Professional Documents
Culture Documents
MINISTRY OF RAILWAYS
Safety Guidelines
for
Signalling Cables
CAMTECH/S/PROJ/2022-23/
SP-3A
April-2022
Any Suggestions about the pamphlet are welcome and may be sent on
Contact person:
Director(S&T)
Indian Railways Centre for Advanced Maintenance Technology
Maharajpur, Gwalior(MP)-474020
Ph:0751-2470185, Mob. No.: 9752447080 FAX:0751-24700841
E-mail: dirsntcamtech@gmail.com
Introduction
A Cable is a unit that contains more than one insulated
conductor bunched into a compact form by providing
mechanical Protection and electrical insulation.
Cables which are mainly used inside the building are
called Indoor cables and cable which are laid in the
outdoor are called Outdoor Signalling Cables.
Signalling cables play an essential role in ensuring the
transmission of signals and a continuous power supply
across all trackside signalling equipment applications.
These cables are used for control and signal conveyance
and keep the rail networks, with their passengers and
cargo, moving safely.
In the following sections guidelines for transportation,
laying & testing of signalling cables are given as per
RDSO guidelines on signalling cable laying vide
Document No. RDSO/SI/G/2010, Version 1.1 E
Effective from 04.02.2014.
3
Planning for Cabling
Cables for signalling circuits shall be of approved
types.
The number of conductors required, depending upon
the circuits should be first determined. Adequate spare
conductors to a minimum of 20% of the total
conductors used shall be provided for in each main
cable up to the farthest point zone, beyond this there
should be a minimum of 10% spare conductors of the
total conductors used.
Where a number of cables have been laid along a
route, the circuits shall be so distributed that cables can
be disconnected for maintenance purpose with the least
possible dislocation to traffic.
Cable route plan shall also be approved by
Engineering and Electrical departments. Approval of
S&T open line is also required where ever it is
prepared by other than open line. In case of
Construction works cable route plan shall be signed by
Engineering and Electrical departments of executing
agencies as well.
As far as possible low lying areas, platform copings,
drainages, hutments, rocky terrains, points and
crossings, shall be avoided. Proximity to Electrical Sub
Stations/Switching stations shall be avoided.
In case of Tunnel, provision of cable duct should form
part of the Tunnel design.
4
Storage and Transportation
Cable drums shall not be stacked on flat side.
Suitable stoppers shall be placed for stability.
It is desirable that cable drums are stored in
covered shed to protect against direct
exposure to sun.
5
Paying Out & Testing
For paying out cables, the cable drums shall be mounted on
cable wheels. It should be ensured that no kink is formed
while paying out the cable.
6
Trenching
For laying of signalling cables in the station yards from
Home to Home signal Manual trenching is
recommended.
From Home to distant signal and beyond into
block/automatic section – mechanized trenching is
recommended.
Under road/platforms/railway tracks/difficult terrain
etc., trench less horizontal directional drilling (HDD)
method may be adopted under the supervision of
competent staff for laying of GI/DWC-HDPE pipe.
Trenches shall be straight as far as possible and steep
angles shall be avoided, clearing roots of trees, rocks
etc in all types of soils.
The bottom of the trench shall be levelled and got rid
of any sharp materials like stone chips, iron pieces etc.
When cables are laid in trunking, it shall be cleared of
all ballast and stones before the cover is secured.
It is desirable that the trenches do not remain
uncovered for long period; instead cables are laid and
refilling done on the same day.
Before commencement of the laying, inspection of the
trench and inspection of protection works shall be
carried out.
7
Laying
The main cable laid parallel to the track shall normally be
buried at a depth of 1.0 m from top of cables to ground
level, including those laid across the track (1.0 m below the
rail flanges). The depth shall not be less than 0.50 m for tail
cables. In theft prone areas, the cables may be laid at a
depth of 1.2 m with anchoring at every 10 m.
Laid parallel to track 1.0 m depth Laid across to track 1.0 m depth
Cable Crossing
When a cable has to cross the track, is should be
ensured that-
(i) The cable crosses the track at right angles.
(ii) The cable does not cross the track under points and
crossings.
(iii) The cable is laid in concrete/GI/DWC-HDPE pipes of
approved type, suitable ducts or in any other approved
manner while crossing the track.
(iv) Wherever feasible horizontal directional drilling
method may be used.