You are on page 1of 8

TABREED

ENERGY TRANSER STATIONS (E.T.S)

Indirect connection via heat exchanger

ETS CONNECTION TECHNICAL GUIDE


TABREED Revision 8

INTRODUCTION

PURPOSE

This guide will discuss the scope of work, and technical requirements of connecting to the
Energy Transfer Station(s) (herein referred to as ETS).

ETS CONNECTION TECHNICAL GUIDE Page 2 of 8


TABREED Revision 8

THE ENERGY TRANSFER STATION

GENERAL

1.1.1 District Cooling


A. Cooling is to be provided for the building via the site-wide district cooling system
provided by(Tabreed).Tabreed will deliver chilled water at the design temperatures
specified under “Technical Requirements – General Conditions” to the CUSTOMER
(building ), subject to the scope of work and the district cooling technical
requirements outlined in this document. The piping connection will be discussed in
this document and is as shown on the attached schematic. The place of connection
will be surveyed and approved by Tabreed and is referred to herein as the Energy
Transfer Station

B. The District Cooling Water System (DCWS) will be designed and installed by
Tabreed complete with primary PHE’S and all monitoring and controls associated
with the main (DCWS). The terminal point between the (DCWS) provider and
building system is the PHE’S hot side connection only. Tabreed requirements for
monitoring the building system to be as per attached schematic diagram
C. Tabreed will provide one metering station for each ETS room on tabreed side only.
D. The Energy Transfer Station (ETS) plant space to be as per Tabreed requirements
E. Configuration and arrangements of Tabreed PHE’S and Tabreed piping work will be
designed& constructed &supervised and approved by Tabreed as per Tabreed
requirements and specifications
F. Configuration and arrangements of building side equipments and piping will be
designed by the building designer as per Tabreed requirements and constructed
under the building contract
G. All works associated with the construction of tunnels, ducts, sleeves or trenches to
accommodate District Cooling Water mains between the Energy Transfer Station
and Plot Boundary shall be designed by the building designer as per Tabreed
requirements and constructed under the building contract to the approval of the
DCWS provider (Tabreed).
H. The District cooling pipe work will utilize Pre-insulated carbon-steel
I. Building system maximum working pressures shall be provided by the building
designer to Tabreed: to allow Tabreed to identify the pressure rating for Tabreed
PHE’S

ETS CONNECTION TECHNICAL GUIDE Page 3 of 8


TABREED Revision 8

SCOPE OF WORK

The scope or limit of work of Tabreed and that of our CUSTOMER is defined as per the
attached schematics. Tabreed CUSTOMER are kindly advised to adhere to the following
design requirements to ensure successful implementation of District Cooling.

TABREED SCOPE OF WORK


1- Tabreed will supply & install the heat exchanger and all required piping connection from
Tabreed’s side as per attached schematic.

2- All industrial controls and automation, including programmable logical controller (PLC),
instrumentation and wiring as per this guide and attached schematic.

THE CUSTOMER SCOPE OF WORK (Building Side )


1- To provide 3 phase electric power supply to the ETS. 50A

2- A water supply line of 1 1/4” (32 mm) is required for filling the customer side piping
system and as a make up for the required pressurization / expansion pump set tank.

3- Drain Connection to the nearest external manhole.

4- Modify (if necessary & where applicable) and install all piping, insulation and valves on
the CUSTOMER (building) side of the ETS, as per the attached schematic.

5- Supply and install the variable speed pumps for distribution.

6- Supply and install pressurization / expansion tank pumps sets.

7- To supply and install one or two number differential pressure transmitters usually located
across the far end chilled water pipes of an air handling unit utilizing a 2-way modulating
motorized valve. The customer should wire this transmitter(s) to the plantroom PLC.

8- Supply and install a motor control center (MCC) in the electric room that incorporates:

a) Main Circuit Breaker.


b) Variable Frequency drives for the chilled water pumps.
c) Capacitor banks for power correction.
d) Distribution Board (DB) for ETS room lighting and receptacles.

ETS CONNECTION TECHNICAL GUIDE Page 4 of 8


TABREED Revision 8

9- Supply and install two numbers Temperature Transmitter on the Chilled Water mains as
per attached schematic.

10- Tabreed CUSTOMER to furnish and install Chilled water treatment system including
manual feed chemicals dozing pot with the necessary rust inhibitors and biocides quantity
necessary for testing, commissioning and operation. A specialized professional company
shall handle the water treatment system.

11- Install industrial grade automatic air vents (1”) at the highest point(s) in the customer’s
(building) piping system.

12- CUSTOMER (building ) will build the E.T.S and all associated civil work with the E.T.S
room, equipment bases and piping trenches

ETS CONNECTION TECHNICAL GUIDE Page 5 of 8


TABREED Revision 8

TECHNICAL REQUIREMENTS

GENERAL CONDITIONS

DISTRICT COOLING REQUIREMENT

(1)Cooling Capacity Requirement: To be confirmed by building


CONSULTANT.
(2)Pipe Connection Size: Depends on load.

