INSTALLATION QUALIFICATION PROTOCOL

FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE


AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/SHNS/HMD/22


AREA : Solid Hormonal Non Sterile REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Protocol, visual inspection, data record and writing the Installation
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 7


INSTALLATION QUALIFICATION PROTOCOL
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/SHNS/HMD/22


AREA : Solid Hormonal Non Sterile REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Protocol and its attachment, we, undersign below,
approve that this Protocol is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 8


INSTALLATION QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/SHNS/HMD/22


AREA : Solid Hormonal Non Sterile REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Report, visual inspection, data record and writing the Installation
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 7


INSTALLATION QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/SHNS/HMD/22


AREA : Solid Hormonal Non Sterile REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 8


INSTALLATION QUALIFICATION PROTOCOL
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : IQ-MP/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of
the Installation Qualification Protocol, visual inspection, data record and writing the Installation
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification
Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 3


INSTALLATION QUALIFICATION REPORT
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : IQ-MR/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of
the Installation Qualification Report, visual inspection, data record and writing the Installation
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification
Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 5


INSTALLATION QUALIFICATION REPORT
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : IQ-MR/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

4.0 Final Approvals

After reviewing this Installation Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform Weighing Booth System installation and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification
Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/SHNS/HMD/22


LOCATION : Solid Hormonal Non Sterile REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Report, visual inspection, data record and writing the Operational
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/SHNS/HMD/22


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System Operational and specification in
technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering and
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION PROTOCOL
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MP/SHNS/HMD/22


LOCATION : Solid Hormonal Non Sterile REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Protocol, visual inspection, data record and writing the Operational
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION PROTOCOL
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MP/SHNS/HMD/22


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Protocol and its attachment, we, undersign
below, approve that this Protocol is qualified to conform HVAC System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering and
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ/MR/SHNS/HMD/22


LOCATION : Solid Hormonal Non Sterile REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Report, visual inspection, data record and writing the Operational
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/SHNS/HMD/22


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System Operational and specification in
technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering and
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION REPORT
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : OQ-MR/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Report, visual inspection, data record and writing the Operational
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Assurance

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : OQ-MR/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform Weighing Booth System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION PROTOCOL
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : OQ-MP/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of
the Operational Qualification Protocol, visual inspection, data record and writing the
Operational Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION PROTOCOL
WEIGHING BOOTH SYSTEM
PT HERMED

SYSTEM : Weighing Booth DOCUMENT NO : OQ-MP/SHNS-02/HMD/23


LOCATION : Solid Hormonal Non Sterile REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Protocol and its attachment, we, undersign
below, approve that this Protocol is qualified to conform Weighing Booth System Operational
and specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


PERFORMANCE QUALIFICATION PROTOCOL
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MP/SHNS/HMD/23


AREA : Solid Hormonal Non Sterile REVISION : 00

3.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Performance Qualification Protocol, visual inspection, data record and writing the Performance
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 14


PERFORMANCE QUALIFICATION PROTOCOL
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MP/SHNS/HMD/23


AREA : Solid Hormonal Non Sterile REVISION : 00

4.0 Final Approvals

After reviewing this Performance Qualification Protocol and its attachment, We the under
signers approved that the performance qualification of the HVAC installed in solid hormone
non sterile Facility PT Hermed are met with the predefined specification and the system can be
used to supply the air to analysis facilities.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
MaintenanceManager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 13


PERFORMANCE QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MR/SHNS/HMD/23


AREA : Solid Hormonal Non Sterile REVISION : 00

3.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Performance Qualification Report, visual inspection, data record and writing the Performance
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 14


PERFORMANCE QUALIFICATION REPORT
FACILITIES HVAC SYSTEM SOLID HORMONAL NON STERILE
AT PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MR/SHNS/HMD/23


