(Year wise plans and costs for 2023-24 to 2027-28 and details of plans & BOQs as Annexures)
The Summary of Expansion and Rehabilitation (Optimally Achievable Case) of Distribution System
11kV Network & below is presented in tables below:
DIIP 15 (a) – Distribution System Expansion (Best Case)
Quantities
2024-25
2025-26
2023-24
2026-27
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of proposals Nos 45 48 50 53 55 251
Length of new HT line Km 215 228 240 252 264 1199
1 New LT Lines
Number of Proposals Nos 269 285 300 315 331 1500
2024-25
2025-26
2023-24
2026-27
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of proposals Nos 22 23 24 25 26 120
Length of new HT line Km 102 109 114 120 127 572
2 Transformers (New)
a. 50 KVA Nos 8 9 9 9 10 45
b. 100 KVA Nos 32 34 36 38 40 180
c. 200 KVA Nos 24 26 27 28 30 135
d. others KVA Nos 98 102 108 114 118 540
Sub Total Nos 162 171 180 189 198 900
3 11 KV Capacitors
a. Fixed 450 KVAR Nos 6 6 6 6 6 30
b. Fixed 900 KVAR Nos - - - - - -
c. Others Nos 14 14 14 14 14 70
Sub Total Nos 20 20 20 20 20 100
4 11 KV Panel Nos 25 25 25 25 25 125
1 New LT Lines
Number of Proposals Nos 269 285 300 315 331 1500
2024-25
2025-26
2023-24
2026-27
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of proposals Nos 20 21 22 23 24 110.0
Length of new HT line Km 613 674 742 816 897 3742
1 New LT Lines
Number of Proposals Nos 2811 3092 3401 3741 4116 17161
2025-26
2023-24
2026-27
2027-28
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of proposals Nos 400 422 444 466 488 2220
Length of new HT line Km 144 152 160 168 176 800
1 New LT Lines
Number of Proposals Nos 400 422 444 466 488 2220
2025-26
2023-24
2026-27
2027-28
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of proposals Nos 3060 3230 3400 3570 3740 17000
Length of new HT line Km 430 308 339 373 410 1859
1 New LT Lines
Number of Proposals Nos
2025-26
2023-24
2026-27
2027-28
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of proposals Nos 400 422 444 466 488 2220
Length of new HT line Km 144 152 160 168 176 800
1 New LT Lines
Number of Proposals Nos
Quantities
2023-24
2026-27
2027-28
2024-25
2025-26
Description Unit
Total
A. Scope of Work for 11 kV and Below Rehabilitation
1 Rehabilitation of HT Lines
Number of proposals Nos 63 67 70 74 77 350
Bifurcation Km 424 448 473 496 520 2361
Reconductoring Km 236 247 261 274 287 1305
2 Replacement of Overloaded Transformers / Extension
a. 50 KVA Nos 252 266 280 294 308 252
b. 100 KVA Nos 348 367 387 406 425 348
c. 200 KVA Nos 223 235 247 260 272 223
d. others KVA Nos 35 36 39 40 43 193
Sub Total Nos 858 904 953 1000 1048 858
3 Replacement of Over loaded Transformers /Augmentation
a. 50 KVA Nos 15 16 17 18 18 84
b. 100 KVA Nos 47 50 52 55 58 262
c. 200 KVA Nos 89 94 99 104 108 494
d. others KVA Nos - - - - - -
Sub Total Nos 151 160 168 177 184 840
Replacement of 11 KV
4 Nos 34 36 38 40 42 190.0
Panel
B. Scope of Work for LT ExpansionRehabilitation
1 New LT Lines
Number of Proposals Nos 1009 1064 1121 1177 1232 5603
Reconductoring of
Km 261 277 291 305 320 1454
new LT line
DIIP 16 (b) – Distribution System Rehabilitation (Optimal Case)
Quantities
2023-24
2026-27
2027-28
2024-25
2025-26
Description Unit
Total
