CONCERETE REPORT

Comp. Qty. From 27 Comp. Qty.


Sr.No Structure Name Req. Qty upto 26 Dec Dec to 02 upto 02 Dec Balance
2020 Dec 2021 2021

1 LimeStone Crusher House 2233 2222.8 2222.8 10.2


2 LimeStone Storage & Transport 1811 1810 1810 1
3 Additive & Coal Storage & Transport 4055 4198.15 4198.15 (+)135.55
4 Raw Mill Feed Hopper 350 374.3 374.3 (+)24.3
5 Raw Mill building 3004 3100.3 3100.3 (+)95.3
6 Coal mill Buildng 1165 1167.2 1167.2 (+2.2)
7 Raw Mill Silo 1746 1845.2 1845.2 (+) 99.2
8 Preheater 3238 3217.7 3217.7 43.9
9 Kiln Pier 634 661.7 661.7 (+) 14.7
10 Alkali Bypass 218 255 255 (+) 37
11 Clinker Cooler 1877 1800.4 1800.4 76.6
12 Clinker & low Alkali Silo 5626 5459.7 5459.7 166.3
13 Cement Mill Feed Hopper 957 945 945 12
14 Gypsum Intake & Crusher 613 603 1 604 9
15 Cement Mill building & Bag House 1695 1676 1676 19
16 Cement Silo 3040 3002 3002 38
17 Packing Plant 1478 1483.7 40 1523.7 (+)45.2
18 Switch Yard 112 205.6 205.6 (+)83
19 MRSS Building 242 331.2 331.2 (+)69.3
20 LC-1 162 186.9 186.9 (+)69.1
21 LC-4 432 459.5 459.5 (+)27.5
22 LC-5 162 178 178 (+)38
23 CCR Building 1183 1280.5 1280.5 (+)97.5
24 Cable gallery 445 438 438 7
25 TT-1 61 66 66 (+)5
26 TT-2 56 58.2 58.2 2.2
27 TT-3 120 121 121 (+)1
28 TT-4 146 154 154 (+) 8
29 TT-5 144 143 143 1
30 Conveyor 744 930 930 (+)42
31 WHRS (PH Boiler) 447 407.3 407.3 39.7
32 WHRS (Cooler Area) 164 164 164 0
33 TG Building 757 882.6 882.6 (+)206.2
34 Water Tank 369 323 323 46
35 Raw Water Tank 3100 0 1376 1376 1724
36 Compressor Room 165 199.8 199.8 (+)61.3
37 Cooling Tower 452 168.8 168.8 283.2
38 Weigh Bridge 20 20 20 0
Total 43223.00 40539.55 1417.00 41956.55 878.10
Miscellaneous manpo
Present Manpower at
% of work % of work
Completed on Completed on
02.01.2021 26.12.2020

99.54 99.54
99.94 99.94
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
99.37 99.37
100.00 100.00
100.00 100.00
95.92 95.92
97.04 97.04
98.75 98.75
98.53 98.37
98.88 98.88
98.75 98.75
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
98.43 98.43
100.00 100.00
103.93 103.93
100.83 100.83
100.00 100.00
99.31 99.31
100.00 100.00
100.00 100.00
100.00 100.00
100.00 100.00
87.53 87.53
44.39
100.00 100.00
37.35 37.35
100.00 100.00
96.276 97.67