You are on page 1of 98

Government of Nepal

Ministry of Energy, Water Resources and Irrigation


Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

SUMMARY OF COST
S. No. Item Code Item Unit Total Rate
I CIVIL WORKS
I.1 1.1 Site clearance m2 23316.05 42.12
I.2 2.4 Earthwork in excavation by mechanical means m3 56993.14 114.76
I.3 2.2 Earthwork in backfilling m3 9880.37 162.87
I.4 2.5 Earthwork in excavation under water for structure m3 49401.84 716.10
I.5 2.8 Earthwork in embankment from materials excavated and deposited m3 96514.61 298.66
I.6 2.7 Earthwork in embankment from borrow pit m3 64741.42 469.26
I.7 2.6 Stripping and storing top soil for embankment m3 6326.05 163.32
I.8 3.1 Concreting M10 m3 751.54 12,082.41
I.9 3.2 Concreting M15 m3 45.11 14,034.90
I.10 3.3 Concreting M20 m3 3723.41 17,697.75
I.11 3.4 Concreting M25 m3 24390.48 18,040.19
I.12 4.1 Reinforcement works kg 1004813.26 128.43
I.13 5.1 Formworks m2 14626.58 982.13
I.14 6.1 Boulder supply and filling in gabion boxes m3 15900 3,521.93
I.15 6.3 Gabion box (Size 3m x 1m x 1m) No 562 5,151.71
I.16 6.4 Gabion box (Size 3m x 1m x 0.5m) No 4274 3,603.92
I.17 6.5 Gabion box (Size 3m x 1m x 0.3m) No 5620 2,992.43
I.18 7.1 Gravel filter m3 7324.7 4,857.45
I.19 7.2 Geo textile m2 21498.03 240.49
I.20 7.3 Blanket layer below foundation m3 4923.13 3,300.81
I.21 8.1 Stone soling works m3 1969.25 4,795.57
I.22 9.1 Turfing m2 31630.25 25.00
I.23 10.1 Rubber seal m 750 1,602.90
I.24 11.1 Channel fixing for railing kg 1541.85 207.44
I.25 11.2 GI pipe fixing for railing m 1079.61 700.21
I.26 12.1 Sheet piling mt 421.2 164,792.98
I.27 12.2 Vertical boulder columns, 500mm dia m 41344 5,792.62
I.28 13.1 Subgrade preparation in dike road m2 8430.6 11.18
I.29 13.2 Sub-base course in dike road m3 1686.12 4,617.32
I.30 13.3 Base course in dike road m3 1264.59 5,583.29
Sub Total I (Civil Works)
II GENERAL ITEMS
II.1 Insurance
Third Party Insurance (0.15% of I)
Insurance of the work (0.15% of I)
Insurance against accident of the work (0.15% of I)
II.2 Commission for performance bond (0.05% of I)
Construction, maintenance and subsequent handover of Contractor's
II.3 office, workshops, stores, warehouses, motor pools etc. (0.25% of I)
Construction, maintenance and subsequent handover of contractor's
laboratory including laboratory equipment and execution of tests
II.4 (0.10% of I)
Construction and maintenance of temporary access road and public
II.5 roads used for access including land compensation (0.25% of I)
Preparation of as-build drawings including one soft copy and three
II.6 sets of prints (0.01% of I)
II.7 Engineer's Facility (0.15% of I)
II.8 Dayworks (0.05% of I)
II.9 Environmental mitigation, monitoring and management (1% of I)
Sub total II (General Items)
III CONTINENCIES
III.1 Contingencies (4% of I)
Sub Total III (Contingencies)
Sub Total I, II and III
VAT @ 13%
GRAND TOTAL
Amount

982,072.03
6,540,532.75
1,609,215.86
35,376,657.62
28,825,053.42
30,380,558.75
1,033,170.49
9,080,414.41
633,114.34
65,895,979.33
440,008,893.39
129,048,166.98
14,365,203.02
55,998,687.00
2,895,261.02
15,403,154.08
16,817,456.60
35,579,364.02
5,170,061.23
16,250,326.46
9,443,676.22
790,756.25
1,202,175.00
319,841.36
755,953.72
69,410,803.18
239,490,081.28
94,256.64
7,785,362.08
7,060,577.07
1,248,246,825.60

1,872,370.24
1,872,370.24
1,872,370.24
624,123.41

3,120,617.06
1,248,246.83

3,120,617.06

124,824.68
1,872,370.24
624,123.41
12,482,468.26
28,834,501.67

49,929,873.02
49,929,873.02
1,327,011,200.29
172,511,456.04
1,499,522,656.33
1687364860.83
-187,842,204.50
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

SUMMARY OF QUANTITIES AND COST


S. No. Item Code Item Unit Barrage and HR Dikes Total
1 1.1 Site clearance m2 23316.051 0 23316.05
2 2.4 Earthwork in excavation by mechanical means m3 49401.85 7591.2876 56993.14
3 2.2 Earthwork in backfilling m3 9880.369 0 9880.37
Earthwork in excavation under water for
4 2.5 m3 49401.84 0 49401.84
structure
Earthwork in embankment from materials
5 2.8 m3 0 96514.613 96514.61
excavated and deposited
6 2.7 Earthwork in embankment from borrow pit m3 0 64741.417 64741.42
7 2.6 Stripping and storing top soil for embankment m3 0 6326.05 6326.05
8 3.1 Concreting M10 m3 751.539 0 751.54
9 3.2 Concreting M15 m3 45.105 0 45.11
10 3.3 Concreting M20 m3 3723.408 0 3723.41
11 3.4 Concreting M25 m3 24390.482 0 24390.48
12 4.1 Reinforcement works kg 1004813.26 0 1004813.3
13 5.1 Formworks m2 14626.579 0 14626.58
14 6.1 Boulder supply and filling in gabion boxes m3 4941 10959 15900
15 6.3 Gabion box (Size 3m x 1m x 1m) No 0 562 562
16 6.4 Gabion box (Size 3m x 1m x 0.5m) No 1464 2810 4274
17 6.5 Gabion box (Size 3m x 1m x 0.3m) No 0 5620 5620
18 7.1 Gravel filter m3 3864 3460.7 7324.7
19 7.2 Geo textile m2 0 21498.03 21498.03
20 7.3 Blanket layer below foundation m3 4923.13 0 4923.13
21 8.1 Stone soling works m3 1969.252 0 1969.25
22 9.1 Turfing m2 0 31630.25 31630.25
23 10.1 Rubber seal m 750 0 750
24 11.1 Channel fixing for bridge railing kg 1541.85 0 1541.85
25 11.2 GI pipe fixing for bridge railing m 1079.612 0 1079.61
26 12.1 Sheet piling mt 421.2 0 421.2
27 12.2 Vertical boulder columns, 500mm dia m 41344 0 41344
28 13.1 Subgrade preparation in dike road m2 8430.6 8430.6
29 13.2 Sub-base course in dike road m3 1686.12 1686.12
30 13.3 Base course in dike road m3 1264.591 1264.59
TOTAL
Rate Amount Dike Amount Barrage Amount
42.12 982,072.03 0.00 982,072.03
114.76 6,540,532.75 871,176.16 5,669,356.59
162.87 1,609,215.86 0.00 1,609,215.86
716.10 35,376,657.62
0.00 35,376,657.62
298.66 28,825,053.42
28,825,054.20 -0.78
469.26 30,380,558.75 30,380,557.53 1.22
163.32 1,033,170.49 1,033,170.49 0.00
12,082.41 9,080,414.41 0.00 9,080,414.41
14,034.90 633,114.34 0.00 633,114.34
17,697.75 65,895,979.33 0.00 65,895,979.33
18,040.19 440,008,893.39 0.00 440,008,893.39
128.43 129,048,166.98 0.00 129,048,166.98
982.13 14,365,203.02 0.00 14,365,203.02
3,521.93 55,998,687.00 38,596,830.87 17,401,856.13
5,151.71 2,895,261.02 2,895,261.02 0.00
3,603.92 15,403,154.08 10,127,015.20 5,276,138.88
2,992.43 16,817,456.60 16,817,456.60 0.00
4,857.45 35,579,364.02 16,810,177.22 18,769,186.80
240.49 5,170,061.23 5,170,061.23 0.00
3,300.81 16,250,326.46 0.00 16,250,326.46
4,795.57 9,443,676.22 0.00 9,443,676.22
25.00 790,756.25 790,756.25 0.00
1,602.90 1,202,175.00 0.00 1,202,175.00
207.44 319,841.36 0.00 319,841.36
700.21 755,953.72 0.00 755,953.72
164,792.98 69,410,803.18 0.00 69,410,803.18
5,792.62 239,490,081.28 0.00 239,490,081.28
11.18 94,256.64 94,256.64 0.00
4,617.32 7,785,362.08 7,785,362.08 0.00
5,583.29 7,060,577.07 7,060,582.65 -5.58
1,248,246,825.60 167,257,718.14 1,080,989,107.46
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

ESTIMATE FOR BARRAGE


S. No. Item Code Item Unit No Length Breadth Height
1 Site Clearance
Undersluice Portion m2 2 35.8 83.402
Barrage Portion m2 1 206 83.402
Wester Regulator m2 1 10.501 5.9
Wester Regulator m2 1 3.5 4.6
Easter Regulator m2 1 10.5 6.4
Easter Regulator m2 1 4.6 4
1.1 Total Site Clearance m2

2 Gabion Box 3*1*0.5m


Box size 3m x 1m x 0.5m (Barrage) No 1096
Box size 3m x 1m x 0.5m (Undersluice) No 368
6.4 Total Gabion Boxes No

3 Boulder Filling
Boulder filling in gabion boxes (Barrage) m3 1096 3 1.5 0.75
Boulder filling in gabion boxes (Undersluice) m3 368 3 1.5 0.75
6.1 Total Boulder filling m3

4 Concreting M25
Concrete Footing m3 2 206 1 1.4
Concrete Footing m3 2 206 2 0.6
Concrete Footing m3 4 35.8 1 1.4
Concrete Footing m3 4 35.8 2 0.6
Barrage Portion m3 1 206 0.4 1.2
Barrage Portion m3 1 206 0.08
Barrage Portion m3 1 206 9.6 0.8
Barrage Portion m3 1 206 3.3 0.8
Barrage Portion m3 1 206 0.845
Barrage Portion m3 1 206 2 1.3
Barrage Portion m3 1 206 6.615
Barrage Portion m3 1 206 7.3395
Barrage Portion m3 1 206 0.7455
Barrage Portion m3 1 206 1.63 2.1
Barrage Portion m3 1 206 0.8085
Barrage Portion m3 1 206 2.4 3.3
Barrage Portion m3 1 206 6.2595
Barrage Portion m3 1 206 11.7 1.07
Barrage Portion m3 1 206 0.125
Barrage Portion m3 1 206 0.5 0.5
Barrage Portion m3 1 206 0.95 1.3
Barrage Portion m3 1 206 0.08
Barrage Portion m3 1 206 0.4 0.4
Barrage Portion m3 2 206 0.245
Barrage Portion m3 1 206 1.121 0.7
Undersluice Portion m3 2 25.8 0.4 1.2
Undersluice Portion m3 2 25.8 0.08
Undersluice Portion m3 2 25.8 9.1 0.8
Undersluice Portion m3 2 25.8 0.245
Undersluice Portion m3 2 25.8 3.56 1.5
Undersluice Portion m3 4 25.8 0.1824
Undersluice Portion m3 2 25.8 9.11 2.2
Undersluice Portion m3 2 25.8 19.255 2.59
Divide Wall m3 3 6.7 5.73 1.8
Divide Wall m3 3 1.8 0.845
Divide Wall m3 3 3.3 4.43 1.8
Divide Wall m3 3 8.4 4.36 1.8
Divide Wall m3 3 1.8 11.76
Divide Wall m3 3 15 6.66 1.8
Divide Wall m3 3 1.8 0.125
Divide Wall m3 3 1 6.16 1.8
Divide Wall m3 3 3 6.66 1.8
Fish Pass m3 14 2 0.5 0.75
Easter Head Regulator (u/s),St. Portion m3 1 6.4 3 1.2
Easter Head Regulator (u/s),St. Portion m3 1 6.4 1.2 3
Easter Head Regulator Inclined portion m3 1 6.4 0.11 1.2
Easter Head Regulator Inclined portion m3 2 6.4 0.114
Easter Head Regulator Inclined portion m3 1 6.4 1.2 2.74
Easter Head Regulator Inclined portion m3 1 6.4 0.24295
Easter Head Regulator Inclined portion m3 1 6.4 0.93 0.43
Easter Head Regulator Inclined portion m3 1 6.4 0.11745
Easter Head Regulator Inclined portion m3 1 6.4 1.77 0.81
Easter Head Regulator (d/s),St. Portion m3 1 6.4 1 1
Easter Head Regulator (d/s),St. Portion m3 1 6.4 5.59 0.5
Easter Head Regulator (d/s),St. Portion m3 1 6.4 1.3975
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.252
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.11 1.13
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.3 2.12
Easter Head Regulator (d/s),St. Portion m3 -1 0.8 1.2 6.4
Easter Head Regulator (d/s),St. Portion m3 -1 0.6 1.2 6.4
Easter Head Regulator (d/s),St. Portion m3 1 0.2 2.4 6.4
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.094068
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.315276
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.184983
Easter Head Regulator (d/s),St. Portion m3 1 6.4 0.2343985
Easter Head Regulator,Dividewall m3 2 3 2.0055
Easter Head Regulator,Dividewall m3 2 3 0.5 5.73
Easter Head Regulator,Dividewall m3 2 1.5 1.36325
Easter Head Regulator,Dividewall m3 2 1.5 0.5 3.895
Easter Head Regulator,Dividewall m3 2 3.794 1.561
Easter Head Regulator,Dividewall m3 2 3.794 0.5 4.46
Easter Head Regulator,Dividewall m3 2 2.4 1.771
Easter Head Regulator,Dividewall m3 2 2.4 0.5 5.06
Easter Head Regulator,Dividewall m3 2 0.5 0.8 3.464
Easter Head Regulator,Dividewall m3 2 0.5 0.8 2.4
Easter Head Regulator,Dividewall m3 2 0.5 1.884 2.4
Easter Head Regulator,Dividewall m3 2 0.5 0.256328
Easter Head Regulator,Dividewall m3 2 0.5 1.116 1.684
Easter Head Regulator,bridge m3 2 0.23 6.4 0.8
Easter Head Regulator,bridge m3 2 0.01875 6.4
Easter Head Regulator,bridge m3 1 4.55 6.4 0.3
Wester Head Regulator (u/s),St. Portion m3 1 5.9 3 1.2
Wester Head Regulator (u/s),St. Portion m3 1 5.9 1.2 3
Wester Head Regulator Inclined portion m3 1 5.9 0.11 1.2
Wester Head Regulator Inclined portion m3 2 5.9 0.114
Wester Head Regulator Inclined portion m3 1 5.9 1.2 2.76
Wester Head Regulator Inclined portion m3 1 5.9 0.23165
Wester Head Regulator Inclined portion m3 1 5.9 0.87 0.43
Wester Head Regulator Inclined portion m3 1 5.9 0.11745
Wester Head Regulator Inclined portion m3 1 5.9 1.7 0.81
Wester Head Regulator (d/s),St. Portion m3 1 5.9 1 1.1
Wester Head Regulator (d/s),St. Portion m3 1 5.9 5.6 0.48
Wester Head Regulator (d/s),St. Portion m3 1 5.9 1.736
Wester Head Regulator (d/s),St. Portion m3 1 5.9 0.324
Wester Head Regulator (d/s),St. Portion m3 1 5.9 0.11 1.2
Wester Head Regulator (d/s),St. Portion m3 1 5.9 0.28 2.32
Wester Head Regulator (d/s),St. Portion m3 -1 0.8 1.2 5.9
Wester Head Regulator (d/s),St. Portion m3 -1 0.5 1.2 5.9
Wester Head Regulator (d/s),St. Portion m3 1 0.1 2.4 5.9
Wester Head Regulator (d/s),St. Portion m3 1 5.9 0.1232
Wester Head Regulator (d/s),St. Portion m3 1 5.9 0.598092
Wester Head Regulator,Dividewall m3 2 3 2.0055
Wester Head Regulator,Dividewall m3 2 3 0.5 5.73
Wester Head Regulator,Dividewall m3 2 1.5 1.36115
Wester Head Regulator,Dividewall m3 2 1.5 0.5 3.889
Wester Head Regulator,Dividewall m3 2 3.827 1.58165
Wester Head Regulator,Dividewall m3 2 3.827 0.5 4.519
Wester Head Regulator,Dividewall m3 2 2.4 1.806
Wester Head Regulator,Dividewall m3 2 2.4 0.5 5.16
Wester Head Regulator,Dividewall m3 2 0.5 0.8 3.564
Wester Head Regulator,Dividewall m3 2 0.5 0.8 2.5
Wester Head Regulator,Dividewall m3 2 0.5 1.784 2.5
Wester Head Regulator,Dividewall m3 2 0.5 0.332928
Wester Head Regulator,Dividewall m3 2 0.5 1.216 1.684
Wester Head Regulator,bridge m3 2 0.23 5.9 0.8
Wester Head Regulator,bridge m3 2 0.01875 5.9
Wester Head Regulator,bridge m3 1 4.55 5.9 0.3
Wing walls (Base) u/s m3 2 5.2 22.7 0.8
Wing walls (Base) d/s m3 2 5.2 8.81 0.8
Wing walls (Base) d/s m3 2 5.2 2 0.8
Abutments (Base) m3 2 3.2 39.2 0.8
Wing Walls (Upper side) Both sides m3 2 10 2.0055
Wing Walls (Upper side) Both sides m3 2 10 0.5 5.73
Wing Walls (Lower side) Both sides m3 2 10 3.2
Wing Walls (Lower side) Both sides m3 2 10 0.5 8
Abutments Both sides m3 2 8.8 2.292
Abutments Both sides m3 2 8.8 0.5 5.73
Abutments Both sides m3 2 34.7 3.2
Abutments Both sides m3 2 34.7 0.5 8
Piers m3 19 1.2717 1.3 4.43
Piers m3 19 1.2717 0.845
Piers m3 19 2 1.8 4.43
Piers m3 19 6.6 1.8 4.36
Piers m3 19 7.26 1.8
Piers m3 19 1.2717 0.54
Piers m3 19 1.2717 6.56 1.8
Bridge m3 2 257.6 0.4 0.85
Bridge m3 2 257.6 0.0120125
Bridge m3 1 257.6 0.071 2.1
Bridge m3 2 257.6 0.1526625
Bridge m3 1 257.6 5 0.015
Bridge m3 1 257.6 4.55 0.165
Bridge m3 2 257.6 0.01875
Bridge m3 2 257.6 0.225 0.665
Cross-Girder m3 76 2.1 0.3 0.65
3.4 Total Concreting for RCC M25 m3

