You are on page 1of 1

7/12/2017 5:16:42 AM

Rural Water Supply And Sanitation Fund Development


Board Kathmandu, Nepal
Summary Cost
(Part II Construction Cost)

Scheme............. 102020 (Dhabgaad Budhauraa WSS) SO........ FriPAD

VDC/Muncipality. Narayanpur District... Dang

Description Total Board Comm. Comm. Kind


Cash
Water Supply
1. NON-LOCAL MATERIALS
1 Cement 15198 14826.59 371.41 0
2 GI Pipes 530.36 517.4 12.96 0
3 HDPE Pipes 700.7 683.58 17.12 0
5 Pipe Fittings and Valves 559217.22 545550.96 13666.26 0
7 Other Construction Materials 1016.71 991.86 24.85 0
Sub Total 576662.99 562570.38 14092.61 0

2. TRANSPORTATION
1 Transportation of non-local materials 3574.25 3486.9 87.35 0
Sub Total 3574.25 3486.9 87.35 0

3. SKILLED LABOR
1 Skilled Labor 8606.2 8395.88 210.32 0
Sub Total 8606.2 8395.88 210.32 0

4. UNSKILLED LABOR
1 Unskilled Labor for Construction 11917.5 0 0 11917.5
3 Unskilled Labor for Local Materials 10323 7509.87 188.13 2625
4 Unskilled Labor for Porterage 0 0 0 0
Sub Total 22240.5 7509.87 188.13 14542.5

5. OTHER COST
5. OTHER COST, IF ANY 650 633.75 16.25 0
Sub Total 650 633.75 16.25 0

Total of Water Supply 611733.94 582596.79 14594.65 14542.5

Grand Total 611733.94 582596.79 14594.65 14542.5

-9-