University of Engineering & Technology, Mardan

Department of Computer Software Engineering

Semester: 7th Examination: Final-Term (Fall 2021) Total Time: 2 Hours


Subject: SE-402 Software Project Management Marks: 50

Note: Attempt All Questions.

Q1: (Marks: 7+8 = 15) [CLO-2, PLO-11, C5]


a. Justify with the help of an example how a Software Quality Assurance group uses
Formal Technical Review for improving overall quality of a software.
b. Rate the different types of costs associated with assuring good quality software.

Q2: (Marks:5+5=10) [CLO-4, PLO-11, TL-C4]


a. Given Risk:
Only 80% of the software components scheduled for reuse will, in fact, be
integrated into the application. The remaining functionality will have to be custom
developed. 200 reusable software components were planned. Cost of each reusable
software component is $10 each.

Risk Probability – 70% likely.

Estimate the Risk Exposure for the given risk.

b. Justify the questions raised by the experienced software projects managers while
assessing overall projects risks with the help of examples.

Q3: (Marks: 7+8=15) [CLO-4, PLO-11, C5]

c. Justify the reasons for baseline in software configuration management with


examples.
a. Defend the steps involved are necessary for change control process.

Q4: (Marks: 5+5=10) [CLO-3, PLO-9, TL-C3]

a. Experiment with the relationship between people and effort for work
accomplishment with the help of an example.
a. Although adding people to a late software project can make it later, identify and
explain the circumstances in which this is not true.

Page 1 of 1