5 Formwork
Concrete Footing m2 4 206 1.4
Concrete Footing m2 2 206 2
Concrete Footing m2 4 35.8 1.4
Concrete Footing m2 2 35.8 2
Barrage Portion ( Both Sides) m2 2 0.4 1.2
Barrage Portion ( Both Sides) m2 2 0.08
Barrage Portion ( Both Sides) m2 2 9.6 0.8
Barrage Portion ( Both Sides) m2 2 3.3 0.8
Barrage Portion ( Both Sides) m2 2 0.845
Barrage Portion ( Both Sides) m2 2 2 1.3
Barrage Portion ( Both Sides) m2 2 6.615
Barrage Portion ( Both Sides) m2 2 7.3395
Barrage Portion ( Both Sides) m2 2 0.7455
Barrage Portion ( Both Sides) m2 2 1.63 2.1
Barrage Portion ( Both Sides) m2 2 0.8085
Barrage Portion ( Both Sides) m2 2 2.4 3.3
Barrage Portion ( Both Sides) m2 2 6.2595
Barrage Portion ( Both Sides) m2 2 11.7 1.07
Barrage Portion ( Both Sides) m2 2 0.125
Barrage Portion ( Both Sides) m2 2 0.5 0.5
Barrage Portion ( Both Sides) m2 2 0.95 1.3
Barrage Portion ( Both Sides) m2 2 0.08
Barrage Portion ( Both Sides) m2 2 0.4 0.4
Barrage Portion ( Both Sides) m2 2 0.245
Barrage Portion ( Both Sides) m2 2 1.121 0.7
Undersluice Portion ( Both Sides) m2 4 0.4 1.2
Undersluice Portion ( Both Sides) m2 4 0.08
Undersluice Portion ( Both Sides) m2 4 9.1 0.8
Undersluice Portion ( Both Sides) m2 4 0.245
Undersluice Portion ( Both Sides) m2 4 3.56 1.5
Undersluice Portion ( Both Sides) m2 8 0.1824
Undersluice Portion ( Both Sides) m2 4 9.11 2.2
Divide Wall m3 6 6.7 5.73
Divide Wall m3 6 0.845
Divide Wall m3 6 3.3 4.43
Divide Wall m3 6 8.4 4.36
Divide Wall m3 6 11.76
Divide Wall m3 6 15 6.66
Divide Wall m3 6 0.125
Divide Wall m3 6 1 6.16
Divide Wall m3 6 3 6.66
Fish Pass m2 28 2 0.75
Fish Pass m2 14 2 0.5
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 3 1.2
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 1.2 3
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.11 1.2
Easter Head Regulator (d/s),St. Portion, Both sides base m3 4 0.114
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 1.2 2.74
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.24295
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.93 0.43
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.11745
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 1.77 0.81
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 1 1
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 5.59 0.5
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 1.3975
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.252
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.11 1.13
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.3 2.12
Easter Head Regulator (d/s),St. Portion, Both sides base m3 -2 0.8 1.2
Easter Head Regulator (d/s),St. Portion, Both sides base m3 -2 0.6 1.2
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.2 2.4
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.094068
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.315276
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.184983
Easter Head Regulator (d/s),St. Portion, Both sides base m3 2 0.2343985
Easter Head Regulator,Dividewall m2 4 3 5.773
Easter Head Regulator,Dividewall m2 4 1.5 3.895
Easter Head Regulator,Dividewall m2 4 3.794 4.46
Easter Head Regulator,Dividewall m2 4 2.4 5.06
Easter Head Regulator,Dividewall m2 4 0.5 3.464
Easter Head Regulator,Dividewall m2 4 0.5 2.4
Easter Head Regulator,Dividewall m2 4 0.5 2.4
Easter Head Regulator,Dividewall m2 4 0.5 0.716
Easter Head Regulator,Dividewall m2 4 0.5 1.684
Easter Head Regulator,bridge m3 4 0.23 0.8
Easter Head Regulator,bridge m3 4 0.01875
Easter Head Regulator,bridge m3 2 4.55 0.3
Easter Head Regulator,bridge (Length) m2 4 6.4 0.8
Wester Head Regulator (u/s),St. Portion m3 2 3 1.2
Wester Head Regulator (u/s),St. Portion m3 2 1.2 3
Wester Head Regulator Inclined portion m3 2 0.11 1.2
Wester Head Regulator Inclined portion m3 4 0.114
Wester Head Regulator Inclined portion m3 2 1.2 2.76
Wester Head Regulator Inclined portion m3 2 0.23165
Wester Head Regulator Inclined portion m3 2 0.87 0.43
Wester Head Regulator Inclined portion m3 2 0.11745
Wester Head Regulator Inclined portion m3 2 1.7 0.81
Wester Head Regulator (d/s),St. Portion m3 2 1 1.1
Wester Head Regulator (d/s),St. Portion m3 2 5.6 0.48
Wester Head Regulator (d/s),St. Portion m3 2 1.736
Wester Head Regulator (d/s),St. Portion m3 2 0.324
Wester Head Regulator (d/s),St. Portion m3 2 0.11 1.2
Wester Head Regulator (d/s),St. Portion m3 2 0.28 2.32
Wester Head Regulator (d/s),St. Portion m3 -2 0.8 1.2
Wester Head Regulator (d/s),St. Portion m3 -2 0.5 1.2
Wester Head Regulator (d/s),St. Portion m3 2 0.1 2.4
Wester Head Regulator (d/s),St. Portion m3 2 0.1232
Wester Head Regulator (d/s),St. Portion m3 2 0.598092
Wester Head Regulator,Dividewall m2 4 3 5.73
Wester Head Regulator,Dividewall m2 4 3 0.5 5.73
Wester Head Regulator,Dividewall m2 4 1.5 3.889 3.889
Wester Head Regulator,Dividewall m2 4 3.827 4.519
Wester Head Regulator,Dividewall m2 4 2.4 5.16
Wester Head Regulator,Dividewall m2 4 0.5 3.564
Wester Head Regulator,Dividewall m2 4 0.5 2.5
Wester Head Regulator,Dividewall m2 4 0.5 0.816
Wester Head Regulator,Dividewall m2 4 0.5 1.684
Wester Head Regulator,bridge m3 4 0.23 0.8
Wester Head Regulator,bridge m3 4 0.01875
Wester Head Regulator,bridge m3 2 4.55 0.3
Wester Head Regulator,bridge (Length) m2 4 5.9 0.8
Wing walls (Base) u/s & d/s m3 2 5.2 0.8
Wing walls (Base) u/s m3 4 0.8 22.7
Wing walls (Base) d/s m3 4 0.8 8.81
Wing walls (Base) d/s m3 4 0.8 2
Abutments (Base) m3 4 0.8 39.2
Wing Walls (Upper side) Both sides m3 4 10 5.73
Wing Walls (Lower side) Both sides m3 4 10 8
Abutments Both sides m3 4 8.8 5.73
Abutments Both sides m3 4 34.7 8
Piers m2 38 27.509 5.76
Bridge ( Sides) m2 2 257.6 2.292
Bridge (Below) m2 1 257.6 1.274
Cross-Girder (Sides) m2 152 2.1 0.65
Cross-Girder (Below) m2 152 2.1 0.3
5.1 Total Formwork m2

6 Inverted filter
Barrage m3 2 206 10 0.75
Undersluice m3 4 25.8 10 0.75
7.1 Total Inverted filter m3

7 Concrete blocks in M20 concreting


Barrage m3 3078 1.2 1.2 0.65
Undersluice m3 378 1.2 1.2 0.65
Undersluice m3 522 1.2 1.2 0.65
3.3 Total Concrete blocks in M20 concreting m3

8 Stone Soling
Barrage Portion m3 1 206 0.52 0.2
Barrage Portion m3 1 206 0.02
Barrage Portion m3 1 206 0.02
Barrage Portion m3 1 206 0.08 0.2
Barrage Portion m3 1 206 0.02
Barrage Portion m3 1 206 0.02
Barrage Portion m3 1 206 12.44 0.2
Barrage Portion m3 1 206 0.0002
Barrage Portion m3 1 206 0.009
Barrage Portion m3 1 206 8.92 0.2
Barrage Portion m3 1 206 0.0006
Barrage Portion m3 1 206 2.97 0.2
Barrage Portion m3 1 206 12.13 0.2
Barrage Portion m3 1 206 0.0004
Barrage Portion m3 1 206 0.00005
Barrage Portion m3 1 206 0.0088
Barrage Portion m3 1 206 0.55 0.2
Barrage Portion m3 1 206 0.008
Barrage Portion m3 1 206 0.44 0.2
Barrage Portion m3 -2 206 2.204 0.2
Barrage Portion m3 -2 206 0.02
Barrage Portion m3 2 206 0.02
Barrage Portion m3 2 206 0.707 0.2
Barrage Portion m3 4 206 0.0083
Barrage Portion m3 2 206 1.204 0.2
Undersluice Portion m3 2 25.8 0.44 0.2
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 2 25.8 7.75 0.2
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 2 25.8 0.91 0.2
Undersluice Portion m3 2 25.8 3.53 0.2
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 2 25.8 9.56 0.2
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 2 25.8 3.04 0.2
Undersluice Portion m3 2 25.8 15.15 0.2
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 2 25.8 0.46 0.2
Undersluice Portion m3 4 25.8 0.0088
Undersluice Portion m3 2 25.8 0.44 0.2
8.1 Total Stone Soling m3

9 PCC M10
Barrage Portion m3 1 206 0.4 0.075
Barrage Portion m3 1 206 0.0015
Barrage Portion m3 1 206 0.57 0.075
Barrage Portion m3 1 206 12.44 0.075
Barrage Portion m3 1 206 0.00225
Barrage Portion m3 1 206 8.96 0.075
Barrage Portion m3 1 206 0.00075
Barrage Portion m3 1 206 3 0.075
Barrage Portion m3 1 206 12.21 0.075
Barrage Portion m3 1 206 0.0015
Barrage Portion m3 1 206 0.57 0.075
Barrage Portion m3 1 206 0.0015
Barrage Portion m3 1 206 0.4 0.075
Barrage Portion m3 -2 206 2.321 0.075
Barrage Portion m3 -2 206 0.00375
Barrage Portion m3 2 206 0.00375
Barrage Portion m3 2 206 0.849 0.075
Barrage Portion m3 4 206 0.0015375
Barrage Portion m3 2 206 1.121 0.075
Undersluice Portion m3 2 25.8 0.4 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 0.52 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 7.92 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 0.95 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 3.53 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 9.59 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 3.01 0.075
Undersluice Portion m3 2 25.8 15.21 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 0.52 0.075
Undersluice Portion m3 4 25.8 0.0015
Undersluice Portion m3 2 25.8 0.4 0.075
3.1 Total PCC M10 m3

10 Earthwork in Excavation
Gabion Box Portion (u/s),Undersluice (left) m3 1 12 35.8 0.75
Concrete Footing (u/s),Undersluice (left) m3 1 2 35.8 2
Concrete Block (u/s),Undersluice (left) m3 1 1.3 35.8 1.4
Concrete Block (u/s),Undersluice (left) m3 1 8.7 23.8 1.4
Stright portion ,Undersluice (left) m3 1 13.3 25.8 1.65
Inclined Portion ,Undersluice (left) m3 1 8.5 25.8 3.9
After Inclined Portion ,Undersluice (left) m3 1 18.89 25.8 5.246
Concrete Block (d/s),Undersluice (left) m3 1 2 23.81 4.2
Concrete Block (d/s),Undersluice (left) m3 1 8 35.8 4.2
Concrete Footing (d/s),Undersluice (left) m3 1 2 35.8 4.8
Gabion Box Portion (d/s),Undersluice (left) m3 1 12 35.8 3.55
Gabion Box Portion (u/s),Undersluice (right) m3 1 12 35.8 2.75
Concrete Footing (u/s),Undersluice (right) m3 1 2 35.8 4
Concrete Block (u/s),Undersluice (right) 1 1.3 35.8 3.4
Concrete Block (u/s),Undersluice (right) m3 1 8.7 23.8 3.4
Stright portion ,Undersluice (right) m3 1 13.3 25.8 3.65
Inclined Portion ,Undersluice(right) m3 1 8.5 25.8 5.9
After Inclined Portion ,Undersluice (right) m3 1 18.89 25.8 7.246
Concrete Block (d/s),Undersluice (right) m3 1 2 23.81 6.2
Concrete Block (d/s),Undersluice (right) 1 8 35.8 6.2
Concrete Footing (d/s),Undersluice (right) m3 1 2 35.8 6.8
Gabion Box Portion (d/s),Undersluice (right) m3 1 12 35.8 5.55
Gabion Box Portion (u/s),Barrage Portion m3 1 12 40.388 1.25
Concrete Footing (u/s),Barrage Portion m3 1 2 40.388 2
Concrete Block (u/s),Barrage Portion m3 1 10 40.388 1.9
Stright portion ,Barrage Portion m3 1 13.99 40.388 1.6
Inclined Portion ,Barrage Portion m3 1 8.9556 40.388 3.2758
After Inclined Portion ,Barrage Portion m3 1 16.263 40.388 4.3174
Concrete Block (d/s),Barrage Portion m3 1 10 40.388 3.4
Concrete Footing (d/s),Barrage Portion m3 1 2 40.388 4
Gabion Box Portion (d/s),Barrage Portion m3 1 12 40.388 2.75
Gabion Box Portion (u/s),Barrage Portion m3 1 12 36.0419 2.75
Concrete Footing (u/s),Barrage Portion m3 1 2 36.0419 4
Concrete Block (u/s),Barrage Portion m3 1 10 36.0419 3.4
Stright portion ,Barrage Portion m3 1 13.99 36.0419 3.1
Inclined Portion ,Barrage Portion m3 1 8.9556 36.0419 4.65
After Inclined Portion ,Barrage Portion m3 1 16.263 36.0419 5.656
Concrete Block (d/s),Barrage Portion m3 1 10 36.0419 4.9
Concrete Footing (d/s),Barrage Portion m3 1 2 36.0419 5.5
Gabion Box Portion (d/s),Barrage Portion m3 1 12 36.0419 4.25
Gabion Box Portion (u/s),Barrage Portion m3 1 12 56.9515 3.25
Concrete Footing (u/s),Barrage Portion m3 1 2 56.9515 4.5
Concrete Block (u/s),Barrage Portion m3 1 10 56.9515 3.9
Stright portion ,Barrage Portion m3 1 13.99 56.9515 3.6
Inclined Portion ,Barrage Portion m3 1 8.9556 56.9515 5.15
After Inclined Portion ,Barrage Portion m3 1 16.263 56.9515 6.156
Concrete Block (d/s),Barrage Portion m3 1 10 56.9515 5.4
Concrete Footing (d/s),Barrage Portion m3 1 2 56.9515 6
Gabion Box Portion (d/s),Barrage Portion m3 1 12 56.9515 4.75
Gabion Box Portion (u/s),Barrage Portion m3 1 12 72.6 2.75
Concrete Footing (u/s),Barrage Portion m3 1 2 72.6 4
Concrete Block (u/s),Barrage Portion m3 1 10 72.6 3.4
Stright portion ,Barrage Portion m3 1 13.99 72.6 3.1
Inclined Portion ,Barrage Portion m3 1 8.9556 72.6 4.65
After Inclined Portion ,Barrage Portion m3 1 16.263 72.6 5.656
Concrete Block (d/s),Barrage Portion m3 1 10 72.6 4.9
Concrete Footing (d/s),Barrage Portion m3 1 2 72.6 5.5
Gabion Box Portion (d/s),Barrage Portion m3 1 12 72.6 4.25
Wester Main Canal (u/s),St. Portion m3 1 4.2 5.9 1.3
Wester Main Canal (u/s),St. Portion m3 1 2.7 5.9 1.03
Wester Main Canal Inclined portion m3 1 3.6 5.9 0.743
Wester Main Canal (d/s),St. Portion m3 1 4.6 5.9 1.5
Easter Main Canal (u/s),St. Portion m3 1 4.2 6.4 3.13
Easter Main Canal (u/s),St. Portion m3 1 0.7 6.4 2.33
Easter Main Canal Inclined portion m3 1 3.6 6.4 2.176
Easter Main Canal (d/s),St. Portion m3 1 4.6 6.4 2.8
Concrete Block (u/s),abutment wall, left m3 1 14 5.2 1.4
Concrete Block (u/s),abutment wall m3 1 3.5 5.2 1.4
Straight portion ,Wall m3 1 11.8 3.2 1.5
Inclined Portion ,Wall m3 1 8.4 3.2 2.8
After Inclined Portion ,Wall m3 1 15.8 3.2 5.1174
Striaght portion u/s,Wall m3 1 12.01 3.2 1.4
Striaght portion d/s,Wall m3 1 14.01 2 5.1174
Concrete Block (u/s),abutment wall,right m3 1 14 5.2 3.4
Concrete Block (u/s),abutment wall m3 1 3.5 5.2 3.4
Stright portion ,Wall m3 1 11.8 3.2 3.5
Inclined Portion ,Wall m3 1 8.4 3.2 4.8
After Inclined Portion ,Wall m3 1 15.8 3.2 7.1774
Striaght portion u/s,Wall m3 1 12.01 3.2 3.4
Striaght portion d/s,Wall m3 1 14.01 2 7.1774
for blanket layer m3
Total Earthwork in Excavation m3
2.4 Earthwork in Excavation by mechanical means
Earthwork in Excavation by mechanical means under
2.5 water

