Professional Documents
Culture Documents
2 Miscellaneous (1%) 12 13 13 14 14 66
3 Contingency (1%) 12 13 13 14 14 66
Sr.
DESCRIPTION 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
No.
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
22 feeders 23 feeders 24 feeders 25 feeders 26 feeders 120 feeders Rs. 35 Works 35 Works 35 Works 35 Works 35 Works 175 Works
(11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV)
Sub-total KM 102 109 114 120 127 572 100% 448,940 478,545 501,397 525,482 555,086 2,509,450
3. 11 kV CAPACITORS
a. Fixed 11 kV 450 kVAR No. 6 6 6 6 6 30 30% 149,500 897 897 897 897 897 4,485
b. Switched 11kV 450 kVAR No. 14 14 14 14 14 70 70% 299,000 4,186 4,186 4,186 4,186 4,186 20,930
Sub-total No. 20 20 20 20 20 100 100% 5,083 5,083 5,083 5,083 5,083 25,415
MVAR 9 9 9 9 9 45
4. 11 kV PANELS No. 22 23 24 25 26 120 1,375,000 30,250 31,625 33,000 34,375 35,750 165,000
7. 11KV 500MCM CABLE S/C KM 4 4 4 4 4 18 5,519,235 19,869 19,869 19,869 19,869 19,869 99,345
(For use with 11kV Panels)
B. TOTAL (Item 1 to 7) COST OF H.T FDRS 552,244 591,376 615,603 644,639 675,618 3,079,480
IESCO POWER DISTRIBUTION REHABILITATION BILL OF QUANTITIES AND COST ESTIMATES
Page 2 of 5
QUANTITIES TOTAL COST (Thousand Rs.)
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
No. RATE
11 kV Lines
Sub-total KM 2 2 2 2 2 10 17 17 17 25 25 101
H Total Cost (Including material cost) 680,816 728,768 758,918 795,042 833,209 3,796,753
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
269 285 300 315 331 1500 Rs. 269 285 300 315 331 1500
LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals Proposals Proposals Proposals Proposals Proposals Proposals
Sub-total No. 162.0 171.0 180.0 189.0 198.0 900.0 100% 203,551 213,859 225,529 237,199 247,505 1,127,643
Sub-total No. 107.0 114.0 120.0 126.0 133.0 600.0 100% 132,702 141,086 148,958 156,830 165,212 744,788
11 NEW 11 kV LINES
Rabbit (Required with Additional D/TF) KM 54 57 60 63 66 300 1,233,319 66,599 70,299 73,999 77,699 81,399 369,995
for Extension of Line
Sub-total KM 54 57 60 63 66 300 66,599 70,299 73,999 77,699 81,399 369,995
a. 3-Phase WASP Line KM 18 19 20 21 22 100 30% 1,474,483 26,541 28,015 29,490 30,964 32,439 147,449
b. 3-Phase ANT Line KM 36 38 40 42 44 200 60% 1,016,683 36,601 38,634 40,667 42,701 44,734 203,337
c. 1-Phase ANT Line KM 6 6 7 7 7 33 10% 933,360 5,600 5,600 6,534 6,534 6,534 30,802
13. LT CAPACITORS
Sub-total No. 109 114 120 126 133 602 240 252 266 278 294 1,330
a. 3-Phase -WASP KM 11 11 12 13 13 60 80% 756,000 8,316 8,316 9,072 9,828 9,828 45,360
b. 3-Phase -ANT KM 3 3 3 3 3 15 20% 298,200 895 895 895 895 895 4,475
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
269 285 300 315 331 1500 Rs. 269 285 300 315 331 1500
LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals Proposals Proposals Proposals Proposals Proposals Proposals
15 PVC CABLES
A. For Coustomers
a. Twin core 7/0.052 KM 27 29 30 32 33 151 75% 88,000 2,376 2,552 2,640 2,816 2,904 13,288
b. Four core 19/0.052 KM 5 6 6 6 7 30 15% 340,443 1,702 2,043 2,043 2,043 2,383 10,214
16 CONNECTORS
a. 1-Phase (S-117) No. 9450 9975 10500 11025 11550 52500 70% 90 851 898 945 992 1,040 4,726
b. 3-Phase (S-157) No. 4050 4275 4500 4725 4950 22500 30% 95 385 406 428 449 470 2,138
Sub-total No. 13500 14250 15000 15750 16500 75000 100% 1,236 1,304 1,373 1,441 1,510 6,864
M TOTAL (Item 8 to 16) COST OF L.T PROPOSALS 489,355 515,851 544,462 572,224 598,633 2,720,525
a. LT Lines
- Ant (New Wasp) KM 2.6 2.6 2.9 3.1 3.1 14.3 8,000 21 21 23 25 25 115
- Gnat (New Ant) KM 0.7 0.7 0.7 0.7 0.7 3.6 5,000 4 4 4 4 4 20
Sub-total KM 3 3 4 4 4 18 25 25 27 29 29 135
b. Transformers
- 25 kVA (New 50 kVA) Retirement No. 5 6 6 6 7 30 50,000 250 300 300 300 350 1,500
- 50 kVA (New 100 kVA) Replacement No. 22 23 24 25 26 120 70,000 1,540 1,610 1,680 1,750 1,820 8,400
- 100 kVA (New 200 kVA) Replacement No. 16 17 18 19 20 90 100,000 1,600 1,700 1,800 1,900 2,000 9,000
O Total Cost (Including material cost) 501,147 528,177 557,544 585,974 612,917 2,785,758
17 ENERGY METERS
18. VEHICLES
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
22 feeders 23 feeders 24 feeders 25 feeders 26 feeders 120 feeders Rs. 35 Works 35 Works 35 Works 35 Works 35 Works 175 Works
(11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV) (11 KV)
a. Osprey KM 32 34 36 38 40 180 15% 4,768,002 152,576 162,112 171,648 181,184 190,720 858,240
b. Dog KM 32 34 36 38 40 180 15% 1,526,269 48,841 51,893 54,946 57,998 61,051 274,729
c. Rabbit KM 22 23 24 25 26 120 10% 1,233,319 27,133 28,366 29,600 30,833 32,066 147,998
d. 11KV 500MCM S/C CABLE KM 129 137 144 151 158 719 60% 5,519,235 711,981 756,135 794,770 833,404 872,039 3,968,329
Sub-total KM 215 228 240 252 264 1199 100% 940,531 998,506 1,050,964 1,103,419 1,155,876 5,249,296
3. 11 kV CAPACITORS
a. Fixed 11 kV 450 kVAR No. 6 6 6 6 6 30 30% 149,500 897 897 897 897 897 4,485
b. Switched 11kV 450 kVAR No. 14 14 14 14 14 70 70% 299,000 4,186 4,186 4,186 4,186 4,186 20,930
Sub-total No. 20 20 20 20 20 100 100% 5,083 5,083 5,083 5,083 5,083 25,415
MVAR 9 9 9 9 9 45
4. 11 kV PANELS No. 45 48 50 53 55 251 1,375,000 61,875 66,000 68,750 72,875 75,625 345,125
7. 11KV 500MCM CABLE S/C KM 8 8 8 8 8 38 5,519,235 41,394 41,394 41,394 41,394 41,394 206,970
(For use with 11kV Panels)
B. TOTAL (Item 1 to 7) COST OF H.T FDRS 1,156,791 1,221,524 1,282,251 1,346,983 1,405,765 6,413,314
IESCO POWER DISTRIBUTION REHABILITATION BILL OF QUANTITIES AND COST ESTIMATES
Page 2 of 5
QUANTITIES TOTAL COST (Thousand Rs.)
