Professional Documents
Culture Documents
Q6. How would you release retention if there are sectional completions?
Q10. Suppose original contract period has now expired. A valuation (monthly) comes to you.
How do you pay preliminary items? Are you going to pay full?
Q11. How do you stop such payment, give me example, take 2 items, “Engineer’
s Office”and
“Tests”?
Q12. How do you stop such payments? Is it contractual? Under what clause and why you
stop? If I have maintained the office for original contract period I should be paid full?
Q15. From a variation claim from contractor what would you check?
Q18. How you will measure the reinstatement of roads for the trenches? Will you pay for
additional width carried out by Contractor?
Q19. How you measure the micro tunnelling. Under which class you pay shaft, pipe and pits?
Q23. How you measure excavation for exposing and relocation of cable?
Q30. Will you approve the payment certificate without performance bond?
Q31. What is Statement at Completion? What is the meaning of amount due and estimated
amount due?
Q32. How you release first half of Retention money if taking over certificates issued in parts?
Q34. After how many days contractor should submit the final account after issuing of defects
liability certificate?
Q38. How will you pay O.H. and recover O.H. if the final contract sum + 15% when compared
to effective contract price.
Q40. How will you pay method related charges for extension of time cost?
Q41. Under which clause of Condition of Contract contractor is eligible for profit under any
claims.
Q42. If contractor fail to sent copy to employer about his intention to claim extension of time
what will happen?
Q43. How you pay Performance Bond and insurances for time extension cost?
Q47. What is final certificate? Is it only certificate or final account complete final account?
E:\QESTION - ANSWER\QS QUESTION CURRENT.doc Page 2 27/05/2002
Q48. How the trial trenches are measured?
Q49. If the trial trench is at bottom as per BOQ 3m² and contractor executed more than 3 m².
Is it paid as variation? For number in material?
Q51. What is the latest edition of FIDIC? What is a lump sum contract and how do you price
the variations?
Q53. Can you explain critical path in relation with construction programme?
Q54. How do you calculate the extension of time and under which condition?
Q55. If the bad weather prevails the whole month, do you calculate whole period for the
extension of time?
Q57. Before paying first interim payment to the contractor what procedure has to befollowed?
Q58. After receiving acceptance letter, how many days are allowed to the contractor to submit
the Performance Bond.
Q59. What is the total percentage included in contract for the retention and do you work it up
for the material at site?
Q61. What is the provisional sum? How do you price it after completion of similar item?
M3
Q62. Can you explain sub-base and wearing course?
Q63. How do you measure above item when checking the interim bill?
Q65. What is the 4 way duct bank and how do you measure.
Q70. Details of your experience which shall help to full fill these duties.
Q72. What are the items in the CESMM3 to pay for the piling?
Q75. Can Engineer give approval for clause 14 program? Is the Engineer is required to give
approval or consent to the program and why?
Q76. What are the grounds that will entitle the contractor to be entitled for the extension of
time?
Q77. Have you prepared claims report. What are the various contents/sections of the claim
report?
Q78. Explain risks in the contract.
Q79. What are the consequences if wrong setting out data is supplied by the Engineer?
Q84. What do you think of the recent Airport accident, who is to be suffering the
consequences, i.e. the contractor or the engineer?
Q85. What is your duty if you were a visitor to that site and saw the lapses in the safety
procedures?
Q87. What is double handling and what is the entitlement of contractor in this regard.
Q88. %age of bitumen content – how to effect adjustment against this item.
Q89. What are the activities at start of the project that you will be involved as senior Q.S.?
Q90. What are the pre – requisites at site that need to be completed before allowing the
contractor to start excavations?
Q91. How to proceed if the contract contains a provisional sum (prime cost????) for
constructing a small building
Q93. Can an engineer issue an instruction which involves additional cost. What is the
requirement if there is a safety issue involved?
Q96. How to ensure that the contractor has not deliberately attempted to make the activities
critical.
Q98. The contractor is requesting for making a new rate for bearing pad. How you will tackle
this.