11 Backfilling for Structures


2.2 Total Backfilling for structures

12 Concreting M15
Head Regulator (Wester Main Canal) m3 1 5.9 0.09 1.8
Head Regulator (Wester Main Canal) m3 1 5.9 1.1745
Head Regulator (Wester Main Canal) m3 1 5.9 2.61 0.86
Head Regulator (Easter Main Canal) m3 1 6.4 0.11 1.8
Head Regulator (Easter Main Canal) m3 1 6.4 1.1137
Head Regulator (Easter Main Canal) m3 1 6.4 2.59 0.94
3.2 Total Concreting M15 m3

Rubber seal supply and fixing


u/s long joint m 1 275
slope end long joint m 1 275
u/s floor short joints m 4 15
d/s floor short joints m 4 20
joint on weir portion m 4 15
10.1 Total Rubber seal supply and fixing m

13 GI Pipes
Bridge m 4 257.603
Head Regulator m 4 6.4
Head Regulator m 4 5.9
11.2 Total GI Pipes m

14 Sheet piling
u/s end @ 120kg/m2 m2 1 260 7
d/s end m2 1 260 6.5
Total sheet piling m2
12.1 Total sheet piling @120kg/m2 mt

15 12.2 Vertical boulder columns, 500mm dia m 2432 17


16 7.3 Blanket layer below foundation m3
Quantity Remarks

5971.583
17180.812
61.956
16.1
67.2
18.4
23316.051

1096
368
1464

3699
1242
4941

576.8
494.4
200.48
171.84
98.88
16.48
1582.08
543.84
174.07
535.6
1362.69
1511.937
153.573
705.138
166.551
1631.52
1289.457
2578.914
25.75
51.5
254.41
16.48
32.96
100.94
161.648
24.768
4.128
375.648
12.642
275.544
18.824
1034.167
2573.315
207.311
4.563
78.943
197.77
63.504
539.46
0.675
33.264
107.892
10.5
23.04
23.04
0.845
1.459
21.043
1.555
2.559
0.752
9.176
6.4
17.888
8.944
1.613
0.796
4.07
-6.144
-4.608
3.072
0.602
2.018
1.184
1.5
12.033
17.19
4.09
5.843
11.845
16.921
8.501
12.144
2.771
1.92
4.522
0.256
1.879
2.355
0.24
8.736
21.24
21.24
0.779
1.345
19.541
1.367
2.207
0.693
8.124
6.49
15.859
10.242
1.912
0.779
3.833
-5.664
-3.54
1.416
0.727
3.529
12.033
17.19
4.083
5.834
12.106
17.294
8.669
12.384
2.851
2
4.46
0.333
2.048
2.171
0.221
8.054
188.864
73.299
16.64
200.704
40.11
57.3
64
80
40.339
50.424
222.08
277.6
139.151
20.417
303.012
984.139
248.292
13.048
285.308
175.168
6.189
38.408
78.652
19.32
193.393
9.66
77.087
31.122
24390.482

1153.6
824
200.48
143.2
0.96
0.16
15.36
5.28
1.69
5.2
13.23
14.679
1.491
6.846
1.617
15.84
12.519
25.038
0.25
0.5
2.47
0.16
0.32
0.49
1.569
1.92
0.32
29.12
0.98
21.36
1.459
80.168
230.346
5.07
87.714
219.744
70.56
599.4
0.75
36.96
119.88
42
14
7.2
7.2
0.264
0.456
6.576
0.486
0.8
0.235
2.867
2
5.59
2.795
0.504
0.249
1.272
-1.92
-1.44
0.96
0.188
0.631
0.37
0.469
69.276
23.37
67.685
48.576
6.928
4.8
4.8
1.432
3.368
0.736
0.075
2.73
20.48
7.2
7.2
0.264
0.456
6.624
0.463
0.748
0.235
2.754
2.2
5.376
3.472
0.648
0.264
1.299
-1.92
-1.2
0.48
0.246
1.196
68.76
34.38
90.746
69.177
49.536
7.128
5
1.632
3.368
0.736
0.075
2.73
18.88
8.32
72.64
28.192
6.4
125.44
229.2
320
201.696
1110.4
6021.17
1180.838
328.182
207.48
95.76
14626.579

3090
774
3864

2881.008
353.808
488.592
3723.408

21.424
4.12
4.12
3.296
4.12
4.12
512.528
0.041
1.854
367.504
0.124
122.364
499.756
0.082
0.01
1.813
22.66
1.648
18.128
-181.61
-8.24
8.24
58.257
6.839
99.21
4.541
0.908
0.908
79.98
0.908
0.908
9.391

0.908
98.659
0.908
31.373
156.348
0.908
4.747
0.908
4.541
1969.252

6.18
0.309
8.807
192.198
0.464
138.432
0.155
46.35
188.645
0.309
8.807
0.309
6.18
-71.719
-1.545
1.545
26.234
1.267
34.639
1.548
0.155
2.012
0.155
30.65
0.155
3.677
0.155
13.661
0.155
37.113
0.155
11.649
58.863
0.155
2.012
0.155
1.548
751.539
322.2
143.2
65.156
289.884
566.181
855.27
2556.701
200.004
1202.88
343.68
1525.08
1181.4
286.4

704.004
1252.461
1293.87
3531.425
295.244

486.88
2384.28
605.82
161.552
767.372
904.045
1184.853
2835.798
1373.192
323.104
1332.804
1189.383
288.335
1225.425
1563.101
1500.912
3315.261
1766.053
396.461
1838.137
2221.109
512.564
2221.109
2868.305
2626.679
5701.701
3075.381
683.418
3246.236
2395.8
580.8
2468.4
3148.589
3023.321
6678.004
3557.4
798.6
3702.6
32.214
16.408
15.781
40.71
84.134
10.438
50.135
82.432
101.92
25.48
56.64
75.264
258.736
53.805
143.39
247.52
61.88
132.16
129.024
362.889
130.669
201.111
4923.13
98803.694
49401.85

49401.84

9880.369

0.956
6.93
13.243
1.267
7.128
15.581
45.105

275
275
60
80
60
750

1030.412
25.6
23.6
1079.612

1820
1690
3510 1.425
421.2 6.091875
2.4681724
41344
4923.13
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

ESTIMATE FOR DIKES


S. No. Item code Item Detail Unit No Length
1 Box size 3m x 1m x 0.3m
Dike 1 Along Slope of dike No. 642
Along Slope of dike No. 71
Dike 2 Along Slope of dike No. 4416
Along Slope of dike No. 491
6.5 Total
1 Box size 3m x 1m x 0.5m
Dike 1 Along base of dike No. 214
Along base of dike No. 142
Dike 2 Along base of dike No. 1472
Along base of dike No. 982
6.4 Total
3 Box size 3m x 1m x 1m
Dike 1 Along base of dike No. 71
Dike 2 Along base of dike No. 491
6.3 Total
2 Boulder filling in gabion boxes
Box size 3m x 1m x 0.3m Along Slope of dike m3 642 3
Box size 3m x 1m x 0.3m Along Slope of dike m3 71 3
Box size 3m x 1m x 0.3m Along Slope of dike m3 4416 3
Box size 3m x 1m x 0.3m Along Slope of dike m3 491 3
Box size 3m x 1m x 0.5m Along base of dike m3 214 3
Box size 3m x 1m x 0.5m Along base of dike m3 142 3
Box size 3m x 1m x 0.5m Along base of dike m3 1472 3
Box size 3m x 1m x 0.5m Along base of dike m3 982 3
Box size 3m x 1m x 1m Along base of dike m3 71 3
Box size 3m x 1m x 1m Along base of dike m3 491 3
6.1 Total
3 Earthwork
2.4 Earthwork in excavation for dikes m3
2.8 Earthwork in embankment from cut materials m3
2.7 Earthwork in embankment from borrow pit m3
2.6 Earthwork in topsoil of embankment for turfing m3 1 31630.2

4 Grass Turfing
Dike 1 Left of dyke m2
Right of dyke m2
Dike 2 Left of dyke m2
Right of dyke m2
9.1 Total
Gravel Packing (Dike)
Dike 1 Along slope of dike m3 1 214.57
Along slope of dike m3 1 214.57
Dike 2 Along slope of dike m3 1 1471.55
Along slope of dike m3 1 1471.55
7.1 Total

Geo Textile (Dike) Along slope of dike m2 1 214.57


Along slope of dike m2 1 1471.55
7.2 Total

Subgrade preparation
Sub-Grade (Dyke 1) m2 1 214.57
Sub-Grade (Dyke 2) m2 1 1471.55
13.1 Total subgrade preparation m2

Sub-base materials
Sub-base (Dyke 1) m3 1 214.57
Sub-base (Dyke 2) m3 1 1471.55
13.2 Total sub base materials

WBM Base course


Base (Dyke 1) m3 1 214.57
Base (Dyke 2) m3 1 1471.55
13.3 Total WBM Base course
Breadth Height Quantity Remarks

642
71
4416
491
5620

214
142
1472
982
2810

71
491
562

1 0.3 577.8
1 0.3 63.9
1 0.3 3974.4
1 0.3 441.9
1 0.5 321
1 0.5 213
1 0.5 2208
1 0.5 1473
1 1 213
1 1 1473
10959

7591.2876
96514.6126
64741.42
0.2 6326.05 for turfing in dikes

1127.79
2363.42
9172.17
18966.87
31630.25
10.2123 0.2 438.25
0.05 0.2 2.15
10.2123 0.2 3005.58
0.05 0.2 14.72
3460.7

12.75 2735.77
12.75 18762.26
21498.03

5 1072.85
5 7357.75
8430.6

5 0.2 214.57
5 0.2 1471.55
1686.12

5 0.15 160.928
5 0.15 1103.663
1264.591
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

EARTHWORK IN DIKES
Dyke1
Side slope (s) 2
Top Width 5m
Ground Formation Avg. Area of middle Total area Quantity ( Bd+sd^2)*L
Chainage(m) Depth(d) Distance
level level Depth(d) part (Bd) Bd+sd^2 Cutting (m3)
0 83.280 89.000 5.720 5.245 26.225 81.245 50
50 85.310 90.08 4.770 5.185 25.925 79.693 50
100 85.420 91.02 5.600 5.555 27.775 89.491 50
150 86.010 91.52 5.510 5.660 28.300 92.371 50
200 86.200 92.01 5.810 4.445 22.225 61.741 14.57
214.57 89.090 92.17 3.080
Total 0.000

Cutting for gabion at base 3*1*1 For dyke 1


Ground Formation Avg. Area of middle Total area Quantity ( Bd+sd^2)*L
Chainage(m) Depth(d) Distance
level level Depth(d) part (Bd) Bd Cutting (m3)
0 83.280 82.420 0.860 1.920 1.920 1.920 50 96.000
50 85.310 82.33 2.980 1.790 1.790 1.790 50 89.500
100 85.420 84.82 0.600 0.780 0.780 0.780 50 39.000
150 86.010 85.05 0.960 0.970 0.970 0.970 50 48.500
200 86.200 85.22 0.980 1.580 1.580 1.580 14.57 23.021
214.57 89.090 86.91 2.180
Total 296.021

Cutting for gabion at base 3*1*0.5 For dyke 1


Ground Formation Avg. Area of middle Total area Quantity ( Bd+sd^2)*L
Chainage(m) Depth(d) Distance
level level Depth(d) part (Bd) Bd Cutting (m3)
0 83.280 82.920 0.360 1.420 7.100 7.100 50 355.000
50 85.310 82.83 2.480 1.290 6.450 6.450 50 322.500
100 85.420 85.32 0.100 0.280 1.400 1.400 50 70.000
150 86.010 85.55 0.460 0.470 2.350 2.350 50 117.500
200 86.200 85.72 0.480 1.080 5.400 5.400 14.57 78.678
214.57 89.090 87.41 1.680
Total 943.678

Dyke2
Side slope (s) 2
Top Width 5m
Ground Formation Avg. Area of middle Total area Quantity ( Bd+sd^2)*L
Chainage(m) Depth(d) Distance
level level Depth(d) part (Bd) Bd+sd^2 Cutting (m3)
0 85.610 91.310 5.700 5.670 28.350 92.648 50 175
50 85.720 91.36 5.640 5.620 28.100 91.269 50 175
100 85.810 91.41 5.600 5.710 28.550 93.758 50 175
150 85.620 91.44 5.820 6.220 31.100 108.477 50 175
200 84.880 91.5 6.620 6.095 30.475 104.773 50 175
250 85.980 91.55 5.570 5.505 27.525 88.135 50 175
300 86.150 91.59 5.440 5.535 27.675 88.947 50 175
350 86.010 91.64 5.630 5.585 27.925 90.309 50 175
400 86.150 91.69 5.540 5.635 28.175 91.681 50 175
450 86.000 91.73 5.730 5.645 28.225 91.957 50 175
500 86.220 91.78 5.560 5.440 27.200 86.387 50 175
550 86.500 91.82 5.320 5.375 26.875 84.656 50 175
600 86.450 91.88 5.430 5.450 27.250 86.655 50 175
650 86.450 91.92 5.470 5.460 27.300 86.923 50 175
700 86.530 91.98 5.450 5.405 27.025 85.453 50 175
750 86.650 92.01 5.360 5.425 27.125 85.986 50 175
800 86.580 92.07 5.490 5.490 27.450 87.730 50 175
850 86.620 92.11 5.490 5.530 27.650 88.812 50 175
900 86.580 92.15 5.570 6.070 30.350 104.040 50 175
950 86.640 93.21 6.570 6.060 30.300 103.747 50 175
1000 86.700 92.25 5.550 5.635 28.175 91.681 50 175
1050 86.580 92.3 5.720 5.810 29.050 96.562 50 175
1100 86.450 92.35 5.900 5.890 29.450 98.834 50 175
1150 86.510 92.39 5.880 5.805 29.025 96.421 50 175
1200 86.720 92.45 5.730 5.605 28.025 90.857 50 175
1250 87.010 92.49 5.480 6.055 30.275 103.601 50 175
1300 85.890 92.52 6.630 6.555 32.775 118.711 50 175
1350 86.100 92.58 6.480 6.345 31.725 112.243 50 175
1400 86.410 92.62 6.210 7.390 36.950 146.174 50 175
1450 84.110 92.68 8.570 7.415 37.075 147.039 21.55 75.425
1471.55 86.440 92.7 6.260
Total 1050.000

Cutting for gabion at base 3*1*1 For dyke 2


Ground Formation Avg. Area of middle Total area Quantity ( Bd+sd^2)*L
Chainage(m) Depth(d) Distance
level level Depth(d) part (Bd) Bd Cutting (m3)
0 85.610 84.880 0.730 0.780 3.900 3.900 50 195.000
50 85.720 84.89 0.830 1.020 1.020 1.020 50 51.000
100 85.810 84.6 1.210 1.045 1.045 1.045 50 52.250
150 85.620 84.74 0.880 0.315 0.315 0.315 50 15.750
200 84.880 85.13 -0.250 0.455 0.455 0.455 50 22.750
250 85.980 84.82 1.160 1.060 1.060 1.060 50 53.000
300 86.150 85.19 0.960 1.010 1.010 1.010 50 50.500
350 86.010 84.95 1.060 1.330 1.330 1.330 50 66.500
400 86.150 84.55 1.600 1.400 1.400 1.400 50 70.000
450 86.000 84.8 1.200 1.105 1.105 1.105 50 55.250
500 86.220 85.21 1.010 1.050 1.050 1.050 50 52.500
550 86.500 85.41 1.090 1.225 1.225 1.225 50 61.250
600 86.450 85.09 1.360 1.130 1.130 1.130 50 56.500
650 86.450 85.55 0.900 0.965 0.965 0.965 50 48.250
700 86.530 85.5 1.030 1.125 1.125 1.125 50 56.250
750 86.650 85.43 1.220 1.105 1.105 1.105 50 55.250
800 86.580 85.59 0.990 1.010 1.010 1.010 50 50.500
850 86.620 85.59 1.030 0.965 0.965 0.965 50 48.250
900 86.580 85.68 0.900 0.805 0.805 0.805 50 40.250
950 86.640 85.93 0.710 0.865 0.865 0.865 50 43.250
1000 86.700 85.68 1.020 1.050 1.050 1.050 50 52.500
1050 86.580 85.5 1.080 1.015 1.015 1.015 50 50.750
1100 86.450 85.5 0.950 0.875 0.875 0.875 50 43.750
1150 86.510 85.71 0.800 0.950 0.950 0.950 50 47.500
1200 86.720 85.62 1.100 1.045 1.045 1.045 50 52.250
1250 87.010 86.02 0.990 0.940 0.940 0.940 50 47.000
1300 85.890 85 0.890 0.990 0.990 0.990 50 49.500
1350 86.100 85.01 1.090 0.970 0.970 0.970 50 48.500
1400 86.410 85.56 0.850 0.730 0.730 0.730 50 36.500
1450 84.110 83.5 0.610 0.980 0.980 0.980 21.55 21.119
1471.55 86.440 85.09 1.350
Total 1593.619

