Tabel 4.31 Perbandingan harga pekerjaan tanah desain awal dan harga pekerjaan
ketiga alternatif desain .......................................................................................... 72
Tabel 4.32 Perhitungan estimasi mutu pekerjaan desain awal .............................. 73
Tabel 4.33 Perhitungan estimasi rembesan pekerjaan desain awal....................... 74
Tabel 4.34 Perhitungan estimasi kekuatan pekerjaan desain alternatif 1.............. 76
Tabel 4.35 Perhitungan estimasi rembesan pekerjaan desain alternatif 1 ............ 77
Tabel 4.36 Perhitungan estimasi kekuatan pekerjaan desain alternatif 2.............. 79
Tabel 4.37 Perhitungan estimasi rembesan pekerjaan desain alternatif 2 ............. 80
Tabel 4.38 Perhitungan estimasi kekuatan pekerjaan desain alternatif 3.............. 82
Tabel 4.39 Perhitungan estimasi rembesan pekerjaan desain alternatif 3 ............. 83
Tabel 4.40 perbandingan kekuatan pekerjaan desain awal dan harga pekerjaan
alternative desain ................................................................................................... 85
Tabel 4.41 Rekapitulasi Properti Material yang Digunakan ................................. 85
Tabel 4.42 Rekapitulasi selisih SF pada desain awal ............................................ 86
Tabel 4.43 Rekapitulasi selisih SF pada alternatif desain 1 .................................. 87
Tabel 4.44 Rekapitulasi Selisih SF Alternatif Desain 2........................................ 89
Tabel 4.45 Rekapitulasi Selisih SF Alternatif Desain 3 ........................................ 90
Tabel 4.46 perbandingan waktu pekerjaan desain awal dan harga pekerjaan
alternative desain ................................................................................................... 94
Tabel 4.47 Metode Paired Comparison Bobot, Hasil Analisa Penelitian, (2023). 95
xi
library.uns.ac.id digilib.uns.ac.id
Tabel 4.48 Metode Paired Comparison Indeks Kriteria Biaya, Hasil Analisa
Penelitian, (2023) .................................................................................................. 95
Tabel 4.49 Metode Paired Comparison Indeks Kriteria Mutu Safety Factor, Hasil
Analisa Penelitian, (2023) ..................................................................................... 96
Tabel 4.50 Metode Paired Comparison Indeks Kriteria Mutu Rembesan, Hasil
Analisa Penelitian, (2023) ..................................................................................... 96
Tabel 4.51 Metode Paired Comparison Indeks Kriteria Waktu, Hasil Analisa
Penelitian, (2023) .................................................................................................. 96
Tabel 4.52 Metode Paired Comparison Indeks Kriteria Sumber Daya, Hasil
Analisa Penelitian, (2023) ..................................................................................... 97
Tabel 4.53 Matriks Analisis Fungsi, Hasil Analisa Penelitian, (2023) ................. 98
xii
library.uns.ac.id digilib.uns.ac.id
DAFTAR GAMBAR
Gambar 2.1 Koefisien gempa ................................................................................ 19
Gambar 2.2 Jaringan Trayektori Rembesan di Dalam Bendungan Urugan .......... 20
Gambar 3.1 Lokasi Tinjauan Penelitian, Google Maps, (2022) ........................... 23
Gambar 3.2 Diagram Cost Model ......................................................................... 26
Gambar 3.3 Grafik Distribusi Hukum Pareto ....................................................... 28
Gambar 3.4 Flowchart Penelitian ......................................................................... 32
Gambar 3.5 Desain Awal ...................................................................................... 33
Gambar 3.6 Alternatif Desain dengan Penambahan Toe Drain ............................ 33
Gambar 3.7 Alternatif Desain dengan Penambahan Cut & Fill ............................ 33
Gambar 3.8 Alternatif Desain dengan Penambahan Toe Drain dan Cut & Fill .... 34
Gambar 4.1 Lokasi Pekerjaan ............................................................................... 38
Gambar 4.2 Cost Model Proyek Rehabilitasi Bendungan Lalung ........................ 39
Gambar 4.3 Diagram Pareto RAB Proyek Rehabilitasi Bendungan Lalung
(Sumber: Hasil Analisis Penelitian, 2023) ............................................................ 42
Gambar 4.4 Diagram Elemen RAB ...................................................................... 42
Gambar 4.5 Desain Awal Tubuh Bendungan ....................................................... 44
Gambar 4.6 Alternatif Desain dengan Penambahan Toe Drain ............................ 44
Gambar 4.7 Alternatif Desain dengan Penambahan Desain Cut & Fill Pada Tubuh
Bendungan Bagian Bawah .................................................................................... 45
Gambar 4.8 Alternatif Desain dengan Penambahan Toe Drain dan Desain Cut &
Fill Pada Tubuh Bendungan Bagian Bawah ......................................................... 45
xiii
library.uns.ac.id digilib.uns.ac.id
DAFTAR LAMPIRAN
xiv