Q102. When is the contractor entitled to request for inapplicability of the contract rates in case
of variations.
Q106. How the penalty clause does applies for reduction of penalty when a section of the work
has completed prior to the completion of whole of the works.
Q108. What is the concurrent delay? What is the entitlement of the contractor in case of the
concurrent delays?
Q112. What is the payment procedure to DEWA(ED) if they are doing some works in the
project? ( i.e. to be paid by the contractor or the direct payment from the client)
Q115. If the road base has been stacked by the contractor in shape of a trustrum of cone;
what is the formula for measurement of volume.
Q117. What adjustment will you make if the final effective contract sum has exceeded the
effective contract price by more than 15%?
Q120. If the second half of the retention is released and the sum withheld is not sufficient to
carryout the snags/outstanding works thru other contractor, how to recover the money.
Q121. How do you evaluate if a variation related to a mechanical work is undertaken by the
contractor thru fabricator, for which he is not able to produce any quotation etc.
Q122. How do you pay if a generator has been hired on site? How do you pay if the client
finally decides to buy the same generator?
Q127. When and how to pay for additional head office overheads to the contractor.
Q128. Have you had any experience with American method of measurements?
Q129. What are the roles of the Engineer?
Q130. In FIDIC how many occasion to making decision on time and money the engineer with
employer and contractor.
Q151. How to word rate for 4 way duct if bill of quantity contains the rate for 2 way duct
Q166 Tell us about the dispute resolution mechanisms typically prevalent in the
Contracts?
E:\QESTION - ANSWER\QS QUESTION CURRENT.doc Page 7 27/05/2002
Q167 Tell us about what do you know about adjudication?
Q168 Why PII is important for the profession and who does it protect?
Q169 What is ‘
run off cover’
Q173 What is substantial completion and when would you consider issue of ToC?
Q175 On what grounds the Contractor is not entitled to Costs when there is an award of
EoT?
Q176 How do you handle Provisional Items with in BOQ and what is its impact on
Effective Contract price?
Q177 Can you tell how is the provisional items (not provisional sums) treated with regard to
Effective Contract Price clause?
Q181 What kind of Personal protection equipment (PPE) would you possess when you are
out on site?
Q182 How is the format of Statement at completion differing from interim Certificates and
what are extra/additional characters this has got?
Q185 What are exclusions on delegated powers that is retained with the Employer and that
needs consent prior to Engineer’
s approval to Contractor?
Q190 Tell us about conflict of interest that you have faced in your profession
Q191 What are the advantages the employer gets through cost reporting and at the end of the
project’
s financial report?
Q198 What role does a planning supervisor undertake during the construction phase of a
project?
Q199 What is the difference between value engineering and value management?
Q200 What is risk management and give an example of what you would do to manage risk?
Q201 You are working for a client and a contractor contacts you on the morning of the retur n
date and states he can not make the deadline, what do you do?
Q202 He returns his tender and it is £100,000 less than the nearest competitor, what do you
do?
Q203 After completing a tender analysis you realize that you have made an arithmetical
error, and the tender you thought was cheapest is not the case, what do you do?
Q204 What would you do if a contract was returned to you from a client and the LADs section
was left blank?
Q205 You get a certificate back from the clients QS and it has been overvalued by £100, 000,
what do you do?
Q206 The internet and telephone connections are down on site, you need to source a
subcontractor how do you do it?
Q208 If a subcontractor is procured and needs an early start on site, what would you do?
First and foremost a letter of int ent in itself does not usually give rise to any contractual
rights or obligation. This is because the letter by stating that there will or may be a
contract in the future is treated as indicating that there is no contract at present.
Q212 It is valuation date, and an assistant QS comes to site, you are very busy and give him
the task of measuring stockpiled crushed concrete, what would you do?
Q258 What would you expect to receive from a subcontract if applying for materials off site?
Q218 You receive an application for payment from your subcontractor and he has applied for
£100,000 due to delay and disruption, what do you do?
Q220 Relationships deteriorate on site and your subcontractor serves notice to adjudicate
what do you do?