Cutting for gabion at base 3*1*0.5 For dyke 2


Ground Formation Avg. Area of middle Total area Quantity ( Bd+sd^2)*L
Chainage(m) Depth(d) Distance
level level Depth(d) part (Bd) Bd Cutting (m3)
0 85.610 85.380 0.230 0.280 1.400 1.400 50 70.000
50 85.720 85.39 0.330 0.520 2.600 2.600 50 130.000
100 85.810 85.1 0.710 0.545 2.725 2.725 50 136.250
150 85.620 85.24 0.380 0.565 2.825 2.825 50 141.250
200 84.880 85.63 0.750 0.705 3.525 3.525 50
250 85.980 85.32 0.660 0.560 2.800 2.800 50 140.000
300 86.150 85.69 0.460 0.510 2.550 2.550 50 127.500
350 86.010 85.45 0.560 0.830 4.150 4.150 50 207.500
400 86.150 85.05 1.100 0.900 4.500 4.500 50 225.000
450 86.000 85.3 0.700 0.605 3.025 3.025 50 151.250
500 86.220 85.71 0.510 0.550 2.750 2.750 50 137.500
550 86.500 85.91 0.590 0.725 3.625 3.625 50 181.250
600 86.450 85.59 0.860 0.630 3.150 3.150 50 157.500
650 86.450 86.05 0.400 0.465 2.325 2.325 50 116.250
700 86.530 86 0.530 0.625 3.125 3.125 50 156.250
750 86.650 85.93 0.720 0.605 3.025 3.025 50 151.250
800 86.580 86.09 0.490 0.510 2.550 2.550 50 127.500
850 86.620 86.09 0.530 0.465 2.325 2.325 50 116.250
900 86.580 86.18 0.400 0.305 1.525 1.525 50 76.250
950 86.640 86.43 0.210 0.365 1.825 1.825 50 91.250
1000 86.700 86.18 0.520 0.550 2.750 2.750 50 137.500
1050 86.580 86 0.580 0.515 2.575 2.575 50 128.750
1100 86.450 86 0.450 0.375 1.875 1.875 50 93.750
1150 86.510 86.21 0.300 0.450 2.250 2.250 50 112.500
1200 86.720 86.12 0.600 0.545 2.725 2.725 50 136.250
1250 87.010 86.52 0.490 0.440 2.200 2.200 50 110.000
1300 85.890 85.5 0.390 0.490 2.450 2.450 50 122.500
1350 86.100 85.51 0.590 0.470 2.350 2.350 50 117.500
1400 86.410 86.06 0.350 0.230 1.150 1.150 50 57.500
1450 84.110 84 0.110 0.480 2.400 2.400 21.55 51.720
1471.55 86.440 85.59 0.850
Total 3707.970
Total 7591.288
Earthwork from structures
Backfilling of structures
Excess earthwork from structures available for dikes
Earthwork required from borrow pit
Quantity ( Bd+sd^2)*L
Filling (m3)
4062.25
3984.67
4474.55
4618.56
899.57

18039.60

Quantity ( Bd+sd^2)*L
Filling (m3)

0.000

Quantity ( Bd+sd^2)*L
Filling (m3)

0.000

Quantity ( Bd+sd^2)*L
Filling (m3)
4632.39
4563.44
4687.91
5423.84
5238.65
4406.75
4447.37
4515.47
4584.07
4597.85
4319.36
4232.81
4332.75
4346.16
4272.65
4299.31
4386.51
4440.59
5201.99
5187.36
4584.07
4828.11
4941.71
4821.05
4542.85
5180.05
5935.55
5612.15
7308.71
3168.70

143040.18

Quantity ( Bd+sd^2)*L
Filling (m3)
3.328947368
2.28
1

6.006006006
0.000

Quantity ( Bd+sd^2)*L
Filling (m3)
3.328947368
2.28

176.250

6.006006006

5.006006006
176.250
161256.03
98803.694
9880.369
88923.325
64741.42
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

DETAIL QUANTITY OF TURFING


Dyke 1
Right side s=2
R.L of Designed Mean ht. Width of turfing Area of side slope at left
Chainage HT.diff Length(L)
Ground Levee El (dm) (dm*(1+s^2)^0.5) side (m2)
0 85.41 89.000 3.590
50 86.11 90.08 3.970 3.780 8.452 50 422.6
100 85.28 91.02 5.740 4.855 10.856 50 542.8
150 85.9 91.52 5.620 5.680 12.7 50 635
200 86.55 92.01 5.460 5.540 12.387 50 619.35
214.57 88.81 92.17 3.360 4.410 9.861 14.57 143.67
Total 2363.42
Dyke 1
Left side s=2
R.L of Designed Mean ht. Width of turfing Area of side slope at left
Chainage HT.diff Length(L)
Ground Levee El (dm) (dm*(1+s^2)^0.5) side (m2)
0 86.62 89.000 2.380
50 87.71 90.08 2.370 2.375 5.31 50 265.5
100 88.68 91.02 2.340 2.355 5.265 50 263.25
150 89.18 91.52 2.340 2.340 5.232 50 261.6
200 89.68 92.01 2.330 2.335 5.221 50 261.05
214.57 89.81 92.17 2.360 2.345 5.243 14.57 76.39
Total 1127.79

Dyke 2
Right side s=2
R.L of Designed Mean ht. Width of turfing Area of side slope at left
Chainage HT.diff Length(L)
Ground Levee El (dm) (dm*(1+s^2)^0.5) side (m2)
0 85.2 91.310 6.110
50 85.81 91.36 5.550 5.830 13.036 50 651.8
100 85.84 91.41 5.570 5.560 12.432 50 621.6
150 85.58 91.44 5.860 5.715 12.779 50 638.95
200 85.32 91.5 6.180 6.020 13.461 50 673.05
250 85.88 91.55 5.670 5.925 13.248 50 662.4
300 86.15 91.59 5.440 5.555 12.421 50 621.05
350 85.99 91.64 5.650 5.545 12.398 50 619.9
400 86.08 91.69 5.610 5.630 12.589 50 629.45
450 86.08 91.73 5.650 5.630 12.589 50 629.45
500 86.27 91.78 5.510 5.580 12.477 50 623.85
550 86.58 91.82 5.240 5.375 12.018 50 600.9
600 86.48 91.88 5.400 5.320 11.895 50 594.75
650 86.48 91.92 5.440 5.420 12.119 50 605.95
700 86.42 91.98 5.560 5.500 12.298 50 614.9
750 86.41 92.01 5.600 5.580 12.477 50 623.85
800 86.51 92.07 5.560 5.580 12.477 50 623.85
850 86.55 92.11 5.560 5.560 12.432 50 621.6
900 86.43 92.15 5.720 5.640 12.611 50 630.55
950 86.62 93.21 6.590 6.155 13.762 50 688.1
1000 86.78 92.25 5.470 6.030 13.483 50 674.15
1050 86.8 92.3 5.500 5.485 12.264 50 613.2
1100 86.56 92.35 5.790 5.645 12.622 50 631.1
1150 86.39 92.39 6.000 5.895 13.181 50 659.05
1200 86.81 92.45 5.640 5.820 13.013 50 650.65
1250 87.18 92.49 5.310 5.475 12.242 50 612.1
1300 86.71 92.52 5.810 5.560 12.432 50 621.6
1350 86.51 92.58 6.070 5.940 13.282 50 664.1
1400 86.23 92.62 6.390 6.230 13.93 50 696.5
1450 84.52 92.68 8.160 7.275 16.267 50 813.35
1471.55 86.12 92.7 6.580 7.370 16.479 21.55 355.12
Total 18966.87

Dyke 2
Left side s=2
R.L of Designed Mean ht. Width of turfing Area of side slope at left
Chainage HT.diff Length(L)
Ground Levee El (dm) (dm*(1+s^2)^0.5) side (m2)
0 88.51 91.310 2.800
50 88.58 91.36 2.780 2.790 6.238 50 311.9
100 88.61 91.41 2.800 2.790 6.238 50 311.9
150 88.68 91.44 2.760 2.780 6.216 50 310.8
200 88.71 91.5 2.790 2.775 6.205 50 310.25
250 88.78 91.55 2.770 2.780 6.216 50 310.8
300 88.81 91.59 2.780 2.775 6.205 50 310.25
350 88.85 91.64 2.790 2.785 6.227 50 311.35
400 88.9 91.69 2.790 2.790 6.238 50 311.9
450 88.93 91.73 2.800 2.795 6.249 50 312.45
500 89 91.78 2.780 2.790 6.238 50 311.9
550 89.03 91.82 2.790 2.785 6.227 50 311.35
600 89.04 91.88 2.840 2.815 6.294 50 314.7
650 89.12 91.92 2.800 2.820 6.305 50 315.25
700 89.19 91.98 2.790 2.795 6.249 50 312.45
750 89.21 92.01 2.800 2.795 6.249 50 312.45
800 89.29 92.07 2.780 2.790 6.238 50 311.9
850 89.33 92.11 2.780 2.780 6.216 50 310.8
900 89.38 92.15 2.770 2.775 6.205 50 310.25
950 90.41 93.21 2.800 2.785 6.227 50 311.35
1000 89.48 92.25 2.770 2.785 6.227 50 311.35
1050 89.5 92.3 2.800 2.785 6.227 50 311.35
1100 89.55 92.35 2.800 2.800 6.26 50 313
1150 89.61 92.39 2.780 2.790 6.238 50 311.9
1200 89.65 92.45 2.800 2.790 6.238 50 311.9
1250 89.71 92.49 2.780 2.790 6.238 50 311.9
1300 89.75 92.52 2.770 2.775 6.205 50 310.25
1350 89.8 92.58 2.780 2.775 6.205 50 310.25
1400 89.85 92.62 2.770 2.775 6.205 50 310.25
1450 89.88 92.68 2.800 2.785 6.227 50 311.35
1471.55 89.91 92.7 2.790 2.795 6.249 21.55 134.67
Total 9172.170
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

QUANTITY COMPUTATION OF REINFORCEMENT


Diameter
S.N Item Code Detail Length
(mm)
1 Pier
Circumference Bars 12 25.454
Vertical Bars (Both Faces around circumference) 16 7.095
Development length (vertical,Top & Bottom) 16 0.8
Development length (Horizontal both sides) 12 0.6
Hooks 10 1.926

2 Abutment & Wing Wall


Base of Wing Wall U/s ( Horizontal bars, Both faces , left & Right sides) 12 22.7
Base of Wing Wall U/s (Vertical bars, Both faces , left & Right sides) 20 5.2
Hooks 10 1.762
Development length Wing Wall U/s, ( Horizontal bars, Both faces , left & Right sides) 12 0.6
Development length Wing Wall U/s, ( Vertical bars, Both faces , left & Right sides) 20 1
Base of Wing Wall D/s ( Horizontal bars, Both faces , left & Right sides) 12 8.81
Base of Wing Wall D/s (Vertical bars, Both faces , left & Right sides) 20 5.2
Development length Wing Wall U/s, ( Horizontal bars, Both faces , left & Right sides) 12 0.6
Development length Wing Wall U/s, ( Vertical bars, Both faces , left & Right sides) 20 1
Hooks 10 1.762
Base of Wing Wall D/s ( Horizontal bars, Both faces , left & Right sides) 12 5.2
Base of Wing Wall D/s (Vertical bars, Both faces , left & Right sides) 20 2
Development length Wing Wall U/s, ( Horizontal bars, Both faces , left & Right sides) 12 0.6
Development length Wing Wall U/s, ( Vertical bars, Both faces , left & Right sides) 20 1
Hooks 10 1.762
Horizontal Bars ( Abutment),Both faces (Left & Right) 12 10
Vertical Bars ( Abutment),Both faces (Left & Right) 16 8.335
Hooks 10 2.128
Horizontal Bars ( Abutment),Both faces (Left & Right) 12 35.9
Vertical Bars ( Abutment),Both faces (Left & Right) 16 8.335
Hooks 10 2.128
Horizontal Bars (Wing Wall),Both faces (Left & Right) 12 8.201
Vertical Bars (Wing Wall),Both faces (Left & Right) 16 6.93
Hooks 10 1.762
Horizontal Bars (Wing Wall),Both faces (Left & Right) 12 8.201
Vertical Bars (Wing Wall),Both faces (Left & Right) 16 9.74
Hooks 10 2.128
Development length ,Vertical Bars ( Abutment),Both faces (Left & Right) 16 0.8
Development length ,Vertical Bars ( Abutment),Both faces (Left & Right) 16 0.8
Development length ,Vertical Bars (Wing Walls),Both faces (Left & Right) 16 0.8
Development length ,Vertical Bars (Wing Walls),Both faces (Left & Right) 16 0.8
Development length ,Horizontal Bars ( Abutment),Both faces (Left & Right) 12 0.6
Development length ,Horizontal Bars ( Abutment),Both faces (Left & Right) 12 0.6
Development length ,Horizontal Bars ( Abutment),Both faces (Left & Right) 12 0.6
Development length ,Horizontal Bars ( Abutment),Both faces (Left & Right) 12 0.6

3 Divide Wall
Horizontal Bars (Both sides) ,3Nos 12 76.858
Vertical Bars (Both sides) ,3Nos 16 8.335
Hooks 10 2.128
Development length ,Vertical Bars ,Both faces (3Nos) 16 0.8
Development length ,Horizontal Bars ,Both faces (3Nos) 12 0.6

4 Barrage Base Portion


U/s Base (X-direction),Both Faces,Straight Throughout 20 206
Ld 20 1
U/s Base (X-direction),Both Faces curtail 20 134.4
Ld 20 1
U/s Base (X-direction),Both Faces Curtail Bend 20 0.3
Ld 20 1
Hooks 10 2.128
U/s Base (Y-direction),One face 16 10
Development length ,Y-direction ,One Face 16 0.8
U/s Base (Y-direction),One face 16 9.161
U/s Base (Y-direction) 16 1.535
U/s Base (Y-direction) 16 3.212
U/s Base (Y-direction) 16 1.05
Middle Portion (X-direction), Both Faces,Straight Throughout 20 206
Ld 20 1
Middle Portion (X-direction),Both Faces curtail 20 134.4
Ld 20 1
Middle Portion(X-direction),Both Faces Curtail Bend 20 0.3
Ld 20 1
Hooks 10 2.128
Middle Portion Barrage (Y-direction),One Face 16 12.693
Development length ,Y-direction ,One Face 16 0.8
Middle Portion Barrage (Y-direction),One Face 16 9.433
Development length ,Y-direction ,One Face 16 0.8
Middle Portion Barrage (Y-direction),One Face 16 3.897
Development length ,Y-direction ,One Face 16 0.8
Middle Portion Barrage (Y-direction),One Face 16 2.865
D/s Base (X-direction),Both Faces,Straight Throughout 20 206
Ld 20 1
D/s Base (X-direction),Both Faces curtail 20 134.4
Ld 20 1
D/s Base(X-direction),Both Faces Curtail Bend 20 0.3
Ld 20 1
Hooks 10 2.128
D/s Base (Y-direction),Both Faces 16 17.532
Development length ,Y-direction ,Both Faces 16 0.8
D/s Base (Y-direction) 16 1.228
D/s Base (Y-direction) 16 3.131
D/s Base (Y-direction) 16 2.863

5 Undersluice Base Portion (Left)


U/s Base (X-direction),Both Faces,Straight Throughout 20 38.387
Ld 20 1
U/s Base (X-direction),Top Face curtail 20 8.221
Ld 20 1
U/s Base (X-direction),Top Face Curtail Bend 20 0.3
U/s Base (X-direction),Bottom Face curtail (Sides) 20 6.383
Ld 20 1
U/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
U/s Base (X-direction),Bottom Face curtail (Middle) 20 8.4
Ld 20 1
U/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
Hooks 10 1.762
U/s Base (Y-direction),One face 16 9.596
Development length ,Y-direction ,One Face 16 0.8
U/s Base (Y-direction) 16 1.704
U/s Base (Y-direction),One face 16 8.73
U/s Base (Y-direction) 16 3.02
U/s Base (Y-direction) 16 1.11
Middle Portion (X-direction), Both Faces,Straight Throughout 20 38.387
Ld 20 1
Middle Portion (X-direction),Top Face curtail 20 8.221
Ld 20 1
Middle Portion (X-direction) Face Curtail Bend 20 0.3
Middle Portion (X-direction),Bottom Face curtail (Sides) 20 6.383
Ld 20 1
Middle Portion (X-direction),Bottom Face Curtail Bend 20 0.3
Middle Portion (X-direction),Bottom Face curtail (Middle) 20 8.4
Ld 20 1
Middle Portion (X-direction),Bottom Face Curtail Bend 20 0.3
Hooks 10 1.762
Middle Portion (Y-direction),One Face 16 14.464
Development length ,Y-direction ,One Face 16 0.8
Middle Portion (Y-direction),One Face 16 3.714
Development length ,Y-direction ,One Face 16 0.8
Middle Portion (Y-direction),One Face 16 9.965
Development length ,Y-direction ,One Face 16 0.8
D/s Base (X-direction),Both Faces,Straight Throughout 20 38.387
Ld 20 1
D/s Base (X-direction),Top Face curtail 20 8.221
Ld 20 1
D/s Base(X-direction),Top Face Curtail Bend 20 0.3
D/s Base (X-direction),Bottom Face curtail (Sides) 20 6.383
Ld 20 1
D/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
D/s Base (X-direction),Bottom Face curtail (Middle) 20 8.4
Ld 20 1
D/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
Hooks 10 1.762
D/s Base (Y-direction),Both Faces 16 18.607
Development length ,Y-direction ,Both Faces 16 0.8
D/s Base (Y-direction) 16 3.057
Ld 16 0.8
D/s Base (Y-direction) 16 2.863
Ld 16 0.8

