??????? Refinery,
Hydroprocessing Project Rev: 2
Sheet: 1 of 10
Quality control and inspection plan for Mechanical Installation Of Compressors, Generators, Pumps, Fans and Blowers
Testing requirements:
H= SUSPENSION OF WORKS. Activities, which shall not be carried out without Contractor’s approval or other party’s approval. Notification about
inspection time (XX hrs)
W = OBSERVANCE. Inspections, measurement, and testing of performing works, and it is required to test their conformance to the project. Notification
about inspection time (XX hrs).
QS = QUALITY SUPERVISION. Continuous monitoring over the work.
RD = DOCUMENTS REVIEW. To check documents conformance to the project
№ Description of Type of Acceptance criteria Reference to Processing Inspection participants
п/п inspections and testing control normative documents
documents SC C Comp. Others
Verify provision of necessary tools,
equipment & consumables for site
assembly, erection and installation
and inspection activities
16870-00-SP-868
Verify provision of match marking 8485-000-FM-934
Vendor Installation,
on parts to be site installed 8485-000-FM-9J0
Document Operation &
Inspection of vendor supplied Control Maintenance Manual
Verify equipment not damaged and
items at warehouse or Attachment 1 GOST
1 that there is no damage to H H
designated lay down area Vendor initial site 24297, forms 12,13,14,
Visual Control equipment painting
prior to installation storage details.
VSN-478
Verify items at site suitably
supported, packed and preserved Equipment certificate
(where required)
wherever necessary
Verify readiness of equipment
VSN 478-36
foundation prior to start installation.
Release for equipment installation
Verify nameplate data/equipment Vendor drawings
All nameplate data and Visual Control tags in
5 equipment tags in accordance accordance with vendor data and W W
16870-00-SP-868 sec 6
with vendor data.
specification requirements
Verify that cold galvanizing touch- Vendor drawings.
Cold galvanizing/paint up or
repairs made to all areas Visual Control paint touch up has been performed .
16870-00-SP-868 sec 21
6 which will become and W W
Vendor painting
inaccessible after erection, as
inspected prior to installing the procedures
applicable
equipment
Verify shims correct size
.
Verify slide plates installed, if
applicable. Project Area Plot
Plans.
Document Verify leveling plates (if applicable)
Pre-erection preparation & 16870-00-SP-868
7 Control H/RD H/RD
complete. jackscrew pads (if applicable)
grouted in Vendor drawings &
procedures
Verify grouting pads placed for
equipment is being set on
foundations, if applicable.
8485-000-FM-949
Complete final visual inspection 8485-000-FM-950
8485-000-FM-951
Verify all inspection/test
requirements 8485-000-FM-952
completed and conformant. 8485-000-FM-953
8485-000-FM-954
Verify re-instatement of inert gas
(Nitrogen) blanket, where 8485-000-FM-958
applicable, and test for specified Vendor drawings. 8485-000-FM-960
Visual Control Oxygen levels (where required) Vendor Installation,
20 Final inspection 8485-000-FM-961 W W
Operation &
Verify “post installation” Maintenance Manual. 8485-000-FM-955
preservation at site complies with
8485-000-FM-956
requirements
8485-000-FM-9H4
Punch list outstanding items 8485-000-FM-9H6
Mechanical installation released for 8485-000-FM-9H7
Hydro testing and commissioning as 8485-000-FM-9H8
applicable. 8485-000-FM-9H9
8485-000-FM-9F3
21 Verify all documentation as Document Check all forms verified, signed by 8485-000-PR-920 Mechanical Equipment W/RD W/RD
per design and Norms and Control all parties Completion Package
compiled in equipment Verify as-built documentation(red
mechanical completion line mark up drawings, vendor
package manuals, etc) is present
Verify relevant equipment
installation check list and
equipment installation acceptance
Project: 8485-XXXXXXX
??????? Refinery,
Hydroprocessing Project Rev: 2
Sheet: 10 of 10
REMARKS