AREA : Solid Hormonal Non Sterile REVISION : 00

4.0 Final Approvals

After reviewing this Performance Qualification Report and its attachment, We the under signers
approved that the performance qualification of the HVAC installed in solid hormone non
sterile Facility PT Hermed are met with the predefined specification and the system can be used
to supply the air to analysis facilities.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
MaintenanceManager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 13


INSTALLATION QUALIFICATION PROTOCOL
HVAC SYSTEM OF RETENSI ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/RTS/HMD/22


AREA : RETENSI ROOM REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Protocol, visual inspection, data record and writing the Installation
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 6


INSTALLATION QUALIFICATION PROTOCOL
HVAC SYSTEM OF RETENSI ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/RTS/HMD/22


AREA : RETENSI ROOM REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Protocol and its attachment, we, undersign below,
approve that this Protocol is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 5


INSTALLATION QUALIFICATION PROTOCOL
HVAC SYSTEM OF STABILITY ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/SBY/HMD/22


AREA : STABILITY ROOM REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Protocol, visual inspection, data record and writing the Installation
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 6


INSTALLATION QUALIFICATION PROTOCOL
HVAC SYSTEM OF STABILITY ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/SBY/HMD/22


AREA : STABILITY ROOM REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Protocol and its attachment, we, undersign below,
approve that this Protocol is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 5


INSTALLATION QUALIFICATION REPORT
HVAC SYSTEM OF RETENSI ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/RTS/HMD/22


AREA : RETENSI ROOM REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Report, visual inspection, data record and writing the Installation
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 6


INSTALLATION QUALIFICATION REPORT
HVAC SYSTEM OF RETENSI ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/RTS/HMD/22


AREA : RETENSI ROOM REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 5


INSTALLATION QUALIFICATION REPORT
HVAC SYSTEM OF STABILITY ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/SBY/HMD/22


AREA : STABILITY ROOM REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Report, visual inspection, data record and writing the Installation
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 6


INSTALLATION QUALIFICATION REPORT
HVAC SYSTEM OF STABILITY ROOM FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/SBY/HMD/22


AREA : STABILITY ROOM REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 5


OPERATIONAL QUALIFICATION PROTOCOL
HVAC SYSTEM OF RETENSI ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MP/RTS/HMD/22


LOCATION : RETENSI ROOM REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Protocol, visual inspection, data record and writing the Operational
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION PROTOCOL
HVAC SYSTEM OF RETENSI ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MP/RTS/HMD/22


LOCATION : RETENSI ROOM REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Protocol and its attachment, we, undersign
below, approve that this Protocol is qualified to conform HVAC System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION PROTOCOL
HVAC SYSTEM OF STABILITTY ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MP/SBY/HMD/22


LOCATION : STABILITY ROOM REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Protocol, visual inspection, data record and writing the Operational
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION PROTOCOL
HVAC SYSTEM OF STABILITTY ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MP/SBY/HMD/22


LOCATION : STABILITY ROOM REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Protocol and its attachment, we, undersign
below, approve that this Protocol is qualified to conform HVAC System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM OF RETENSI ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/RTS/HMD/22


LOCATION : RETENSI ROOM REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of
the Operational Qualification Report, visual inspection, data record and writing the
Operational Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM OF RETENSI ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/RTS/HMD/22


LOCATION : RETENSI ROOM REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System Operational and specification in
technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM OF STABILITTY ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/SBY/HMD/22


LOCATION : STABILITY ROOM REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of
the Operational Qualification Protocol, visual inspection, data record and writing the
Operational Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM OF STABILITTY ROOM FACILITIES
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/SBY/HMD/22


LOCATION : STABILITY ROOM REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Protocol and its attachment, we, undersign
below, approve that this Protocol is qualified to conform HVAC System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian

Qualification Team
Dilla Habibah

Qualification Coordinator

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


INSTALLATION QUALIFICATION PROTOCOL
HVAC SYSTEM OF MICROBIOLOGY LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Protocol, visual inspection, data record and writing the Installation
Qualification Protocol:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian
Qualification Team

