Slab Level Total BBM Completed Balance Total Plaster Completed
0.00 Mtr 134.08 Cu Mtr 113.96 Cu Mtr 20.04 Cu Mtr 1943.00 Sq Mtr 1358.00 Sq Mtr
4.95 Mtr 79.45 Cu Mtr 72.18 Cu Mtr 7.27 Cu Mtr 1151.43 Sq Mtr 213.19 Sq Mtr
8.75 Mtr 50.17 Cu Mtr 15.15 Cu Mtr 35.05 Cu Mtr 731.50 Sq Mtr 0.00 Sq Mtr
11.75 Mtr 111.04 Cu Mtr 0.00 Cu Mtr 111.04 Cu Mtr 1609.30 Sq Mtr 0.00 Sq Mtr