6 Undersluice Base Portion (Right)


U/s Base (X-direction),Both Faces,Straight Throughout 20 38.387
Ld 20 1
U/s Base (X-direction),Top Face curtail 20 8.221
Ld 20 1
U/s Base (X-direction),Top Face Curtail Bend 20 0.3
U/s Base (X-direction),Bottom Face curtail (Sides) 20 6.383
Ld 20 1
U/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
U/s Base (X-direction),Bottom Face curtail (Middle) 20 8.4
Ld 20 1
U/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
Hooks 10 1.762
U/s Base (Y-direction),One face 16 9.596
Development length ,Y-direction ,One Face 16 0.8
U/s Base (Y-direction) 16 1.704
U/s Base (Y-direction),One face 16 8.73
U/s Base (Y-direction) 16 3.02
U/s Base (Y-direction) 16 1.11
Middle Portion (X-direction), Both Faces,Straight Throughout 20 38.387
Ld 20 1
Middle Portion (X-direction),Top Face curtail 20 8.221
Ld 20 1
Middle Portion (X-direction) Face Curtail Bend 20 0.3
Middle Portion (X-direction),Bottom Face curtail (Sides) 20 6.383
Ld 20 1
Middle Portion (X-direction),Bottom Face Curtail Bend 20 0.3
Middle Portion (X-direction),Bottom Face curtail (Middle) 20 8.4
Ld 20 1
Middle Portion (X-direction),Bottom Face Curtail Bend 20 0.3
Hooks 10 1.762
Middle Portion (Y-direction),One Face 16 14.464
Development length ,Y-direction ,One Face 16 0.8
Middle Portion (Y-direction),One Face 16 3.714
Development length ,Y-direction ,One Face 16 0.8
Middle Portion (Y-direction),One Face 16 9.965
Development length ,Y-direction ,One Face 16 0.8
D/s Base (X-direction),Both Faces,Straight Throughout 20 38.387
Ld 20 1
D/s Base (X-direction),Top Face curtail 20 8.221
Ld 20 1
D/s Base(X-direction),Top Face Curtail Bend 20 0.3
D/s Base (X-direction),Bottom Face curtail (Sides) 20 6.383
Ld 20 1
D/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
D/s Base (X-direction),Bottom Face curtail (Middle) 20 8.4
Ld 20 1
D/s Base (X-direction),Bottom Face Curtail Bend 20 0.3
Hooks 10 1.762
D/s Base (Y-direction),Both Faces 16 18.607
Development length ,Y-direction ,Both Faces 16 0.8
D/s Base (Y-direction) 16 3.057
Ld 16 0.8
D/s Base (Y-direction) 16 2.863
Ld 16 0.8

7 Wester Main Canal


Horizontal Bars,Both faces,2 sides (U/s Top of Base) 16 3
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces ,2 sides(U/s Top of Base) 20 5.695
Development length (vertical,Top) 20 1
Horizontal Bars,Both faces ,2 sides(Top of weir) 16 1.5
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (Top of weir) 20 3.86
Development length (Top of weir) 20 1
Horizontal Bars,Both faces,2 sides (Inclined Portion) 16 3.828
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (Inclined Portion) 20 4.5
Development length (Inclined Portion) 20 1
Horizontal Bars,Both faces,2 sides (D/s base) 16 2.4
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (D/s base) 20 5.16
Development length (vertical,Top) 20 1
Horizontal Bars,Both faces,2 sides ( Steps) 16 0.8
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides ( Steps) 20 3.564
Development length( Steps) 20 1
Horizontal Bars,Both faces,2 sides ( Steps) 16 0.8
Hooks 10 2.128
Ld 16 0.8
Vertical Bars ,Both faces,2 sides ( Steps) 20 3.032
Development length( Steps) 20 1
Horizontal Bars,Both faces,2 sides (D/s base) 16 1.784
Hooks 10 2.128
Ld 16 0.8
Vertical Bars ,Both faces,2 sides (D/s base) 20 2.5
Development length (vertical,Top) 20 1
Horizontal Bars,Both faces,2 sides (Inclined Portion) 16 1.154
Hooks 10 2.128
Ld 16 0.8
Vertical Bars ,Both faces,2 sides (Inclined Portion) 20 2.092
Development length (Inclined Portion) 20 1
Horizontal Bars,Both faces,2 sides (D/s base) 16 0.4
Hooks 10 2.128
Ld 16 0.8
Vertical Bars ,Both faces,2 sides (D/s base) 20 1.684
Development length (vertical,Top) 20 1
X-Direction,Both faces (U/s base) 16 5.9
Ld 16 0.8
Hooks 10 1.417
Y-Direction ,Both faces (U/s base) 16 4.2
Development length (Y-direction,Top) 16 0.8
Horizontal Bars,Both faces (Base of weir) 12 5.9
Hooks 10 1.417
Ld 16 0.8
Top & Bottom Bars ,Both faces (Base of weir) 10 5.9
Sides bars,Both faces (Base of weir) 12 5.9
Stirrups 12 7.598
X-Direction,Both faces (Inclined Portion) 16 5.9
Ld 16 0.8
Hooks 10 1.417
Y-Direction ,Both faces(Inclined Portion) 16 5.846
Development length (Y-direction,Top) 16 0.8
X-Direction,Both faces (Base Portion) 16 5.9
Ld 16 0.8
Hooks 10 1.417
Y-Direction ,Both faces(Base Portion) 12 8.945
Development length (Y-direction,Top) 12 0.6
X-Direction, (Base Portion) 16 5.9
Ld 16 0.8
Hooks 10 1.417
Y-Direction ,Both faces(Base Portion) 12 1.52
Development length (Y-direction,Top) 12 0.6
Horizontal, (Base Portion) 12 5.9
Hooks 10 1.417
Ld 16 0.8
Y-Direction ,Both faces(Base Portion) 16 1.915
Development length (Y-direction,Top) 16 0.8
X-Direction,Both faces (Bridge) 10 5.9
Ld 16 0.8
Y-Direction ,Both faces (Bridge) Top 16 6
Development length (Bridge) 16 0.8
Y-Direction ,Both faces (Bridge) Bottom 20 6
Development length (Bridge) 20 1
Top & Bottom (Bridge sides) 12 5.9
Sides (Bridge sides) 8 5.9
Vertical (Bridge, Both faces) 8 0.85
Development length (Bridge) 8 0.4
Sides (Bridge) 16 0.763

7 Easter Main Canal


Horizontal Bars,Both faces,2 sides (U/s Top of Base) 16 3
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces ,2 sides(U/s Top of Base) 20 5.788
Development length (vertical,Top) 20 1
Horizontal Bars,Both faces ,2 sides(Top of weir) 16 1.5
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (Top of weir) 20 3.861
Development length (Top of weir) 20 1
Horizontal Bars,Both faces,2 sides (Inclined Portion) 16 2.773
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (Inclined Portion) 20 4.311
Development length (Inclined Portion) 20 1
Horizontal Bars,Both faces,2 sides (D/s base) 16 2.4
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (D/s base) 20 5.06
Development length (vertical,Top) 20 1
Horizontal Bars,Both faces,2 sides ( Steps) 16 0.8
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides ( Steps) 20 3.464
Development length( Steps) 20 1
Horizontal Bars,Both faces,2 sides ( Steps) 16 0.8
Hooks 10 2.128
Ld 16 0.8
Vertical Bars ,Both faces,2 sides ( Steps) 20 2.932
Development length( Steps) 20 1
Horizontal Bars,Both faces,2 sides (D/s base) 16 1.884
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (D/s base) 20 2.4
Development length (vertical,Top) 20 1
Horizontal Bars,Both faces,2 sides (Inclined Portion) 16 1.013
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (Inclined Portion) 20 2.042
Development length (Inclined Portion) 20 1
Horizontal Bars,Both faces,2 sides (D/s base) 16 0.4
Ld 16 0.8
Hooks 10 2.128
Vertical Bars ,Both faces,2 sides (D/s base) 20 1.684
Development length (vertical,Top) 20 1
X-Direction,Both faces (U/s base) 16 6.4
Ld 16 0.8
Hooks 10 1.465
Y-Direction ,Both faces (U/s base) 16 4.2
Development length (Y-direction,Top) 16 0.8
Horizontal Bars,Both faces (Base of weir) 12 6.4
Ld 16 0.8
Hooks 10 1.465
Top & Bottom Bars ,Both faces (Base of weir) 10 6.4
Stirrups 12 7.35
X-Direction,Both faces (Inclined Portion) 16 6.4
Ld 16 0.8
Hooks 10 1.465
Y-Direction ,Both faces(Inclined Portion) 16 4.766
Development length (Y-direction,Top) 16 0.8
X-Direction,Both faces (Base Portion) 16 6.4
Ld 16 0.8
Hooks 10 1.465
Y-Direction ,Both faces(Base Portion) 12 9.01
Development length (Y-direction,Top) 12 0.6
X-Direction, (Base Portion) 16 6.4
Ld 16 0.8
Hooks 10 1.465
Y-Direction ,Both faces(Base Portion) 12 1.73
Development length (Y-direction,Top) 12 0.6
Horizontal, (Base Portion) 12 6.4
Ld 16 0.8
Hooks 10 1.465
Y-Direction ,Both faces(Base Portion) 16 1.915
Development length (Y-direction,Top) 16 0.8
X-Direction,Both faces (Bridge) 10 6.4
Y-Direction ,Both faces (Bridge) Top 16 6
Development length (Bridge) 16 0.8
Y-Direction ,Both faces (Bridge) Bottom 20 6
Development length (Bridge) 20 1
Top & Bottom (Bridge sides) 12 6.4
Sides (Bridge sides) 8 6.4
Vertical (Bridge, Both faces) 8 0.85
Development length (Bridge) 8 0.4
Sides (Bridge) 16 0.763

8 Main Bridge (19 Spans)


Main Girder (2nos)
Continous Throughout Main Girder (g1,g2) 32 257.64
Ld Continous Throughout Main Girder (g1,g2) 32 30.4
Spacer Bars 32 0.3
g3 (2 straight) 32 235.6
Curtail Bend 32 6.688
g3 (2 curtail) 32 272.08
Spacer Bars 32 0.3
Ld Continous Throughout Main Girder (g3) 32 30.4
g4 32 110.2
Curtail Bend 32 6.688
Spacer Bars 32 0.3
Side Bars Continous Throughout Main Girder 10 257.64
Ld Continous Throughout Main Girder 10 9.5
g5 Continous Throughout Main Girder 20 257.64
Ld Continous Throughout Main Girder 20 19
Stirrups (gs3) 10 2.817
Cross Girder (76 nos)
Continous Throughout Cross Girder (cg5,cg6,cg8&cg7) 16 159.6
Ld Continous Throughout Cross Girder 16 60.8
Spacer Bars (1 layers) top & bottom 16 0.198
Side Bars Continous Throughout Cross Girder 12 159.6
Ld Continous Throughout Cross Girder 12 45.6
Strirrups (Cs1) 10 1.899
Main Bridge
Horizontal Bars Top S7 10 257.64
Ld 10 0.5
Horizontal Bars Bottom S2 10 257.64
Ld 10 0.5
Y-Direction S5 12 4.7
Ld 12 0.6
Y-Direction S1 12 3.4
Ld 12 0.6
Top curtail (Y directon) 12 3.68
Side of Bridge (Both sides) 10 3.66
Side Inclined ( Y- direction both sides) 10 257.64
Sides ( Y- direction both sides) 12 257.64
4.1 Total

9 Channel Section
Bridge
Head Regulator
Head Regulator
11.1 Total
Total No of Total Shape
Lap Length weight/m Remarks
Length bars weight (kg) Code

3 28.454 855 0.888 21603.41 C1


1.6 8.695 3610 1.578 49531.76 V1
0 1.6 3610 1.578 9114.53 Ld
0 1.2 855 0.888 911.09 Ld
0 1.926 8550 0.617 10160.32 H2

2.4 25.1 108 0.888 2407.19 H1


0 5.2 672 2.466 8617.19 V1
0 1.762 918 0.617 998.01 H2
0 1.2 108 0.888 115.08 Ld
0 2 672 2.466 3314.3 Ld
1.2 10.01 108 0.888 960 H1
0 5.2 268 2.466 3436.62 V1
0 1.2 108 0.888 115.08 Ld
0 2 268 2.466 1321.78 Ld
0 1.762 378 0.617 410.94 H2
0 5.2 44 0.888 203.17 H1
0 2 140 2.466 690.48 V1
0 1.2 44 0.888 46.89 Ld
0 2 140 2.466 690.48 Ld
0 1.762 110 0.617 119.59 H2
1.2 11.2 204 0.888 2028.9 H1
1.6 9.935 300 1.578 4703.23 V1
0 2.128 816 0.617 1071.39 H2
3.6 39.5 204 0.888 7155.5 H1
1.6 9.935 1056 1.578 16555.37 V1
0 2.128 2550 0.617 3348.09 H2
1.2 9.401 176 0.888 1469.26 H1
1.6 8.53 252 1.578 3392.01 V1
0 1.762 616 0.617 669.69 H2
1.2 9.401 232 0.888 1936.76 H1
1.6 11.34 252 1.578 4509.42 V1
0 2.128 812 0.617 1066.14 H2
0 1.6 300 1.578 757.44 Ld
0 1.6 1056 1.578 2666.19 Ld
0 1.6 252 1.578 636.25 Ld
0 1.6 252 1.578 636.25 Ld
0 1.2 204 0.888 217.38 Ld
0 1.2 204 0.888 217.38 Ld
0 1.2 176 0.888 187.55 Ld
0 1.2 232 0.888 247.22 Ld

7.8 84.658 153 0.888 11501.97 C1


1.6 9.935 1695 1.578 26573.24 V1
0 2.128 8109 0.617 10646.92 H2
0 1.6 1695 1.578 4279.54 Ld
0 1.2 153 0.888 163.04 Ld

35 241 40 2.466 23772.24 H1


0 2 40 2.466 197.28 Ld
23 157.4 40 2.466 15525.94 H1
0 2 40 2.466 197.28 Ld
0 8.4 40 2.466 828.58 A4
0 2 40 2.466 197.28 Ld
0 2.128 8201 0.617 10767.72 H2
1.6 11.6 1206 1.578 22075.59 Y1
0 1.6 1206 1.578 3044.91 Ld
1.6 10.761 1206 1.578 20478.91 H1
0 1.535 1206 1.578 2921.21 A1
0 3.212 1206 1.578 6112.65 A2
0 1.05 1206 1.578 1998.22 S1
35 241 52 2.466 30903.91 H1
0 2 52 2.466 256.46 Ld
23 157.4 52 2.466 20183.72 H1
0 2 52 2.466 256.46 Ld
0 8.4 52 2.466 1077.15 A4
0 2 52 2.466 256.46 Ld
0 2.128 10703 0.617 14052.78 H2
2.4 15.093 1206 1.578 28723.01 A3
0 1.6 1206 1.578 3044.91 Ld
1.6 11.033 1206 1.578 20996.55 H1
0 0.8 1206 1.578 1522.45 Ld
0 3.897 1206 1.578 7416.26 H1
0 0.8 1206 1.578 1522.45 Ld
0 2.865 1206 1.578 5452.29 A2
35 241 68 2.466 40412.81 H1
0 2 68 2.466 335.38 Ld
23 157.4 68 2.466 26394.09 H1
0 2 68 2.466 335.38 Ld
0 8.4 68 2.466 1408.58 A4
0 2 68 2.466 335.38 Ld
0 2.128 14039 0.617 18432.87 H2
2.4 19.932 2412 1.578 75863.9 Y2
0 1.6 2412 1.578 6089.82 Ld
0 1.228 1206 1.578 2336.97 S1
0 3.131 1206 1.578 5958.51 A1
0 2.863 1206 1.578 5448.48 A1

7 45.387 39 2.466 4365.05 H1


0 2 39 2.466 192.35 Ld
2 20.442 19.5 2.466 982.99 H1
0 2 19.5 2.466 96.17 Ld
0 1.2 19.5 2.466 57.7 A4
2 16.766 19.5 2.466 806.23 H1
0 2 19.5 2.466 96.17 Ld
0 0.6 19.5 2.466 28.85 A4
2 20.8 19.5 2.466 1000.21 H1
0 2 19.5 2.466 96.17 Ld
0 0.6 19.5 2.466 28.85 A4
0 1.762 1539 0.617 1673.13 H2
1.6 11.196 227 1.578 4010.47 Y1
0 1.6 227 1.578 573.13 Ld
0 1.704 227 1.578 610.38 A1
1.6 10.33 227 1.578 3700.27 H1
0 3.02 227 1.578 1081.78 A2
0 1.11 227 1.578 397.61 S1
7 45.387 58 2.466 6491.61 H1
0 2 58 2.466 286.06 Ld
2 20.442 29 2.466 1461.89 H1
0 2 29 2.466 143.03 Ld
0 1.2 29 2.466 85.82 A4
2 16.766 29 2.466 1199 H1
0 2 29 2.466 143.03 Ld
0 0.6 29 2.466 42.91 A4
2 20.8 29 2.466 1487.49 H1
0 2 29 2.466 143.03 Ld
0 0.6 29 2.466 42.91 A4
0 1.762 2322 0.617 2524.37 H2
2.4 16.864 227 1.578 6040.79 Y2
0 1.6 227 1.578 573.13 Ld
0 3.714 227 1.578 1330.38 H1
0 0.8 227 1.578 286.56 Ld
1.6 11.565 227 1.578 4142.65 H1
0 0.8 227 1.578 286.56 Ld
7 45.387 74 2.466 8282.4 H1
0 2 74 2.466 364.97 Ld
2 20.442 37 2.466 1865.17 H1
0 2 37 2.466 182.48 Ld
0 1.2 37 2.466 109.49 A4
2 16.766 37 2.466 1529.76 H1
0 2 37 2.466 182.48 Ld
0 0.6 37 2.466 54.75 A4
2 20.8 37 2.466 1897.83 H1
0 2 37 2.466 182.48 Ld
0 0.6 37 2.466 54.75 A4
0 1.762 2997 0.617 3258.2 H2
3.2 21.807 454 1.578 15622.8 Y2
0 3.2 454 1.578 2292.52 Ld
0 3.057 227 1.578 1095.04 A1
0 1.6 227 1.578 573.13 Ld
0 2.852 227 1.578 1021.6 A1
0 1.6 227 1.578 573.13 Ld

