DOCUMENT B

THE TENDER

Appendix to Tender

ITEM Sub-Clause Data

Employer's name and address………. 1.1.2.2 & 1.3 LAGUNA (VIETNAM) CO., LTD
CU DU HAMLET, LOC VINH COMMUNE
PHU LOC DISTRICT
THUA TIEN HUE PROVINCE
VIETNAM

Contractor's name and address …….. 1.1.2.3 & 1.3 TO BE DETERMINED

Engineer's name and address……….. 1.1.2.4 & 1.3 TO BE ADVISED

Time for Completion of the Works…… 1.1.3.3 …….. EIGHT HUNDRED AND TEN (810) DAYS

Defects Notification Period…………… 1.1.3.7 ……..


TWELVE (12) MONTHS FROM THE COMPLETION DATE

Electronic transmission system…….. 1.3 …………. FAX AND EMAIL (REFER TO AMENDMENT -
SUB-CLAUSE 1.2 OF PAGE C/2)

Governing Law…………………………. 1.4 …………. SOCIALIST REPUBLIC OF VIETNAM

Ruling language……………………….. 1.4 …………. ENGLISH

Language for communications………. 1.4 …………. ENGLISH

Time for access to the Site………….. 2.1 …………. (TO BE STIPULATED IN THE LETTER OF
ACCEPTANCE)

Amount of Performance Security……. 4.2 …………. 10 % OF THE ACCEPTED CONTRACT AMOUNT

Normal working hours………………… 6.5 …………. AS STIPULATED BY THE LOCAL AUTHORITY

Delay damages for the Works……….. 8.7 & 14.5 (b) REFER TO DEFINITION OF SECTION IN PAGE B/10

If there are Provisional Sums:


Percentage for adjustment of
Provisional Sums ………………….. 13.5 (b)…….. CONTRACTOR TO PROPOSE _______%

O:\Company\PROJECT LISTS\1020_BANYAN TREE\MC\Tender\Doc\RE-TENDER - OCT 09\BTR Front End\06 DocB App to Letter of Tender (II)(III)(IV) (2)
10/20/2009
B/8
DOCUMENT B
THE TENDER

Appendix to Tender
If Sub-Clause 13.8 applies:
Adjustment for Changes in Cost :
Table(s) of adjustment data……….. 13.8 ………… NOT APPLICABLE

Coefficient; Country of origin; Source of index; Value on stated date(s)*


scope of index currency of index Title/definition Value Date

a=_____NA________ N.A. N.A. N.A. N.A.


b=_______________
c=_______________
d=_______________
e=_______________

* These values and dates confirm the definition of each index, but do not define Base Date indices

Total advance payment……………….. 14.2 ………… NOT APPLICABLE

Number and timing of instalments ….. 14.2 ………… NOT APPLICABLE

Currencies and proportions………….. 14.2 ………… NOT APPLICABLE

Start repayment of advance payment. 14.2 (a)…….. NOT APPLICABLE

Repayment amortisation of advance


payment………………………………… 14.2 (b)…….. NOT APPLICABLE

Percentage of retention………………. 14.3 ………… 10% OF WORK DONE

Limit of Retention Money…………….. 14.3 ………… 5% OF THE ACCEPTED


CONTRACT AMOUNT

If Sub-Clause 14.5 applies :


Plant and Materials for payment
when shipped en route to the Site… 14.5 (b)…….. NOT APPLICABLE

Plant and Materials for payment


when delivered to the Site…………. 14.5 (c) ……. NOT APPLICABLE

Minimum amount of Interim Payment 14.6 ………… NOT APPLICABLE


Certificates……………………………..

If payments are only to be made in currency/currencies named on the first pages of the Letter of Tender :

Currency/currencies of payment….. 14.15 ………. UNITED STATES DOLLARS

Currency Unit Percentage payable in the Rate of exchange : number


Currency of Local per unit of Foreign

Local : N.A.
Foreign : N.A.

O:\Company\PROJECT LISTS\1020_BANYAN TREE\MC\Tender\Doc\RE-TENDER - OCT 09\BTR Front End\06 DocB App to Letter of Tender (II)(III)(IV) (2)
10/20/2009
B/9
DOCUMENT B
THE TENDER

Appendix to Tender

Periods for submission of insurance:


(a) evidence of insurance………….. 18.1 ………… 7 DAYS
(b) relevant policies…………………. 18.1 ………… 21 DAYS

Maximum amount of deductibles for


insurance of the Employer's risks…… 18.2 (d)…….. NOT APPLICABLE

Minimum amount of third party


insurance………………………………. 18.3 ………… REFER TO SPECIMEN POLICY IN APPENDIX H

Date by which the DAB shall be


appointed ……………………………… 20.2 ………… NOT APPLICABLE

the DAB shall be ……………………… 20.2 ………… NOT APPLICABLE

Appointment (if not agreed) to be


made by ……………………………….. 20.3 ………… NOT APPLICABLE

If there are Sections :


Definition of Sections:

Description Time for Completion Delay Damages


(Sub-Clause 1.1.5.6) (Sub-Clause 1.1.3.3) (Sub-Clause 8.7)

Section 1 - Mock Up Villas comprising :- 240 Days from Commencement date US$600.00 per day
a) 1 unit - SPV-2BR including Sundays and
b) 1 unit - Beach Villa Public Holidays

Section 2 - Phase 1A – Part 1 comprising :- 600 Days from Commencement date US$9,300.00 per day
a) 17 units – 1 Bedroom Beach Villa including Sundays and
b) 19 units – 2 Bedroom SPV-2BR Public Holidays
c) 10 units – 3 Bedroom SPV-3BR
d) 4 units – 3 Bedroom RV-3BR
e) 1 unit – 4 Bedroom President Villa
f) All other Buildings and External works
demarcated in drawing no. Site/SP/1.1.1

Section 3 - Phase 1A – Part 2 comprising :- 720 Days from Commencement date US$7,000.00 per day
a) 45 units – 2 Bedroom SPV-2BR, including Sundays and
including External Works demarcated Public Holidays
in Drawing No: Site/SP/1.1.1

Section 4 - Phase 1B comprising :- 810 Days from Commencement date US$4,000.00 per day
a) 37 units – 1 Bedroom Lagoon Villa; including Sundays and
including External Works demarcated Public Holidays
in Drawing No: Site/SP/1.1.1

O:\Company\PROJECT LISTS\1020_BANYAN TREE\MC\Tender\Doc\RE-TENDER - OCT 09\BTR Front End\06 DocB App to Letter of Tender (II)(III)(IV) (2)
10/20/2009