Dilla Habibah
Qualification Coordinator
Tegi Septian Hakiki
Site Project

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 6


INSTALLATION QUALIFICATION PROTOCOL
HVAC SYSTEM OF MICROBIOLOGY LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MP/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Protocol and its attachment, we, undersign below,
approve that this Protocol is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date


Reza Febrian
Qualification Team

Dilla Habibah
Qualification Coordinator

Tegi Septian Hakiki


Site Project

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 5


INSTALLATION QUALIFICATION REPORT
HVAC SYSTEM OF MICROBIOLOGY LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

4.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Installation Qualification Report, visual inspection, data record and writing the Installation
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 6


INSTALLATION QUALIFICATION REPORT
HVAC SYSTEM OF MICROBIOLOGY LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : IQ-MR/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

5.0 Final Approvals

After reviewing this Installation Qualification Report and its attachment, we, undersign below,
approve that this Report is qualified to conform HVAC System installation and specification in
technical specification and operation PT Hermed .

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 5


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/ML/HMD/22


LOCATION : Microbiology Laboratory REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Report, visual inspection, data record and writing the Operational
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/ML/HMD/22


LOCATION : Microbiology Laboratory REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Report and its attachment, we, undersign
below, approve that this Report is qualified to conform HVAC System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/ML/HMD/22


LOCATION : Microbiology Laboratory REVISION : 00

2.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Operational Qualification Report, visual inspection, data record and writing the Operational
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Technical

Quality Support - QA

PT KUSUMA PERSADA ENGINEERING 4


OPERATIONAL QUALIFICATION REPORT
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : OQ-MR/ML/HMD/22


LOCATION : Microbiology Laboratory REVISION : 00

3.0 Final Approvals

After reviewing this Operational Qualification Report and its attachment, we, undersign
below, approve that this Report is qualified to conform HVAC System Operational and
specification in technical specification and operation PT Hermed.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 3


PERFORMANCE QUALIFICATION PROTOCOL
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MP/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

3.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Performance Qualification Report, visual inspection, data record and writing the Performance
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Technical

Quality Support – QA

Analis QC

PT KUSUMA PERSADA ENGINEERING 13


PERFORMANCE QUALIFICATION PROTOCOL
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MP/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

4.0 Final Approvals

After reviewing this Performance Qualification Report and its attachment, We the under signers
approved that the performance qualification of the HVAC installed in Microbioilogy Of
Laboratory Facility PT Hermed are met with the predefined specification and the system can be
used to supply the air to analysis facilities.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Engineering &
Mainteance manager

Quality Assurance Manager

PT KUSUMA PERSADA ENGINEERING 12


PERFORMANCE QUALIFICATION REPORT
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MR/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

3.0 Validation Team

The following personnel comprise the validation team who responsible for the execution of the
Performance Qualification Report, visual inspection, data record and writing the Performance
Qualification Report:

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Technical

Quality Support – QA

Analis QC

PT KUSUMA PERSADA ENGINEERING 13


PERFORMANCE QUALIFICATION REPORT
HVAC SYSTEM MICROBIOLOGY OF LABORATORY FACILITY
PT HERMED

SYSTEM : HVAC DOCUMENT NO : PQ-MR/ML/HMD/22


AREA : Microbiology Laboratory REVISION : 00

4.0 Final Approvals

After reviewing this Performance Qualification Report and its attachment, We the under signers
approved that the performance qualification of the HVAC installed in Microbioilogy Of
Laboratory Facility PT Hermed are met with the predefined specification and the system can be
used to supply the air to analysis facilities.

PT Kusuma Persada Engineering

Name Signature Initials Date

Reza Febrian

Qualification Team

Dilla Habibah

Qualification Coordinator

Tegi Septian Hakiki

Site Project

PT Hermed

Name Signature Initials Date

Engineering &
Maintenance Manager

Quality Assurance

PT KUSUMA PERSADA ENGINEERING 12