7 45.387 39 2.466 4365.05 H1


0 2 39 2.466 192.35 Ld
2 20.442 19.5 2.466 982.99 H1
0 2 19.5 2.466 96.17 Ld
0 1.2 19.5 2.466 57.7 A4
2 16.766 19.5 2.466 806.23 H1
0 2 19.5 2.466 96.17 Ld
0 0.6 19.5 2.466 28.85 A4
2 20.8 19.5 2.466 1000.21 H1
0 2 19.5 2.466 96.17 Ld
0 0.6 19.5 2.466 28.85 A4
0 1.762 1539 0.617 1673.13 H2
1.6 11.196 227 1.578 4010.47 Y1
0 1.6 227 1.578 573.13 Ld
0 1.704 227 1.578 610.38 A1
1.6 10.33 227 1.578 3700.27 H1
0 3.02 227 1.578 1081.78 A2
0 1.11 227 1.578 397.61 S1
7 45.387 58 2.466 6491.61 H1
0 2 58 2.466 286.06 Ld
2 20.442 29 2.466 1461.89 H1
0 2 29 2.466 143.03 Ld
0 1.2 29 2.466 85.82 A4
2 16.766 29 2.466 1199 H1
0 2 29 2.466 143.03 Ld
0 0.6 29 2.466 42.91 A4
2 20.8 29 2.466 1487.49 H1
0 2 29 2.466 143.03 Ld
0 0.6 29 2.466 42.91 A4
0 1.762 2322 0.617 2524.37 H2
2.4 16.864 227 1.578 6040.79 Y2
0 1.6 227 1.578 573.13 Ld
0 3.714 227 1.578 1330.38 H1
0 0.8 227 1.578 286.56 Ld
1.6 11.565 227 1.578 4142.65 H1
0 0.8 227 1.578 286.56 Ld
7 45.387 74 2.466 8282.4 H1
0 2 74 2.466 364.97 Ld
2 20.442 37 2.466 1865.17 H1
0 2 37 2.466 182.48 Ld
0 1.2 37 2.466 109.49 A4
2 16.766 37 2.466 1529.76 H1
0 2 37 2.466 182.48 Ld
0 0.6 37 2.466 54.75 A4
2 20.8 37 2.466 1897.83 H1
0 2 37 2.466 182.48 Ld
0 0.6 37 2.466 54.75 A4
0 1.762 2997 0.617 3258.2 H2
3.2 21.807 454 1.578 15622.8 Y2
0 3.2 454 1.578 2292.52 Ld
0 3.057 227 1.578 1095.04 A1
0 1.6 227 1.578 573.13 Ld
0 2.852 227 1.578 1021.6 A1
0 1.6 227 1.578 573.13 Ld

0 3 156 1.578 738.5 V2


0 1.6 156 1.578 393.87 Ld
0 2.128 180 0.617 236.34 H2
0 5.695 84 2.466 1179.69 V2
0 1 84 2.466 207.14 Ld
0 1.5 108 1.578 255.64 V2
0 1.6 108 1.578 272.68 Ld
0 2.128 84 0.617 110.29 H2
0 3.86 44 2.466 418.83 V2
0 1 44 2.466 108.5 Ld
0 3.828 124 1.578 749.03 V2
0 1.6 124 1.578 313.08 Ld
0 2.128 192 0.617 252.09 H2
0 4.5 108 2.466 1198.48 V2
0 1 108 2.466 266.33 Ld
0 2.4 144 1.578 545.36 V2
0 1.6 144 1.578 363.57 Ld
0 2.128 162 0.617 212.7 H2
0 5.16 68 2.466 865.27 V2
0 1 68 2.466 167.69 Ld
0 0.8 100 1.578 126.24 V2
0 1.6 100 1.578 252.48 Ld
0 2.128 76 0.617 99.79 H2
0 3.564 28 2.466 246.09 V2
0 1 28 2.466 69.05 Ld
0 0.8 88 1.578 111.09 V2
0 2.128 68 0.617 89.28 H2
0 1.6 68 1.578 171.69 Ld
0 3.032 28 2.466 209.35 V2
0 1 28 2.466 69.05 Ld
0 1.784 72 1.578 202.69 V2
0 2.128 84 0.617 110.29 H2
0 1.6 84 1.578 212.08 Ld
0 2.5 52 2.466 320.58 V2
0 1 52 2.466 128.23 Ld
0 1.154 60 1.578 109.26 V2
0 2.128 48 0.617 63.02 H2
0 1.6 48 1.578 121.19 Ld
0 2.092 36 2.466 185.72 V2
0 1 36 2.466 88.78 Ld
0 0.4 52 1.578 32.82 V2
0 2.128 40 0.617 52.52 H2
0 1.6 40 1.578 100.99 Ld
0 1.684 16 2.466 66.44 V2
0 1 16 2.466 39.46 Ld
0 5.9 56 1.578 521.37 H1
0 1.6 56 1.578 141.39 Ld
0 1.417 110 0.617 96.17 H2
0 4.2 76 1.578 503.7 V1
0 3.2 76 1.578 383.77 Ld
0 5.9 42 0.888 220.05 H1
0 1.417 140 0.617 122.4 H2
0 1.6 140 1.578 353.47 Ld
0 5.9 6 0.617 21.84 H1
0 5.9 42 0.888 220.05 H1
1.2 8.798 21 0.888 164.07 S2
0 5.9 76 1.578 707.58 H1
0 1.6 76 1.578 191.88 Ld
0 1.417 155 0.617 135.51 H2
0 5.846 76 1.578 701.1 I1
0 0.8 76 1.578 95.94 Ld
0 5.9 104 1.578 968.26 H1
0 1.6 104 1.578 262.58 Ld
0 1.417 260 0.617 227.32 H2
1.2 10.145 82 0.888 738.72 Y2
0 1.2 82 0.888 87.38 Ld
0 5.9 9 1.578 83.79 H1
0 1.6 9 1.578 22.72 Ld
0 1.417 45 0.617 39.34 H2
0 1.52 41 0.888 55.34 Y2
0 0.6 41 0.888 21.84 Ld
0 5.9 28 0.888 146.7 H1
0 1.417 55 0.617 48.09 H2
0 1.6 55 1.578 138.86 Ld
0 1.915 62 1.578 187.36 V1
0 1.6 62 1.578 156.54 Ld
0 5.9 62 0.617 225.7 H1
0 1.6 62 1.578 156.54 Ld
0 6 31 1.578 293.51 V1
0 1.6 31 1.578 78.27 Ld
0 6 31 2.466 458.68 V1
0 2 31 2.466 152.89 Ld
0 5.9 8 0.888 41.91 H1
0 5.9 4 0.395 9.32 H1
0 0.85 124 0.395 41.63 V1
0 0.8 124 0.395 39.18 Ld
0 0.763 62 1.578 74.65 I3

0 3 160 1.578 757.44 V2


0 1.6 160 1.578 403.97 Ld
0 2.128 180 0.617 236.34 H2
0 5.788 84 2.466 1198.95 V2
0 1 84 2.466 207.14 Ld
0 1.5 108 1.578 255.64 V2
0 1.6 108 1.578 272.68 Ld
0 2.128 84 0.617 110.29 H2
0 3.861 44 2.466 418.93 V2
0 1 44 2.466 108.5 Ld
0 2.773 120 1.578 525.1 V2
0 1.6 120 1.578 302.98 Ld
0 2.128 138 0.617 181.19 H2
0 4.311 80 2.466 850.47 V2
0 1 80 2.466 197.28 Ld
0 2.4 140 1.578 530.21 V2
0 1.6 140 1.578 353.47 Ld
0 2.128 162 0.617 212.7 H2
0 5.06 68 2.466 848.5 V2
0 1 68 2.466 167.69 Ld
0 0.8 100 1.578 126.24 V2
0 1.6 100 1.578 252.48 Ld
0 2.128 76 0.617 99.79 H2
0 3.464 28 2.466 239.18 V2
0 1 28 2.466 69.05 Ld
0 0.8 84 1.578 106.04 V2
0 2.128 64 0.617 84.03 H2
0 1.6 64 1.578 161.59 Ld
0 2.932 28 2.466 202.45 V2
0 1 28 2.466 69.05 Ld
0 1.884 68 1.578 202.16 V2
0 1.6 68 1.578 171.69 Ld
0 2.128 78 0.617 102.41 H2
0 2.4 56 2.466 331.43 V2
0 1 56 2.466 138.1 Ld
0 1.013 60 1.578 95.91 V2
0 1.6 60 1.578 151.49 Ld
0 2.128 48 0.617 63.02 H2
0 2.042 32 2.466 161.14 V2
0 1 32 2.466 78.91 Ld
0 0.4 52 1.578 32.82 V2
0 1.6 52 1.578 131.29 Ld
0 2.128 40 0.617 52.52 H2
0 1.684 16 2.466 66.44 V2
0 1 16 2.466 39.46 Ld
1.6 8 56 1.578 706.94 H1
0 1.6 56 1.578 141.39 Ld
0 1.465 132 0.617 119.32 H2
0 4.2 82 1.578 543.46 V1
0 1.6 82 1.578 207.03 Ld
1.2 7.6 42 0.888 283.45 H1
0 1.6 42 1.578 106.04 Ld
0 1.465 126 0.617 113.89 H2
1 7.4 6 0.617 27.39 H1
1.2 8.55 23 0.888 174.63 S2
1.6 8 62 1.578 782.69 H1
0 1.6 62 1.578 156.54 Ld
0 1.465 150 0.617 135.59 H2
0 4.766 82 1.578 616.7 I1
0 0.8 82 1.578 103.52 Ld
1.6 8 94 1.578 1186.66 H1
0 1.6 94 1.578 237.33 Ld
0 1.465 282 0.617 254.9 H2
1.2 10.21 110 0.888 997.31 Y2
0 1.2 110 0.888 117.22 Ld
1.6 8 10 1.578 126.24 H1
0 1.6 10 1.578 25.25 Ld
0 1.465 60 0.617 54.23 H2
0 1.73 55 0.888 84.49 Y2
0 0.6 55 0.888 29.3 Ld
1.2 7.6 28 0.888 188.97 H1
0 1.6 28 1.578 70.69 Ld
0 1.465 66 0.617 59.66 H2
0 1.915 78 1.578 235.71 V1
0 1.6 78 1.578 196.93 Ld
1 7.4 62 0.617 283.08 H1
0 6 38 1.578 359.78 V1
0 1.6 38 1.578 95.94 Ld
0 6 38 2.466 562.25 V1
0 2 38 2.466 187.42 Ld
1.2 7.6 8 0.888 53.99 H1
0.8 7.2 4 0.395 11.38 H1
0 0.85 148 0.395 49.69 V1
0 0.8 148 0.395 46.77 Ld
0 0.763 74 1.578 89.1 I3

68.8 326.44 16 6.313 32973.05 H1


9.6 80 16 6.313 8080.64 Ld
0 0.3 3438 6.313 6511.23 H1
64 299.6 4 6.313 7565.5 H1
3.2 19.776 4 6.313 499.38 A4
73.6 345.68 4 6.313 8729.11 C4
0 0.3 2096 6.313 3969.61 H1
9.6 80 4 6.313 2020.16 Ld
30.4 140.6 8 6.313 7100.86 H1
3.2 19.776 8 6.313 998.77 A4
0 0.3 1472 6.313 2787.82 H1
21.5 279.14 12 0.617 2066.75 H1
1 21 12 0.617 155.48 Ld
43 300.64 6 2.466 4448.27 H1
4 46 6 2.466 680.62 Ld
0 2.817 3438 0.617 5975.55 S2

21.6 181.2 12 1.578 3431.2 H1


8.8 139.2 12 1.578 2635.89 Ld
0 0.198 2130 1.578 665.51 H1
16.2 175.8 6 0.888 936.66 H1
4.8 100.8 6 0.888 537.06 Ld
0 1.899 1065 0.617 1247.84 S2

21.5 279.14 17 0.617 2927.9 H1


0 1 17 0.617 10.49 Ld
21.5 279.14 13 0.617 2238.98 H1
0 1 13 0.617 8.02 Ld
0 4.7 1290 0.888 5383.94 V1
0 1.2 1290 0.888 1374.62 Ld
0 3.4 2578 0.888 7783.5 V1
0 1.2 2578 0.888 2747.12 Ld
0 3.68 1290 0.888 4215.51 T1
0 3.66 2580 0.617 5826.21 T2
21.5 279.14 16 0.617 2755.67 H1
25.8 283.44 12 0.888 3020.34 H1
1004813.3

0.5 516 5.7 1470.6 C3


0.5 13 5.7 37.05 C3
0.5 12 5.7 34.2 C3
1541.85
S.N Item Code Detail Unit No Length Breadth

1 Gates (Barrage)
I-Beams (Vertical) Kg 126 1.7
I-Beams (Horizontal) Kg 270 2
I-Beams (Horizontal) Kg 54 1.55
C-Section (Base of gate) Kg 90 2
C-Section (Base of gate) Kg 18 1.55
11.1 Total
C type steel plates at both sides (Barrage Gate) kg 36 1.5 0.04
Steel plates kg 18 12 0.01
Pulley plates (Circular) kg 36 0.1256 0.002
Pulley plates (Circular) kg 36 0.0314 0.002
Pulley plates (Triangular), both sides kg 72 0.0364 0.002
Pulley plates (Circular) kg 36 0.025434 0.002
Lifting chain kg 36 6.76 0.007
4.1 Total kg

2 Gate (Easter head regulator)


I-Beams (Vertical) Kg 3 1.7
I-Beams (Horizontal) Kg 4 0.85
C-Section (Base of gate) Kg 2 0.85
11.1 Total
C type steel plates at both sides (Barrage Gate) kg 2 0.97 0.03
Steel plates kg 1 2 0.01
Steel poles kg 2 0.001963 2.62
Steel poles kg 1 0.001963 2.98
4.1 Total kg

3 Gate (Waster head regulator)


I-Beams (Vertical) Kg 3 1.7
I-Beams (Horizontal) Kg 4 0.6
C-Section (Base of gate) Kg 2 0.6
11.1 Total
C type steel plates at both sides (Barrage Gate) kg 2 0.97 0.03
Steel plates kg 1 1.5 0.01
Steel poles kg 2 0.001963 2.62
Steel poles kg 1 0.001963 2.98
4.1 Total kg
Total weight Shape
Height weight/m Remarks
(Quantity,kg) Code

56.9 12187.98
56.9 30726
56.9 4762.53
49.4 8892
49.4 1378.26
57946.77
5.73 12.377
1.7 3.672
0.009
0.002
0.005
0.002
1.704
17.771
0.925

56.9 290.19 2.566875


56.9 193.46 1.602147
49.4 83.98
567.63
3.86 0.225 160
1.7 0.034 5796
0.01 34.99376 46368
0.006 35.99376 231840000
0.275

56.9 290.19
56.9 136.56
49.4 59.28
486.03
3.86 0.225
1.7 0.026
0.01
0.006
0.267
S. No. Item Code Item Unit Rate Quantity Amount
12 4.1 Reinforcement works kg 128.43 18.313 2,351.94
24 11.1 Channel fixing for bridge railing kg 207.44 59000.43 12,239,049.20
TOTAL 12,241,401.14
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

SUMMARY OF RATES
S. No. Item Code Description of Works Unit Rate
1 SITE CLEARANCE
Site clearance including cutting thin vegetation, grubbing their roots and
1 1.1 disposal, cutting, uprooting and disposal of grasses with light compaction
and clearing, removal of topsoil and disposal m2 42.12
2 EARTH WORK IN EXCAVATION/EMBANKMENT 0.00
Excavation of soft clay & silty soils including disposal up to 10 m lead &
2 2.1
1.5m lift) m3 456.03
Earthwork in filling with 15cm thick soil, including lead 10m & 1.5m lift &
3 2.2
manually compaction without sprinkle of water m3 162.87
Earthwork in filling with 15cm thick soil, including lead 10m & 1.5m lift &
4 2.3
manually compaction with sprinkle of water m3 325.74
Earthwork in excavation of foundation of structures, including
construction of soring and bracing, removal of stumps and other
5 2.4
deleterious matter and backfilling with approved Materials as per
drawing and technical specifications by mechanical means m3 114.76
Earthwork in excavation of foundation of structures, including
construction of soring and bracing, removal of stumps and other
6 2.5 deleterious matter and backfilling with approved Materials as per
drawing and technical specifications by mechanical means for marshy
land, including dewatering m3 716.10
Stripping and storing top soil: stripping, storing of top soil by road side at
15m interval and re-application on embankment slopes, cut slope and
7 2.6
other areas in localities where the available embankment materials is not
conducive to plant growth m3 163.32
Construction of Embankment with Material obtained from borrow pits:
8 2.7 providing, laying, spreading and compacting embankment with borrow
materials m3 469.26
Construction of Embankment with Material Deposited from Cutting by
9 2.8
mechanical means m3 298.66
3 CEMENT CONCRETE WORKS 0.00
Concreting of foundations, vertical faces, walls, Abutment in 1:3:6 (M10)
10 3.1 cement sand aggregate mix including supply of materials and haulage
distance upto 30m m3 12,082.41
Concreting of foundations, vertical faces, walls, in 1:2:4 (M15) PCC for
11 3.2 RCC, cement sand aggregate mix including supply of materials and
haulage distance upto 30m m3 14,034.90
Concreting of super structure, Vertical faces, Deck Slab, Beams, Walls
12 3.3 of ratio 1:1.5:3 (M20) including supply of materials and haulage distance
upto 30 m m3 17,697.75
Concreting of super structure, Vertical faces, Deck Slab, Beams, Walls
13 3.4 of ratio 1:1:2 (M25) including supply of materials and haulage distance
upto 30 m m3 18,040.19
4 REINFORCEMENT 0.00
Cutting , bending , placing in position and binding of reinforcement steel
14 4.1 bars as per the design/drawing for RCC works including haulage to 30m
distance. kg 128.43
5 FORMWORK 0.00
Making wooden forms including supply and selection of materials fixing,
15 5.1 nailing according to drawings, placing separators, dismantling forms and
hauling upto 30m distance m2 982.13
6 GABION WORKS & BOULDER FILLING WORKS 0.00
16 6.1 Boulder supply and filling into Gabion Boxes m3 3,521.93
Supplying of Machine made GI wire gabion Boxes of Mesh size
17 6.2 100mm*120mm with heavy coated GI wires (Mesh wire: 3mm, selvedge
wire 3.9mm and Lacing wire 2.4mm) - Size 2m X 1m X 1m No 3,667.17
Supplying of Machine made GI wire gabion Boxes of Mesh size
18 6.3 100mm*120mm with heavy coated GI wires (Mesh wire: 3mm, selvedge
wire 3.9mm and Lacing wire 2.4mm) - Size 3m X 1m X 1m No 5,151.71
Supplying of Machine made GI wire gabion Boxes of Mesh size
19 6.4 100mm*120mm with heavy coated GI wires (Mesh wire: 3mm, selvedge
wire 3.9mm and Lacing wire 2.4mm) - Size 3m X 1m X 0.5m
No 3,603.92
Supplying of Machine made GI wire gabion Boxes of Mesh size
20 6.5 100mm*120mm with heavy coated GI wires (Mesh wire: 3mm, selvedge
wire 3.9mm and Lacing wire 2.4mm) - Size 3m X 1m X 0.3m No 2,992.43
7 GRAVEL FILTER/GEO TEXTILE 0.00
Supplying well graded filter aggregate of size 20 mm and less and laying
21 7.1 underneath of canal lining for drain including haulage up to 10 m & lift
1.5 m. m3 4,857.45
Geo-Textiles: Supplying & laying of Geo-textile filter of 300 GSM grade
22 7.2
below boulder pitching m2 240.49
Laying thick filter layer of 75mm to 6mm. Stone aggregates in canal bed
23 7.3
incl.haulage up to 10m distance m3 3,300.81

