You are on page 1of 4

Inspection & Test plan - Installation of fan coil units

Doc. No.: AAC-1719-ITP-HVAC-003 REV. 02 Date: 21/08/13


RESPONSIBILTY INSPECTION & ACCEPTABLE
ACTIVITY ACTIVITY DESCRIPTION CONTROL PROCEDURE / FREQUENCY VERIFYING
NO. SPECIFICATION PARTY DOCUMENT AAC KITTCO EHAF
1 Material
Ensure FCU's to be delivered are as as per approved Material Project Engineer After Receiving Material
per the approved material submittal Submittal & equipment QC Inspection
1.1 H W R
& equipment schedule schedule. Engineer Request

Inspection of Materials upon receipt as per approved Material Project Engineer After Receiving Material
at site. Submittal & project QC Inspection
1.2 specification ( SECTION Engineer Request H H I
23 82 19)

Proper storage on the site. as per approved Material Project Engineer After Receiving Material
Submittal & project QC Inspection
1.3 specification ( SECTION Engineer Request S S S
23 82 19)

2 Drawings
Aprroved Drawings to be used as per approved Shop Project During Approved
Drawing & Project Engineer QC Installatio Shop Drawing
2.1 Specification ( SECTION 23 Engineer n H W R
82 19)

3 Installation
approved
Approved Method shop drawings
Statement , Aprroved Installation
Installation of FCU is coordinated Project During
3.1 Shop Drawing & Checklist H H S
with other services. Engineer QC Installation
Approved equipment Engineer
schedule

3
approved shop
drawings
Approved Method Statement Project Engineer During Installation
3.2 Installation of support and hanger. H H S
& Aprroved Shop Drawing QC Engineer Installation Checklist

3
Inspection & Test plan - Installation of fan coil units

Doc. No.: AAC-1719-ITP-HVAC-003 REV. 02 Date: 21/08/13


RESPONSIBILTY INSPECTION & ACCEPTABLE
ACTIVITY ACTIVITY DESCRIPTION CONTROL PROCEDURE / PARTY FREQUENCY VERIFYING
NO. SPECIFICATION DOCUMENT AAC KITTCO EHAF
approved shop
Installation of fcu units at proper Approved Method drawings
Project Engineer During Installation
3.3 location and level with proper slope Statement & Aprroved H H S
QC Engineer Installation Checklist
in direction of CDP network Shop Drawing

Approved shop drawings, approved shopp


approved method statement drawings
& Project specification Project Engineer During Installation
3.4 Installation of vibration isolators ( SECTION 23 82 19). Checklist H H S
QC Engineer Installation

Approved shop drawings, approved shopp


approved method statement, drawings
Equipment Schedule & Project Engineer During Installation
3.5 Installation of FCU Project specification Checklist H H I
QC Engineer Installation
( SECTION 23 82 19).

4 Inspection
Approved shop drawings, Work
approved method statement, Inspection
Equipment schedule and Air Request,
balancing as per Project Engineer Installation
4.1 Final installation inspection of FCU specification ( SECTION 23 After Installation Checklist H H I
QC Engineer
82 19)

LEGEND: H- Hold Point (WIR to be issued but work cannot proceed without approval of concerned authority
) W- Witness Point (WIR to be issued but work can proceed without approval of concerned authority
) S- Survelliance (No WIR required, activity subject to monitering)
R - Review(Record/Document Review)

3
I - Inspection

You might also like