Status of Boundary Wall as on 17.10.

2023
Sr. Construction LHS RHS Total Hindered
No Package Scope Compl. Balance Scope Compl. Balance Scope Compl. Balance Legth in Km Reasons
(in Km) (in Km) (in Km) (in Km) (in Km) (in Km) (in Km) (in Km) (in Km)
1 CP 01 27.917 25.849 2.068 30.251 27.740 2.511 58.168 53.589 4.579 0.000 Villagers Agitation, Opening for
villagers.
Villagers Agitation, Opening for
2 CP 02 66.660 63.140 3.520 58.339 55.194 3.145 124.999 118.334 6.665 6.100
villagers. Court cases.
3 CP 03 73.367 73.367 0.000 73.367 73.367 0.000 146.734 146.734 0.000 0.000
4
CP 04 51.409 51.147 0.262 51.409 50.371 1.038 102.818 101.518 1.300 1.300 Due to Farmer issues and protest

5 CP 05 47.145 40.625 6.520 47.040 41.680 5.360 94.186 82.305 11.880 6.455 Due to Farmers Agitation
6 CP 06 36.000 21.500 14.500 36.000 19.900 16.100 72.000 41.400 30.600 5.000 Due to Farmers Agitation
7 CP 07 46.260 40.500 5.760 46.260 40.500 5.760 92.520 81.000 11.520 2.041 Hindrance due to local issue
Farmer issues.
8 CP 08 42.720 42.220 0.500 42.720 42.620 0.100 85.440 84.840 0.600 0.600

9 CP 09 Forest Issues+Farmer's
53.588 45.104 8.484 52.711 43.178 9.533 106.299 88.282 18.017 16.297 Objection+Hilly
Constraint+GAIL excavated
ROW
10 CP 10 57.910 57.910 115.820 3.976 Local issues
11 CP 11 27.935 27.935 55.870 15.980
12 CP 12 54.353 54.353 108.706 5.171 Hindrance due to local public
issues.
13 CP 13 41.716 41.716 83.432 82.488 32.284 km length hindered by Local
Villagers / farmer's
14 CP 14 6.860 6.690 13.550

15 CP 15 22.250 22.250 44.500 Local Villagers obstructing the


work.
16 CP 16 30.790 30.790 61.580
Total 687.880 680.741 1368.622 143.760