(3)Design temperature diagram on Tabreed PHE


(3-1) Temperature diagram on Tabreed side (Tabreed PHE cold side) is
(A) Tabreed Supply chilled water temperature 40OF (4.44 OC)
(B) Tabreed Return chilled water temperature 56OF (13.33OC)
(3-2) Temperature diagram on Building side (Tabreed PHE hot side) is
(A) Building Supply chilled water temperature 42OF (5.56 OC)
(B) Building Return chilled water temperature 58OF (14.44OC)

Chilled water flow depends on load.

Maximum variation in Tabreed supply


Chilled water temperature is + / - 1.8OF (1.0OC)

Minimum acceptable building return chilled


Water temperature is 56OF (13.33OC)

Maximum acceptable building return chilled


Water temperature is 60OF (15.56 OC)

Pressure drop inside Tabreed PHE is 0.7 bar

Design water velocities / Pressure drops


• Pipe size 2” and smaller Min = 1.5 ft/sec, Max 4 ft /sec
• Pipe size 2 1/2” and larger Min = .75 ft / 100 ft, Max 4 ft / 100ft

Particular Requirements: How To Achieve The Above Conditions?

1- Building designer will design building air side equipment and chilled water piping using
the above chilled water temperatures .for building side

2- By designing the control system around variable flow chilled water system using two way
equal percentage control valves for all air handling units and fan coil units. Air Handling
units above 2,000 CFM shall have modulating equal percentage type. Fan Coil units with
capacity equal and smaller than 2,000 CFM can be on/off or modulating type.

3- The Air handling units and fan coil units at the end of the faraway circuits should have
three way control valves to avoid chilled water stagnation and allow for the minimum

ETS CONNECTION TECHNICAL GUIDE Page 6 of 8


TABREED Revision 8

pump flow. The number of air handling units or fan coil units designed for using three way
control valve should correspond to a maximum chilled water flow of 10% of full design
flow. The bypass on the three-way valve should have a double regulating valve to do
proper balancing and shut off of the bypass whenever the system requires that.

4- All Air handling units, Fan coil units and main branches shall have a double regulating
balancing valve with self sealing test point used for chilled water flow measurement
required during balancing and commissioning. During commissioning phase the customer
shall have a digital-measuring instrument furnished by the valve manufacturer to translate
quickly and accurately the valve pressure drop into corresponding chilled water flow.

5- Tabreed CUSTOMER to furnish and install secondary chilled water pumps. Two or
more operating and one standby pumps should be used in order to allow flow control
to vary between 10% and 100%. Pumps motors, and pump seal cooling should be
designed for variable speed operation range of 10 to 50 Hz ( 300 to 1,500 rpm). The
minimum mechanical efficiency of pump is 78% and the electric efficiency of the pump
motor is 94%. The variable speed drive efficiency should be 95% at 50 Hz (1,450 rpm),
90% at 35 Hz (1,000 rpm), 85% at 25 Hz (725 rpm) and 85% 10 Hz (300 rpm).

6- Install strainers on all AHU supply chilled water pipe.

7- Tabreed CUSTOMER are required to perform a complete and thorough flushing of their
chilled water piping network, so that at the time of connection to Tabreed’s ETS, the
client’s piping system is full of clean water and is clear from all unwanted debris.

8- Tabreed CUSTOMER are required to furnish and install VFD drives in the MCC with the
following control requirement in order to monitor them by Tabreed Programmable Logical
Controller PLC installed in the ETS room.

Analog Input 0-10V DC, input impedance 200KΩ


4-20 amps, input impedance 250Ω,
Differentially isolated external potentiometer, 0-10v dc, 1KΩ minimum

Digital Input 6- programmable positive or negative control logic

Auxiliary Supply 24V DC ± 20%, 100 mA

Reference Supply 10V DC (-0% to +3%), 10 mA

Analog Output Programmable: 0-20 mA, impedance 500Ω, resolution 10-bit, ±


3%

Digital Output 2 programmable from C Relays, 250 V AC 2 Amp, or 30V DC 2


Amp resistive. 1 programmable open collector, 48 V DC, 50mA

9- Differential Pressure Transmitter: Electronic, output: 4-20mA dc signal, linear with


differential pressure, into 1000 ohms, isolated.

ETS CONNECTION TECHNICAL GUIDE Page 7 of 8


TABREED Revision 8

10- Temperature Transmitter Output: 4-20mAdc linear with temperature into 1000 ohms,
isolated.

Recommended manufacturers for the VFDs are Allen Bradley, ABB, GE, or similar.

Recommended manufacturers for the Differential Pressure transmitter are Rosemount,


Yokogawa, E+H, Sen Sit, Dieterich, Barton or approved equal.

____________________________

ETS CONNECTION TECHNICAL GUIDE Page 8 of 8

You might also like