You are on page 1of 3

GOVERNMENT OF PUNJAB

PUBLIC WORKS DEPARTMENT B&R BRANCH ON BEHALF OF MORT&H


Development to four lanes with paved side shoulders of End of Patiala
Bypass to start of Sangrur Bypass of section NH-64(New NH NO-7)from
Name of Project
existing Km 64.570 to KM 106.170 in the state of Punjab

CLIENT:-Public Works Department( B&R) branch, Government of Punjab

CONSULTANT:-M/s STUP CONSULTANTS PVT LTD

CONTRACTOR:-M/s GAWAR CONSTRUCTION LTD


Percentage of fractured face of Aggregate
( As per MORT&H Section -500 )

SOURCE Mubharakpur TESTED AT at site Lab

DATE OF SAMPLING 28.07.2016 RANGE OF SIEVE 4.75 mm Ret.

DATE OF TESTING 31.07.2016 TYPE OF AGGREGATE Corase Aggregate

SAMPLE TAKEN 89+980 LHS MATERIAL USED FOR BC

Wt. of Sample before


Sample Wt. of Sample after removal
removal of Fractured face % of fractured face
No. of fractured face (gm)
(gm)

1 2 3= (1-2)/1x100

1 3246 110 96.6

2 4568 132 97.1

3 6548 138 97.9


Average = 97.20

REMARKS :-

CONTRACTOR'S REPRESENTATIVE CONSULTANT'S REPRESENTATIVE


GOVERNMENT OF PUNJAB
PUBLIC WORKS DEPARTMENT B&R BRANCH ON BEHALF OF MORT&H
Development to four lanes with paved side shoulders of End of Patiala
Bypass to start of Sangrur Bypass of section NH-64(New NH NO-7)from
Name of Project
existing Km 64.570 to KM 106.170 in the state of Punjab

CLIENT:-Public Works Department( B&R) branch, Government of Punjab

CONSULTANT:-M/s STUP CONSULTANTS PVT LTD

CONTRACTOR:-M/s GAWAR CONSTRUCTION LTD


DETERMINATION OF CLAY LUMPS ( DELETERIOUS MATERIAL )
( As per IS: 2386 ( Part II ) - 1963 )

SOURCE TESTED AT

DATE OF SAMPLING RANGE OF SIEVE

DATE OF TESTING TYPE OF AGGREGATE

SAMPLE TAKEN MATERIAL USED FOR

Wt. of Sample before


Sample Wt. of Sample after removal
removal of silt/clay lumps % of silt/clay lumps
No. ofsilt/ clay lumps (gm)
(gm)

1 2 3= (1-2)/1x100

4
Average =

REMARKS :-
CONTRACTOR'S REPRESENTATIVE CONSULTANT'S REPRESENTATIVE