A. Scope of Work for 11 kV and Below Rehabilitation
1 Rehabilitation of HT Lines
Number of proposals Nos 34 36 38 40 42 190
Bifurcation Km 231 243 256 268 281 231
Reconductoring Km 128 135 141 148 156 708
2 Replacement of Overloaded Transformers / Extension
a. 50 KVA Nos 252 266 280 294 308 1400
b. 100 KVA Nos 348 367 387 406 425 1933
c. 200 KVA Nos 223 235 247 260 272 1237
d. others KVA Nos 35 36 39 40 43 193
Sub Total Nos 858 904 953 1000 1048 4763
3 Replacement of Over loaded Transformers /Augmentation
a. 50 KVA Nos 15 16 17 18 18 84
b. 100 KVA Nos 47 50 52 55 58 262
c. 200 KVA Nos 89 94 99 104 108 494
d. others KVA Nos - - - - - -
Sub Total Nos 151 160 168 177 184 840
Replacement of 11 KV
4 Nos 34 36 38 40 42 190
Panel
B. Scope of Work for LT ExpansionRehabilitation
1 New LT Lines
Number of Proposals Nos 1009 1064 1121 1177 1232 5603
Reconductoring of
Km 221 234 246 259 271 1231
new LT line
Detail of BOQ is attached in Annexure – IX
The Distribution Expansion Plan for Village Electrification, Deposit Works, Vehicles, T&P, Civil
Works and GIS Plan are same in both best and optimal cases. However, the summary is
presented on prescribed formats below:
DIIP 15 (e) – Distribution System Expansion –Vehicles, T&P & Civil Works (Best Case)
DIIP 16 (e) – Distribution System Expansion –Vehicles, T&P & Civil Works (Optimal Case)
Quantities
Sr.
2023-24
2024-25
2026-27
2025-26
2027-28
No Description Unit
. Total
1 Vehicles *
a. Officers Transport Policy Nos
b. Heavy Vehicles (Trucks) Nos
c. Light Vehicles Nos
d. Bucket Mounted Trucks Nos
e. Motor cycles Nos
f. Jeeps (4x4) Nos
i. Light Vehicle (Pickup
Nos
Shehzore)
Sub Total
2 Tools & Plants (T&P)
a. Instrument and Test
Nos
Equipment
b. Special Tools Nos
c. Mechanical Plants
Nos The Detail BOQ is presented in section
(generators, welding plants etc.)
6-A-(xiii)
d. LM & ALM Tools other than
Nos
personal protective equipment
i. Others Nos
Sub Total
3 List of New Offices *
New Grid Stations * No.
New GSO Circle No.
P&I Divisions No.
SS & T Divisions No.
Operation Sub Divisions No.
Operation Divisions No.
Revenue Offices No.
Operation Circles No.
Construction Circle No.
Construction Divisions No.
AE Transmission SS&TL No.
AE Maintenance Grids No.
Other offices No.
Annexure: Detailed BOQs of all plans
ii. CAPITAL EXPENDITURE AND ADDITIONAL OPERATING COSTS FOR EXPANSION AND
REHABILITATION OF DISTRIBUTION SYSTEM
Million Rs.
Total (A+B+C)
Year
Sr. Description Unit
No. Total
2025-26
2024-25
2026-27
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of
Mil 1418 1497 1571 1650 1723 1418
proposals
Length of new HT
Mil 941 999 1051 1103 1156 5249
line
2 Transformers (New)
a. 50 KVA Mil 6 6 6 6 7 32
b. 100 KVA Mil 23 24 25 27 28 127
c. 200 KVA Mil 24 26 27 28 30 137
d. others KVA Mil 151 157 166 176 182 832
Sub Total Mil 204 214 226 237 248 1128
3 11 KV Capacitors
a. Fixed 450 KVAR Mil 1 1 1 1 1 4
b. Fixed 900 KVAR Mil
c. Others/Switched Mil 4 4 4 4 4 21
Sub Total Mil 5 5 5 5 5 25
4 11 KV Panel Mil 62 66 69 73 76 345
1 New LT Lines
Number of Mil
501 528 558 586 613 2786
Proposals
Length of new LT Mil
69 72 77 80 84 382
line
2 LT Capacitors
Different KVARs Mil 0.2 0.3 0.3 0.3 0.3 1.3
DIIP 36 (a) - Distribution System Expansion (Optimal Case)*
Cost in MRs.