8 STONE WORK 0.00


Stone soling in foundation and levelling including haulage distance up to
24 8.1
30 m. m3 4,795.57
25 8.2 Boulder pitching on slope including haulage upto 100m and lift upto 1.5m
m3 4,507.37
9 TURFING 0.00
26 9.1 Turfing: Grass Seeding works including seeding and Water Sprinkling. m2 25.00
10 RUBBER SEAL 0.00
27 10.1 Supplying and fixing rubber seal on concrete face m 1,602.90
11 IRON WORKS 0.00
Cutting , bending , placing in position of Channel bars as per the
28 11.1 design/drawing for RCC works including haulage to 30m distance. kg 207.44
Cutting , bending , placing in position of GI Pipes as per the
29 11.2 design/drawing for RCC works including haulage to 30m distance. m 700.21
12 PILING 0.00
30 12.1 Driving vertical steel pile/ sheet piles complete mt 164,792.98
Providing, driving and installing Boulder pile of specified size and quality;
31 12.2 Pile diameter - 500mm m 5,792.62
13 ROAD AND PAVEMENT WORKS 0.00
Subgrade preparation: Loosening, levelling and compacting original
ground supporting embankment to facilitate placement of first layer of
embankment, scarified to a depth of 150 mm, mixed with water at OMC
and then compacted by rolling so as to achieve dry density as per
32 13.1 drawing and specifications m2 11.18
Providing subbase: Providing and laying granular sub-base material by
mechanical means on prepared surface, mixing on OMC, and
33 13.2 compacting to achieve the desifed density, complete m3 4,617.32
WBM Base course: Providing, laying, spreading and compacting WBM
including brooming requisite types of screening/ binding materials to fill
up the interstices of coarse aggregate, watering and compacting to the
34 13.3 required density by mechanical means. m3 5,583.29
Remarks
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

RATE ANALYSIS
Norms Code Item Code Code Description of Works Quantity Unit Type
1 SITE CLEARANCE
Site clearance including cutting thin vegetation, grubbing their
roots and disposal, cutting, uprooting and disposal of grasses
1.1 1.1 1 m2
with light compaction and clearing, removal of topsoil and
disposal
Cutting thin vegetation, grubing their roots and disposal 25m far
1_4 1.1 from the const. site. (the vegetation dia <= 30cm and density > m2 Labour
15 nr/100m2)

Cutting, uprooting and disposal of grasses with light compaction,


1_5 1.1 m2 Labour
levelling and clearing the site.

Removal of top soils and disposal away from the construction


1_8 1.1 m2 Labour
site (thickness=15-20 cms)
1.1 Total
1.1 Contractor's Overhead
1.1 Grand Total
1.1 Unit Item Rate
2 2 EARTH WORK IN EXCAVATION/EMBANKMENT
Excavation of soft clay & silty soils including disposal up to 10 m
2_1 2.1 2.1 1 m3 Labour
lead & 1.5m lift)
2.1
2.1 Total
2.1 Contractor's Overhead
2.1 Grand Total
2.1 Unit Item Rate
Earthwork in filling with 15cm thick soil, including lead 10m &
2_25-b 2.2 2.2 1 m3 Labour
1.5m lift & manually compaction without sprinkle of water
2.2
2.2 Total
2.2 Contractor's Overhead
2.2 Grand Total
2.2 Unit Item Rate
Earthwork in filling with 15cm thick soil, including lead 10m &
2_25-a 2.3 2.3 1 m3 Labour
1.5m lift & manually compaction with sprinkle of water
2.3
2.3 Total
2.3 Contractor's Overhead
2.3 Grand Total
2.3 Unit Item Rate
Earthwork in excavation of foundation of structures, including
construction of soring and bracing, removal of stumps and other
9_4(I-B-i) 2.4 2.4 240 m3 Labour
deleterious matter and backfilling with approved Materials as per
drawing and technical specifications by mechanical means
2.4 Labour
2.4 Equipment
2.4 Total
2.4 Contractor's Overhead
2.4 Grand Total
2.4 Unit Item Rate
Earthwork in excavation of foundation of structures, including
construction of soring and bracing, removal of stumps and other
9_4V 2.5 2.5 deleterious matter and backfilling with approved Materials as per 10 m3 Labour
drawing and technical specifications by mechanical means for
marshy land, including dewatering
2.5 Labour
2.5 Equipment
Equipment
Cost of dewatering
Shoring and strutting
2.5 Total
2.5 Contractor's Overhead
2.5 Grand Total
2.5 Unit Item Rate
Stripping and storing top soil: stripping, storing of top soil by
road side at 15m interval and re-application on embankment
9.5 2.6 2.6 slopes, cut slope and other areas in localities where the 300 m3 Labour
available embankment materials is not conducive to plant
growth
2.6 Labour
2.6 Equipment
2.6 Total
2.6 Contractor's Overhead
2.6 Grand Total
2.6 Unit Item Rate
Construction of Embankment with Material obtained from borrow
9.8 2.7 2.7 pits: providing, laying, spreading and compacting embankment 300 m3 Labour
with borrow materials
2.7 Labour
2.7
2.7 Borrow pit material
2.7 Equipment
2.7 Equipment
2.7 Equipment
Equipment
Equipment
2.7 Total
2.7 Contractor's Overhead
2.7 Grand Total
2.7 Unit Item Rate
2.7
Construction of Embankment with Material Deposited from
9_9(B) 2.8 2.8 300 m3 Labour
Cutting by mechanical means
2.8 Labour
2.8 Equipment
2.8 Equipment
2.8 Equipment
2.8 Total
2.8 Contractor's Overhead
2.8 Grand Total
2.8 Unit Item Rate
2.8
3 3 CEMENT CONCRETE WORKS
Concreting of foundations, vertical faces, walls, Abutment in
7_2-c 3.1 3.1 1:3:6 (M10) cement sand aggregate mix including supply of 1 m3 Labour
materials and haulage distance upto 30m
3.1 Labour
3.1 Materials
3.1 Materials
3.1 Materials
3.1 Materials
3.1 Total
3.1 Contractor's Overhead
3.1 Grand Total
3.1 Unit Item Rate
Concreting of foundations, vertical faces, walls, in 1:2:4 (M15)
7-2-d 3.2 3.2 PCC for RCC, cement sand aggregate mix including supply of 1 m3 Labour
materials and haulage distance upto 30m
3.2 Labour
3.2 Materials
3.2 Materials
3.2 Materials
3.2 Materials
3.2 Materials
3.2 Total
3.2 Contractor's Overhead
3.2 Grand Total
3.2 Unit Item Rate
Concreting of super structure, Vertical faces, Deck Slab, Beams,
7_4-b 3.3 3.3 Walls of ratio 1:1.5:3 (M20) including supply of materials and 1 m3 Labour
haulage distance upto 30 m
3.3 Labour
3.3 Materials
3.3 Materials
3.3 Materials
3.3 Materials
3.3 Total
3.3 Contractor's Overhead
3.3 Grand Total
3.3 Unit Item Rate
Concreting of super structure, Vertical faces, Deck Slab, Beams,
7_4-c 3.4 3.4 Walls of ratio 1:1:2 (M25) including supply of materials and 1 m3 Labour
haulage distance upto 30 m
3.4 Labour
3.4 Materials
3.4 Materials
3.4 Materials
3.4 Materials
3.4 Total
3.4 Contractor's Overhead
3.4 Grand Total
3.4 Unit Item Rate
4 4 REINFORCEMENT
Cutting , bending , placing in position and binding of
7_5 4.1 4.1 reinforcement steel bars as per the design/drawing for RCC 1000 kg Labour
works including haulage to 30m distance.
4.1 Labour
4.1 Materials
4.1 Materials
4.1 Total
4.1 Contractor's Overhead
4.1 Grand Total
4.1 Unit Item Rate
5 5 FORMWORK
Making wooden forms including supply and selection of
8_2-b 5.1 5.1 materials fixing, nailing according to drawings, placing 10 m2 Labour
separators, dismantling forms and hauling upto 30m distance
5.1 Labour
5.1 Materials
5.1 Materials
5.1 Total
5.1 Contractor's Overhead
5.1 Grand Total
5.1 Unit Item Rate
6 6 GABION WORKS & BOULDER FILLING WORKS
16_11 6.1 6.1 Boulder supply and filling into Gabion Boxes 1 m3 Labour
6.1 Materials
6.1 Total
6.1 Contractor's Overhead
6.1 Grand Total
6.1 Unit Item Rate
Supplying of Machine made GI wire gabion Boxes of Mesh size
100mm*120mm with heavy coated GI wires (Mesh wire: 3mm,
6.2 6.2 1 No Materials
selvedge wire 3.9mm and Lacing wire 2.4mm) - Size 2m X 1m X
1m
Gabion construction works including placing in position, tying
16_8-a 6.2 1 No Labour
gabion by tightening wire

6.2 Tie wire Materials


6.2 Total
6.2 Contractor's Overhead
6.2 Grand Total
6.2 Unit Item Rate
Supplying of Machine made GI wire gabion Boxes of Mesh size
100mm*120mm with heavy coated GI wires (Mesh wire: 3mm,
6.3 6.3 1 No Materials
selvedge wire 3.9mm and Lacing wire 2.4mm) - Size 3m X 1m X
1m
Gabion construction works including placing in position, tying
16_8-b 6.3 1 No Labour
gabion by tightening wire
6.3 Tie wire Materials
6.3 Total
6.3 Contractor's Overhead
6.3 Grand Total
6.3 Unit Item Rate
Supplying of Machine made GI wire gabion Boxes of Mesh size
100mm*120mm with heavy coated GI wires (Mesh wire: 3mm,
6.4 6.4 1 No Materials
selvedge wire 3.9mm and Lacing wire 2.4mm) - Size 3m X 1m X
0.5m

Gabion construction works including placing in position, tying


16_8-d 6.4 1 No Labour
gabion by tightening wire

6.4 Tie wire Materials


6.4 Total
6.4 Contractor's Overhead
6.4 Grand Total
6.4 Unit Item Rate
Supplying of Machine made GI wire gabion Boxes of Mesh size
100mm*120mm with heavy coated GI wires (Mesh wire: 3mm,
6.5 6.5 1 No Materials
selvedge wire 3.9mm and Lacing wire 2.4mm) - Size 3m X 1m X
0.3m
Gabion construction works including placing in position, tying
16_8-d 6.5 1 No Labour
gabion by tightening wire
6.5 Tie wire Materials
6.5 Total
6.5 Contractor's Overhead
6.5 Grand Total
6.5 Unit Item Rate
7 7 GRAVEL FILTER/GEO TEXTILE
Supplying well graded filter aggregate of size 20 mm and less
23_5 7.1 7.1 and laying underneath of canal lining for drain including haulage 1 m3 Labour
up to 10 m & lift 1.5 m.
7.1 Materials
7.1 Total
7.1 Contractor's Overhead
7.1 Grand Total
7.1 Unit Item Rate
Geo-Textiles: Supplying & laying of Geo-textile filter of 300 GSM
7.2 7.2 1 m2 Labour
grade below boulder pitching
7.2 Materials
7.2 Total
7.2 Contractor's Overhead
7.2 Grand Total
7.2 Unit Item Rate

Laying thick filter layer of 75mm to 6mm. Stone aggregates in


7.3 m3 Labour
23_1 7.3 canal bed incl.haulage up to 10m distance 1
7.3 Labour
7.3 Materials
7.3 Total
7.3 Contractor's Overhead
7.3 Grand Total
7.3 Unit Item Rate

8 8 STONE WORK
Stone soling in foundation and levelling including haulage
6_5 8.1 8.1 1 m3 Labour
distance up to 30 m.
8.1 Materials
8.1 Total
8.1 Contractor's Overhead
8.1 Grand Total
8.1 Unit Item Rate
Boulder pitching on slope including haulage upto 100m and lift
23_5 8.2 8.2 1 m3 Labour
upto 1.5m
Labour
8.2 Materials
8.2 Total
8.2 Contractor's Overhead
8.2 Grand Total
8.2 Unit Item Rate
9 9 TURFING
Turfing: Grass Seeding works including seeding and Water
9.1 9.1 1 m2 Labour
Sprinkling.
9.1 Grass Seeding Materials
9.1 Watering grass seeds Equipment
9.1 Total
9.1 Contractor's Overhead
9.1 Grand Total
9.1 Unit Item Rate
9.1
10 10 RUBBER SEAL
10.1 10.1 Supplying and fixing rubber seal on concrete face 1 m Labour

10.1 Materials
10.1 Total
10.1 Contractor's Overhead
10.1 Grand Total
10.1 Unit Item Rate
10.1
11 11 IRON WORKS
Cutting , bending , placing in position of Channel bars as per the
11.1 11.1 design/drawing for RCC works including haulage to 30m 1 kg Labour
distance.
11.1 Labour
11.1 Materials
11.1 Total
11.1 Contractor's Overhead
11.1 Grand Total
11.1 Unit Item Rate

Cutting , bending , placing in position of GI Pipes as per the


11.2 11.2 design/drawing for RCC works including haulage to 30m 1 m Labour
distance.
11.2 Labour
11.2 Materials
11.2 Total
11.2 Contractor's Overhead
11.2 Grand Total
11.2 Unit Item Rate
12 12 PILING

16.4 12.1 12.1 Driving vertical steel pile/ sheet piles complete 2.5 mt Labour

12.1 Labour
12.1 Materials
12.1 Equipment
12.1 Equipment
12.1 Cost for shifting piling rig
12.1 cost for erecting and dismantling of piling rig
Depreciations charges for track, wooden sleeper, fish plates,
12.1
bolts dog spikes
12.1 Total
12.1 Contractor's Overhead
12.1 Grand Total
12.1 Unit Item Rate

Providing, driving and installing Boulder pile of specified size


16.1A 12.2 12.2 5 m Labour
and quality; Pile diameter - 500mm

12.2 Labour
12.2 Materials
12.2 Materials
12.2 Equipment
12.2 Equipment
12.2 Cost for shifting piling rig
12.2 cost for erecting and dismantling of piling rig
Depreciations charges for track, wooden sleeper, fish plates,
12.2
bolts dog spikes
12.2 Total
12.2 Contractor's Overhead
12.2 Grand Total
12.2 Unit Item Rate
13 13 ROAD AND PAVEMENT WORKS
Subgrade preparation: Loosening, levelling and compacting
original ground supporting embankment to facilitate placement
10.4 II 13.1 13.1 of first layer of embankment, scarified to a depth of 150 mm, 4000 m2 Labour
mixed with water at OMC and then compacted by rolling so as
to achieve dry density as per drawing and specifications
13.1 Labour
13.1 Equipment
13.1 Equipment
13.1 Total
13.1 Contractor's Overhead
13.1 Grand Total
13.1 Unit Item Rate
13.1
Providing subbase: Providing and laying granular sub-base
12.1 A 13.2 13.2 material by mechanical means on prepared surface, mixing on 300 m3 Labour
OMC, and compacting to achieve the desifed density, complete
13.2 Labour

13.2 Materials

13.2 Equipment
13.2 Equipment
13.2 Equipment
13.2 Total
13.2 Contractor's Overhead
13.2 Grand Total
13.2 Unit Item Rate
13.2
WBM Base course: Providing, laying, spreading and compacting
WBM including brooming requisite types of screening/ binding
12.1 A 13.3 13.3 360 m3 Labour
materials to fill up the interstices of coarse aggregate, watering
and compacting to the required density by mechanical means.