Q222 Is the decision of the adjudicator binding and when can you start other proceedings,
arbitration, litigation etc?
Q223 What path can be followed to improve contractual links between parties such as clients
and consultants under a traditional D & B job?
Q224 What is a collateral warranty and what would you normally expect to be included in
one?
Q226 Why do you want to join the elite institution that is RICS?
Q227 A client contacts you with a request to carry works, what would you offer and what
would you expect to be included?
Q230 You have passed a certificate for the now bankrupt subcontractor that is due to go out
for payment; do you still allow it to be processed?
Q258 The contract that you completed at Fairford, was it part of the Defence Estates prime
contracting procurement process?
Q234 A client contacts you and requests that you do some work for him, he pays cash or
cheque in advance, and what do you do?
Q235 Who is entitled to the interest gained on this money before you draw down on it?
Q243 What is a structural survey? How does this differ from a building survey?
Q249 Tell me what you know about the rules and regulations of the RICS?
Q251 Say you had a client with a medium sized plot of land on which stood a Georgian
house, what type of things would you need to take into consideration, if, for example the
client wanted to redevelop the land?
E:\QESTION - ANSWER\QS QUESTION CURRENT.doc Page 11 27/05/2002
Q252 What are LAD's and how do you calculate them?
Q254 What is the minimum level of PI cover? How is it worked out for your company?
If the job is not wanted the contractor will submit an inflated tender, called cover bid.
Q257 What works you did in the past as Quantity Surveyor?
Q258 If rain falls one day on site. Do you give extension of time and compensation to
contractor for the same?
Q259 For releasing advance payment what are the documents you require?
Q260 What are the contractual requirements?
Q261 What is the priority of documents?
Q262 What are included in Appendix to Tender?
Q263 In which circumstances variations are issued?
Q264 How you calculate the amount for extension of time?
Q265 How you measure pipes? How you measure pipes and fittings inside manholes and
back drops?
Q266 In CESMM 3 performance bond and Insurance is classified as what?
Q267 What is method related charge?
Q268 How you measure reinstatement of asphalt? Under which section?
Q269 What is C P M?
Q270 What is float?
Q271 From the program of work how you know which item is critical?
Q272 If you find two items are critical what actions you take?
Q273 If two items in a program with 5 and 7 days and if both are critical, which one is more
critical? Why?
Q274 What is concurrent delay?
Q275 What is provisional sum? Where is the amount for provisional sum in included?
Q276 How you fix the rate of an item which is not included in B O Q? Rate for 200 mm dia.
pipe is included in BOQ. How you calculate the rate for pipe of different dia.
Q277 An item which is not related to the items in BOQ to be carried out in the project. How
you finalize the price?
Q278 How you measure new kerb? How you itemize it?
Q279 When you release retentions? What are the requirements for releasing retentions?
Q280 If some defects occurs after releasing final certificate. Do you have any contractual
rights to instruct the contractor to do the work?
Q281 What is clause14? Can the Engineer revise the program of work? If the program of
work changes how it affect mode of your payment? What is clause 12?
Q282 Can you change the extension of time that you have already given to the contractor?
Q283 What you are doing for CPD?
Q284 How you pay extension of time cost for performance bond and insurance?
Q285 When paying material on site what you check?
Q286 In case you feel the day work amount paying to the contractor is higher in material,
plant and labour what you do?
Q287 What is discharge? Who prepares discharge and submit to whom?
Q288 Are you familiar with DM conditions?
E:\QESTION - ANSWER\QS QUESTION CURRENT.doc Page 12 27/05/2002
Q289 How you calculate liquidated damages for delay?
Q290 What is the duration of defects liability period?
Q291 When you release performance bond?
Q292 In which circumstances the contractor is liable to get extension of time?
Q293 What are the important points you check in Insurance and performance bond?
Q335 Method related charges – what are these and what is advantage of putting it in the Bill
of quantities? How to pay method related charges?
Q346 What are the pre requisite for approving an advance payment and how to recover it?