2023-24
2025-26
2024-25
2026-27
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Expansion*
1 New HT Lines
Number of
Mil
proposals
Length of new HT
Mil
line
2 Transformers (New)
a. 50 KVA Mil
b. 100 KVA Mil
c. 200 KVA Mil
d. others KVA Mil
Sub Total Mil
3 11 KV Capacitors
a. Fixed 450 KVAR Mil
b. Fixed 900 KVAR Mil
c. Others/Switched Mil
Sub Total Mil
4 11 KV Panel Mil
1 New LT Lines
Number of Mil
Proposals
Length of new LT Mil
line
2 LT Capacitors
Different KVARs Mil
2026-27
2023-24
2025-26
2027-28
Description Unit
Total
Cost in MRs.
2024-25
2026-27
2023-24
2025-26
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Rehabilitation
1 Rehabilitation of HT Lines
Number of
Mil 1,500 1,658 1,823 1,993 2,197 9,171
proposals
Bifurcation Mil 763 804 846 884 930 4226
Reconductoring Mil 270 289 301 315 333 1508
Rerouting Mil
2 Replacement of Overloaded Transformers
a. 50 KVA Mil 177.6 187.4 197.3 207.2 217.0 986.6
b. 100 KVA Mil 245.2 258.6 272.7 286.1 299.5 1362.2
c. 200 KVA Mil 226.3 238.5 250.6 263.8 276.0 1255.2
d. others KVA Mil 36.4 36.9 40.5 41.0 44.6 199.4
Sub Total Mil 685.5 721.4 761.1 798.1 837.1 3803.3
3 Replacement of Defective/Burnt Transformers
a. 50 KVA Mil 7.6 8.1 8.7 9.2 9.2 42.8
b. 100 KVA Mil 32.9 35.0 36.4 38.5 40.6 183.2
c. 200 KVA Mil 89.8 94.9 99.9 105.0 109.0 498.6
d. others KVA Mil
Sub Total Mil 130.3 138.0 145.0 152.6 158.7 724.7
Mil
4 11 KV Panel 47 50 52 55 58 261
B. Scope of Work for LT Expansion
1 New LT Lines
Number of Mil
511 566 627 692 760 3,156
Proposals
Reconductoring of Mil
9.2 9.2 10.0 10.7 10.7 49.8
new LT line
Annexure: Detailed BOQs of all plans
2026-27
2023-24
2025-26
2027-28
Description Unit
Total
2024-25
2026-27
2023-24
2025-26
2027-28
Description Unit
Total
A. Scope of Work for 11 kV and Below Rehabilitation
1 Rehabilitation of HT Lines
Number of
Mil 246 260 273 287 300 1366
proposals
Bifurcation Mil 195 205 216 227 238 1080
Reconductoring Mil
Rerouting Mil
2 New Transformers
a. 50 KVA Mil 28 30 31 33 35 156
b. 100 KVA Mil 23 24 25 26 27 125
c. 200 KVA Mil
d. others KVA Mil 167 176 185 195 204 927
Sub Total Mil 218 230 242 254 266 1209
3 Replacement of Defective/Burnt Transformers
a. 50 KVA Mil
b. 100 KVA Mil
c. 200 KVA Mil
d. others KVA Mil
Sub Total Mil
Mil
4 11 KV Panel
B. Scope of Work for LT Expansion
1 New LT Lines
Number of Mil
961 1014 1069 1122 1176 5343
Proposals
Addition of new Mil
576 608 642 673 706 3205
LT line
2026-27
2023-24
2025-26
2027-28
Description Unit
Total
The Above O&M expense includes Repair and Maintenance Expenses also. The escalation has been
assumed generally and will be calculated based on the MYT issued by NEPRA. For details of
proposed escalation formula please refer to the MYT petition.
DIIP-46 FINANCING PLAN SOURCES OF FINANCING
Sub
Total
Functional Plans
Public
Distribution Expansion
Contribution
a) TANGIBLE BENEFITS
Additional Sales - GWh
Description 2023-24 2024-25 2025-26 2026-27 2027-28
Domestic
Commercial
Industrial
Agricultural
Other
TOTAL Sales
(Rehabilitation &
Expansion)
Expected Sales due to
Rehabilitation Plan
Expected Sales Due to
Expansion Plan
Technical
Commercial
a) NON-TANGIBLE BENEFITS