You are on page 1of 1

Dickinson Public Schools District

$69,000,000 Proposed Bond Referendum Cost Break Down

Construction Costs*
Building Demolition: Only spaces not cost efficient to renovate or $1,300,000
modify, exact SF TBD

Building Remodel: Hazardous materials abatement, replace $7,750,000


mechanical systems, interior renovations, exact SF TBD

New Construction: New classrooms, cafeteria, and $40,850,000


circulation spaces, exact SF TBD

Elementary Secure Entrances: TBD Renovations, modifications, or $3,000,000


additions for security needs

Construction General Conditions: Estimated costs-based project $5,300,000

Soft Costs*
Project Fees: Architectural, Electrical, Mechanical, $6,750,000
Structural Engineering, CM, Surveying, Permitting, Borings, Testing

Furniture, Fixtures, and Equipment $2,750,000

Contingency*

District Contingency Funds $2,500,000


_________________________________________________________________________
TOTAL ESTIMATE $70,200,000*

*All costs are estimates