13.3 Labour
13.3 Materials
13.3 Materials
13.3 Equipment
13.3 Equipment
13.3 Total
13.3 Contractor's Overhead
13.3 Grand Total
13.3 Unit Item Rate
13.3
Detail Quantity Unit Rate Amount Remarks

10% of this item assumed in site


Unskilled 0.03 M-day 550.00 16.50
clearance

20% of this item assumed in site


Unskilled 0.0046 M-day 550.00 2.53
clearance

20% of this item assumed in site


Unskilled 0.032 M-day 550.00 17.60
clearance
36.63
0.15 5.49
42.12
42.12

Unskilled 0.7 M-day 550.00 385.00


Tools and Equipment 3% 11.55
396.55
0.15 59.48
456.03
456.03

Unskilled 0.25 M-day 550.00 137.50

Tools and Equipment 3% 4.13


141.63
0.15 21.24
162.87
162.87

Unskilled 0.5 M-day 550.00 275.00

Tools and Equipment 3% 8.25


283.25
0.15 42.49
325.74
325.74

Skilled 1 M-day 880.00 880.00 DoR Norms

Unskilled 3 M-day 550.00 1,650.00


Hydraulic Excavator 6 Hr. 3,570.00 21,420.00
23,950.00
0.15 3,592.50
27,542.50
114.76

Skilled 0.08 M-day 880.00 70.40 DoR Norms

Unskilled 4 M-day 550.00 2,200.00


Hydraulic Excavator 0.3 Hr. 3,570.00 1,071.00
Tipper 5 m3 1 Hr. 1,454.00 1,454.00
20 % 959.08
10 % 472.50
6,226.98
0.15 934.05
7,161.03
716.10

Skilled 2 M-day 880.00 1,760.00 DoR Norms

Unskilled 10 M-day 550.00 5,500.00


Dozer Track 6 Hr. 5,891.00 35,346.00
42,606.00
0.15 6,390.90
48,996.90
163.32

Skilled 1 M-day 880.00 880.00 DoR Norms

Unskilled 4 M-day 550.00 2,200.00

360 m3 114.76 41,313.60


Hydraulic Excavator 6 hr 3,570.00 21,420.00
Tractor with Rotevator 12 hr 1,133.00 13,596.00
Dozer Track 3 hr 5,891.00 17,673.00
Motor Grader 3 hr 3,618.00 10,854.00
Vibratory Roller 8 ton 6 hr 2,413.00 14,478.00
122,414.60
0.15 18,362.19
140,776.79
469.26

Skilled 1 M-day 880.00 880.00 DoR Norms


Unskilled 10 M-day 550.00 5,500.00
Dozer Track 6 hr 5,891.00 35,346.00
Motor Grader 6 hr 3,618.00 21,708.00
Vibratory Roller 8 ton 6 hr 2,413.00 14,478.00
77,912.00
0.15 11,686.80
89,598.80
298.66

Skilled 1 M-day 880.00 880.00


Unskilled 4 M-day 550.00 2,200.00
Cement 0.22 Mt 18,082.15 3,978.07
Aggregates (40 mm) 0.65 m3 2,948.37 1,916.44
Aggregates (20 mm) 0.24 m3 3,448.37 827.61
Coarse Sand 0.47 m3 1,498.56 704.32
10,506.44
0.15 1,575.97
12,082.41
12,082.41

Skilled 1 M-day 880.00 880.00

Unskilled 4 M-day 550.00 2,200.00


Cement 0.32 Mt 18,082.15 5,786.29
Aggregates (40 mm) 0.52 m3 2,948.37 1,533.15
Aggregates (20 mm) 0.22 m3 3,448.37 758.64
Aggregates (10 mm) 0.11 m3 3,448.37 379.32
Sand 0.445 m3 1,498.56 666.86
12,204.26
0.15 1,830.64
14,034.90
14,034.90

Skilled 0.8 M-day 880.00 704.00

Unskilled 7 M-day 550.00 3,850.00


Cement 0.4 Mt 18,082.15 7,232.86
Aggregates (20 mm) 0.57 m3 3,448.37 1,965.57
Aggregates (10 mm) 0.29 m3 3,448.37 1,000.03
Sand 0.425 m3 1,498.56 636.89
15,389.35
0.15 2,308.40
17,697.75
17,697.75

Skilled 0.8 M-day 880.00 704.00

Unskilled 0.7 M-day 550.00 385.00


Cement 0.61 Mt 18,082.15 11,030.11
Aggregates (20 mm) 0.64 m3 3,448.37 2,206.96
Aggregates (10 mm) 0.21 m3 3,448.37 724.16
Sand 0.425 m3 1,498.56 636.89
15,687.12
0.15 2,353.07
18,040.19
18,040.19

Skilled 12 M-day 880.00 10,560.00

Unskilled 12 M-day 550.00 6,600.00


Rebars (Fe 500) 1050 Kg 88.58 93,011.25
Binding Wires 10 Kg 150.58 1,505.82
111,677.07
0.15 16,751.56
128,428.63
128.43

Skilled 1.44 M-day 880.00 1,267.20

Unskilled 2.1 M-day 550.00 1,155.00


Wood 0.087667 m3 66,349.29 5,816.62 Reuse 6 times
Nails 2.5 Kg 120.58 301.46
8,540.28
0.15 1,281.04
9,821.32
982.13

Unskilled 0.5 M-day 550.00 275.00


Stone 1 m3 2,787.55 2,787.55
3,062.55
0.15 459.38
3,521.93
3,521.93
Machine made gabion boxes,
hexagonal mesh 10 x 12 cms
10 m2 286.94 2,869.40
mesh wire 3 mm, salvage wire
3.9 mm, lacing wire 2.64 mm

Unskilled 0.4 M-day 550.00 220.00

G.I. wire, heavy zinc coated 0.75 Kg 132.58 99.44


3,188.84
0.15 478.33
3,667.17
3,667.17
Machine made gabion boxes,
hexagonal mesh 10 x 12 cms
14 m2 286.94 4,017.17
mesh wire 3 mm, salvage wire
3.9 mm, lacing wire 2.64 mm

Unskilled 0.6 M-day 550.00 330.00

G.I. wire, heavy zinc coated 1 Kg 132.58 132.58


4,479.75
0.15 671.96
5,151.71
5,151.71
Machine made gabion boxes,
hexagonal mesh 10 x 12 cms
10 m2 286.94 2,869.40
mesh wire 3 mm, salvage wire
3.9 mm, lacing wire 2.64 mm

Unskilled 0.3 M-day 550.00 165.00

G.I. wire, heavy zinc coated 0.75 Kg 132.58 99.44


3,133.84
0.15 470.08
3,603.92
3,603.92
Machine made gabion boxes,
hexagonal mesh 10 x 12 cms
8.4 m2 286.94 2,410.30
mesh wire 3 mm, salvage wire
3.9 mm, lacing wire 2.64 mm

Unskilled 0.18 M-day 550.00 99.00

G.I. wire, heavy zinc coated 0.7 Kg 132.58 92.81


2,602.11
0.15 390.32
2,992.43
2,992.43
Unskilled 1.41 M-day 550.00 775.50

Aggregates (20 mm) 1 m3 3,448.37 3,448.37


4,223.87
0.15 633.58
4,857.45
4,857.45

Unskilled 0.04 M-day 550.00 22.00


Geo-textile, 300 gsm 1 m2 187.12 187.12
209.12
0.15 31.37
240.49
240.49

Skilled M-day 880.00 308.00


0.35
Unskilled 0.53 M-day 550.00 291.50
River bed mixed Gravel 1 m3 2,270.77 2,270.77
2,870.27
0.15 430.54
3,300.81
3,300.81

Unskilled 1.5 M-day 550.00 825.00


Stone 1.2 2,787.55 3,345.06
4,170.06
0.15 625.51
4,795.57
4,795.57
Skilled 0.88 M-day 880.00 774.40
Unskilled 0.65 M-day 550.00 357.50
Stone 1 m3 2,787.55 2,787.55
3,919.45
0.15 587.92
4,507.37
4,507.37

Unskilled 0.01 M-day 550.00 5.50

Grass seeds 0.03 kg 300.58 9.02


Water Tanker 0.004 Hr. 1,806.00 7.22
21.74
0.15 3.26
25.00
25.00

Unskilled 0.01 M-day 550.00 5.50

Rubber seal 1m 1,388.33 1,388.33


1,393.83
0.15 209.07
1,602.90
1,602.90

Skilled 0.06 M-day 880.00 52.80

Unskilled 0.04 M-day 550.00 22.00


Channel Section 1 Kg 105.58 105.58
180.38
0.15 27.06
207.44
207.44

Skilled 0.01 M-day 880.00 8.80

Unskilled 0.03 M-day 550.00 16.50


GI pipes 1.5" dia, medium class 1m 583.58 583.58
608.88
0.15 91.33
700.21
700.21

Skilled 1 M-day 880.00 880.00 DoR Norms

Unskilled 5 M-day 550.00 2,750.00


Sheet piles 2500 kg 125.58 313,955.37
Crane 6 Hr. 3,102.00 18,612.00
Piling rig with Bentonite pump 6 Hr. 2,222.00 13,332.00
1.5 % 5,229.74
0.5 % 1,743.25
0.5 % 1,743.25
358,245.60
0.15 53,736.84
411,982.44
164,792.98

Skilled 1 M-day 880.00 880.00 DoR Norms

Unskilled 7 M-day 550.00 3,850.00


Stone 0.982 m3 2,787.55 2,737.37
Bentonite 75 kg 50.58 3,793.66
Crane 2.5 Hr. 3,102.00 7,755.00
Piling rig with Bentonite pump 2.5 Hr. 2,222.00 5,555.00
1.5 368.57
0.5 122.86
0.5 122.86
25,185.31
0.15 3,777.80
28,963.11
5,792.62

Skilled 1 M-day 880.00 880.00

Unskilled 4 M-day 550.00 2,200.00


Tractor with ripper attachment 6 Hr. 1,142.00 6,852.00
Vibratory Roller 8 ton 12 Hr. 2,413.00 28,956.00
38,888.00
0.15 5,833.20
44,721.20
11.18

Skilled 2 M-day 880.00 1,760.00

Unskilled 12 M-day 550.00 6,600.00

Aggregates (40 mm) 384 m3 2,948.37 1,132,175.26

Motor Grader 6 Hr. 3,618.00 21,708.00


Vibratory Roller 8 ton 12 Hr. 2,413.00 28,956.00
Tractor 12 Hr. 1,110.00 13,320.00
1,204,519.26
0.15 180,677.89
1,385,197.15
4,617.32
Skilled 3 M-day 880.00 2,640.00

Unskilled 15 M-day 550.00 8,250.00


Aggregates (20 mm) 435.6 m3 3,448.37 1,502,111.31
Aggregates (20 mm) 57.6 m3 3,448.37 198,626.29
Motor Grader 6 Hr. 3,618.00 21,708.00
Vibratory Roller 8 ton 6 Hr. 2,413.00 14,478.00
1,747,813.60
0.15 262,172.04
2,009,985.64
5,583.29
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

COST OF MATERIALS AT SITE

Quantity Metalled
Material Truck Idle
Carried by Truck Rate, Road
S. No. Materials Unit Rate Available Rate,
the Truck, NRs/Hr distance,
at NRs./Hr
mt km

1 Cement Mt 17,500.00 Gaur 6 1,336.02 350.00 20


2 Aggregates (40 mm) m3 2,400.00 Gaur 4.69 1,336.02 350.00 10
3 Aggregates (20 mm) m3 2,900.00 Gaur 4.69 1,336.02 350.00 10
4 Aggregates (10 mm) m3 2,900.00 Gaur 4.69 1,336.02 350.00 10
5 Sand m3 786.50 Dhansar 5.90 1,336.02 350.00 18
6 Coarse Sand m3 786.50 Dhansar 5.9 1,336.02 350.00 18
7 River bed mixed Gravel m3 1,375.00 Dhansar 4.69 1,336.02 350.00 18
8 Rebars (Fe 500) Kg 88.00 Gaur 6000 1,336.02 350.00 20
9 Binding Wires Kg 150.00 Gaur 6000 1,336.02 350.00 20
10 Stone m3
770.00 Chandi 3.5 1,336.02 350.00 30
11 G.I. wire, heavy zinc coated Kg 132.00 Gaur 6000 1,336.02 350.00 20

Machine made gabion boxes, hexagonal


12 mesh 10 x 12 cms mesh wire 3 mm, m2
salvage wire 3.9 mm, lacing wire 2.64 mm
285.00 Gaur 1800 1,336.02 350.00 20
13 Geo-textile, 300 gsm m2 187.00 Gaur 30000 1,336.02 350.00 20
14 Wood m3 66,000.00 Gaur 10 1,336.02 350.00 20
15 Nails Kg 120.00 Gaur 6000 1,336.02 350.00 20
16 Grass seeds kg 300.00 Gaur 6000 1,336.02 350.00 20
17 GI pipes 1.5" dia, medium class m 583.00 Gaur 6000 1,336.02 350.00 20
18 Channel Section Kg 105.00 Gaur 6000 1,336.02 350.00 20
19 Rubber seal Rm 1,386.00 Gaur 1500 1,336.02 350.00 20
20 Sheet piles kg 125.00 Gaur 6000 1,336.02 350.00 20
21 Bentonite kg 50.00 Gaur 6000 1,336.02 350.00 20
Other
Metalled Metalled Other Load
Other Road Road Loading Transportat Rate of Load
Road Road Time Road Unload Royalty,
distance, Time for Unloading ion Cost, Labour, Unload
Speed, for round Speed, Labour, NRs
km round Time, Hr. NRs NRs cost, NRs
km/Hr trip, Hr. km/Hr M-day
trip, Hr
4 40.00 1.00 10.00 0.80 0.75 444.55 1.501 550.00 137.59
4 40.00 0.50 10.00 0.80 0.75 426.29 1.041 550.00 122.08
4 40.00 0.50 10.00 0.80 0.75 426.29 1.041 550.00 122.08
4 40.00 0.50 10.00 0.80 0.75 426.29 1.041 550.00 122.08
5 40.00 0.90 10.00 1.00 0.75 474.73 1.455 550.00 135.64 101.69
5 40.00 0.90 10.00 1.00 0.75 474.73 1.455 550.00 135.64 101.69
5 40.00 0.90 10.00 1.00 0.75 597.21 1.455 550.00 170.63 127.93
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14

11 40.00 1.50 10.00 2.20 0.75 1,487.36 2.283 550.00 358.76 171.43
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14

4 40.00 1.00 10.00 0.80 0.75 1.48 1.501 550.00 0.46


4 40.00 1.00 10.00 0.80 0.75 0.09 1.501 550.00 0.03
4 40.00 1.00 10.00 0.80 0.75 266.73 1.501 550.00 82.55
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14
4 40.00 1.00 10.00 0.80 0.75 1.78 1.501 550.00 0.55
4 40 1.00 10 0.80 0.75 0.44 1.501 550.00 0.14
4 40.00 1.00 10.00 0.80 0.75 0.44 1.501 550.00 0.14
Rate
including
Remarks
Transportati
on, NRs
18,082.15 District Rate
2,948.37 Broken agg, district rate
3,448.37 Broken agg, district rate
3,448.37 Broken agg, district rate
1,498.56 From collection
1,498.56 From collection
2,270.77 From collection
88.58 District Rate
150.58 District Rate
From collection, stone
2,787.55 and boulder
132.58 District Rate

286.94 Market Rate


187.12 District Rate
66,349.29 District Rate
120.58 District Rate
300.58 District Rate
583.58 District Rate
105.58 District Rate
1,388.33 District Rate
125.58 District Rate
50.58 Market Rate
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

TRUCK RATE ANALYSIS


S.N. Data Unit Cost, NRs
1 Cost of Truck NRs. 2,500,000.00
2 Life Span Hr. 10,000.00
3 Yearly working Hours Hr. 2,000.00
4 Life span of Tyre Hr. 2,000.00
5 Daily Wages of Driver NRs. 795.00
6 Daily Wages of Helper NRs. 550.00
7 Working Hour per day Hr. 8.00
8 Cost of Tyre per No. NRs. 27,986.73

1 Ownership Cost (Fixed Cost)


a. Depriciation cost / hr =3300000/10000 250.00
b. Insurance cost / hr = 0.02*3300000/2000 25.00
c. Interest cost / hr = 0.01*3300000/2000 12.50
Sub-Total - 1 287.50

2 Operation and Maintenance Cost


a. Overhauling cost/hr = 0.55*3300000/10000 137.50
b. O & M cost / hr = 0.23*3300000/10000 57.50
Sub-Total - 2 195.00

3 Cost of Consumables (varriable Cost)


A. Oil and Lubricants Cost / Hrs. Req.Litres Rate/Lt.
a. High speed Diesel (HSD) 5.50 77.87 428.29
b. Mobil (Loose Pack) 0.10 615.04 61.50
c. Grease 0.015 574.33 8.61
d. Gear oil 0.03 517.69 15.53
Sub-Total 513.93

B. Spare Parts
a. Cost of Tyre /Hrs. 83.96
b. Miscellaneous (LS) cost / Hrs. 7.50
c. Extra Cost/ Hrs. 2.50
Sub Total 93.96

C. Salaries
a. Driver 99.38
b. Helper 68.75
Sub-Total 168.13
D. Improvement and other minor repair 15.00
Actual consumer prices per Hr (A+B+C+D) 791.02

4 Supervision Cost/ Hrs. = 0.05 X3300000 /2000 62.50


Total Operating Cost/ Hrs. (1 + 2 + 3 + 4 ) 1,336.02
Idle cost/Hr (1+3) 350.00
Remarks
District Rate

6 No.*Ct/Lt
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

EQUIPMENT HIRING COST


Cost including hire charge, fuel and manpower and other running costs
Equipment Unit Hourly Cost (DoR rates)
Hydraulic Excavator Hr. 3,570.00
Dozer Track Hr. 5,891.00
Vibratory Roller 8 ton Hr. 2,413.00
Motor Grader Hr. 3,618.00
Tipper 5 m 3
Hr. 1,454.00
Water Tanker Hr. 1,806.00
Tractor with Rotevator Hr. 1,133.00
Water Pump Hr. 44.00
Crane Hr. 3,102.00
Piling rig with Bentonite pump Hr. 2,222.00
Tractor with ripper attachment Hr. 1,142.00
Tractor Hr. 1,110.00
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

COST OF COLLECTION OF LOCAL MATERIALS


Source /
S.N. Construction Material Unit Norms Ref.
Size Unskilled Labor Rate Amount
M-day NRs. NRs.
1 Fine Aggregate (Sand) 65% Cum 3-1d 1.43 550.00 786.50
2 Coarse Aggregate - 1 5-70 mm Cum 3-2a 2.50 550.00 1,375.00
3 Coarse Aggregate - 2 5 - 40 mm Cum 3-2b 4.00 550.00 2,200.00
4 Coarse Aggregate - 3 5 - 20 mm Cum 3-2c 5.88 550.00 3,234.00
5 Boulders Cum 4 1.40 550.00 770.00
Government of Nepal
Ministry of Energy, Water Resources and Irrigation
Department of Water Resources and Irrigation
Bagmati Irrigation Project
LALBAKAIYA IRRIGATION PROJECT HEADWORKS DESIGN

RATE OF LABOUR
Rate
S. No. Item Unit Remarks
(NRs.)
1 Skilled M-day 880.00 District Rate
2 Unskilled M-day 550.00 District Rate
3 Driver M-day 795.00 Govt Salary rate minmum
4 Helper M-day 550.00 District Rate