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
No. RATE
11 kV Lines
Sub-total KM 4 4 4 4 5 21 41 41 41 41 49 213
H Total Cost (Including material cost) 1,417,524 1,496,596 1,571,034 1,650,365 1,723,002 7,858,522
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
269 285 300 315 331 1500 Rs. 269 285 300 315 331 1500
LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals Proposals Proposals Proposals Proposals Proposals Proposals
Sub-total No. 107.0 114.0 120.0 126.0 133.0 600.0 100% 132,702 141,086 148,958 156,830 165,212 744,788
11 NEW 11 kV LINES
Rabbit (Required with Additional D/TF) KM 54 57 60 63 66 300 1,233,319 66,599 70,299 73,999 77,699 81,399 369,995
for Extension of Line
Sub-total KM 54 57 60 63 66 300 66,599 70,299 73,999 77,699 81,399 369,995
a. 3-Phase WASP Line KM 18 19 20 21 22 100 30% 1,474,483 26,541 28,015 29,490 30,964 32,439 147,449
b. 3-Phase ANT Line KM 36 38 40 42 44 200 60% 1,016,683 36,601 38,634 40,667 42,701 44,734 203,337
c. 1-Phase ANT Line KM 6 6 7 7 7 33 10% 933,360 5,600 5,600 6,534 6,534 6,534 30,802
13. LT CAPACITORS
Sub-total No. 109 114 120 126 133 602 240 252 266 278 294 1,330
a. 3-Phase -WASP KM 11 11 12 13 13 60 80% 756,000 8,316 8,316 9,072 9,828 9,828 45,360
b. 3-Phase -ANT KM 3 3 3 3 3 15 20% 298,200 895 895 895 895 895 4,475
Sr. DESCRIPTION UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL Ratio UNIT 2022-23 2023-24 2024-25 2025-26 2026-27 TOTAL
269 285 300 315 331 1500 Rs. 269 285 300 315 331 1500
LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals LT Proposals Proposals Proposals Proposals Proposals Proposals Proposals
15 PVC CABLES
A. For Coustomers
a. Twin core 7/0.052 KM 27 29 30 32 33 151 75% 88,000 2,376 2,552 2,640 2,816 2,904 13,288
b. Four core 19/0.052 KM 5 6 6 6 7 30 15% 340,443 1,702 2,043 2,043 2,043 2,383 10,214
16 CONNECTORS
a. 1-Phase (S-117) No. 9450 9975 10500 11025 11550 52500 70% 90 851 898 945 992 1,040 4,726
b. 3-Phase (S-157) No. 4050 4275 4500 4725 4950 22500 30% 95 385 406 428 449 470 2,138
Sub-total No. 13500 14250 15000 15750 16500 75000 100% 1,236 1,304 1,373 1,441 1,510 6,864
M TOTAL (Item 8 to 16) COST OF L.T PROPOSALS 489,355 515,851 544,462 572,224 598,633 2,720,525
a. LT Lines
- Ant (New Wasp) KM 2.6 2.6 2.9 3.1 3.1 14.3 8,000 21 21 23 25 25 115
- Gnat (New Ant) KM 0.7 0.7 0.7 0.7 0.7 3.6 5,000 4 4 4 4 4 20
Sub-total KM 3 3 4 4 4 18 25 25 27 29 29 135
b. Transformers
- 25 kVA (New 50 kVA) Retirement No. 5 6 6 6 7 30 50,000 250 300 300 300 350 1,500
- 50 kVA (New 100 kVA) Replacement No. 22 23 24 25 26 120 70,000 1,540 1,610 1,680 1,750 1,820 8,400
- 100 kVA (New 200 kVA) Replacement No. 16 17 18 19 20 90 100,000 1,600 1,700 1,800 1,900 2,000 9,000
O Total Cost (Including material cost) 501,147 528,177 557,544 585,974 612,917 2,785,758
17 ENERGY METERS
18. VEHICLES