Professional Documents
Culture Documents
LESSON PLAN
CRANE OPERATIONS
NCOO-B01
A16ACX1
REVISED 02/02/2012
1
INTRODUCTION (10 MIN)
(ON SLIDE # 1)
(ON SLIDE # 2)
INSTRUCTOR NOTE
(ON SLIDE # 3)
3. LEARNING OBJECTIVE(S):
2
(2) Provided a MAC 50, an engineer equipment requirement,
attachments, tools, engineer equipment records and forms, and
references, operate the Marine All-Terrain Crane (MAC 50) to
safely meet operational requirements with no injury to personnel
or damage to the equipment per the references.
(1345-XENG-2005)
(ON SLIDE # 4)
3
of reference, perform operation checks (before, during, and
after) per the TM 11262A-OR/3. (1345-XENG-2005c)
INSTRUCTOR NOTE
4
(ON SLIDE # 6)
(ON SLIDE # 7)
(ON SLIDE # 8, 9)
5
a. To ensure a safe lift, the operator will verify the
following prior to the lift:
INSTRUCTOR NOTE
6
(1) They are softer and wider than chain or wire rope
slings preventing them from damaging items being lifted.
(4) They are elastic and can stretch under load which
absorbs shock and cushions the load.
e. Disadvantages are:
7
the loop around both “live” and “dead” ropes with the first
clip. Extend the “dead” end of the wire rope along the “live”
end placing clips every 10 to 12 inches for at least 3 feet
leaving a 6 inch tail off the end of the last clip. A locally
fabricated wire rope sling only has 75% of the original lifting
capacity of the wire rope and should never be used to attempt a
max lift on any crane. Therefore, a wire rope that has a
vertical strength of 1000 lbs is reduced to 750 lbs on a
fabricated sling. ALWAYS test your wire rope sling assembly with
a test weight in a safe environment, upon completion of the test
retighten the wire rope clips. Only someone with rigging
experience should make a wire rope sling.
8
________________________________________________________________
________________________________________________________________
________________________________________________________________
(2) Make sure you inspect the crane at the start of each
work day.
(2) Check all gauges for proper readings and listen for
any unusual noises.
(2) Has the roadway to the job site been inspected to make
sure it's safe?
9
(ON SLIDE # 15)
daily
10 ft.
(1) If you do not know the load weight, do not use the load
indicator (SLI) in the crane.
10
(ON SLIDE # 48)
11
(10) Never position a crane close to embankments or
ditches. The weight of the machine, the added weight of the
load, and load movement can cause the embankment to collapse.
(3) Using a short boom length at both high and low boom
angle. This chart (see Power Point) shows approximately what
percentage of lift capacity is lost when the crane is one, two,
or three degrees off level.
(2) After the outriggers are fully out and fully down,
raise only the outriggers needed to level the crane according to
the level indicator. Insure that the tires are off the ground.
12
(3) Remember, you are leveling the turntable. The wheels
and tires may not be level after leveling the turntable.
d. Correct parts of line reeved between the boom head and the
hook block. Is an important thing to consider when making a safe
lift is to have:
(1) Use the cable capacity load chart, for the parts of
line required to handle the weight of the load.
(6) When reeved with odd number parts of line, the hook
block will appear slightly out of level.
13
g. Any change in the setup must be within load chart limits.
level
(BREAK 10 MIN)
14
TRANSITION: We have just the covered the safety procedures. If
there is no further question, let’s move on to the proper
handling of a load.
________________________________________________________________
________________________________________________________________
________________________________________________________________
15
(2) Prior to the lift, discuss the signals you will be
using to avoid any confusion.
g. Always keep the load near the crane and as close to the
ground as the terrain permits, especially on loads near
capacity.
16
(2) When using guy lines, never wrap the line around a
part of the body since the line may have to be released quickly.
17
(ON SLIDE # 96)
Occurs when the hook block collides with the boom head.
18
(ON SLIDE # 99)
a. Parts of Line:
b. Boom Angle:
d. Boom length:
19
(ON SLIDE # 103)
(a) Asphalt.
(b) Gravel.
(c) Earth/Loam.
(b) Sand.
20
(c) Uneven terrain.
capacity?
1 Parts of line.
2 Boom angle
3 Operating radius
4 Boom length
5 Stability
6 Types of footing
21
(ON SLIDE # 111)
b. The MAC 50 crane has two working ranges. They are Fully
Extended Outriggers, Mid Point Outriggers.
e. For any lift made, all corresponding load charts are read
the same way.
(4) The radius is shown along the left hand column. These
ratings are based on a freely suspended load with the crane
level and standing on a firm-supporting surface. The ratings
make no allowances for adverse job conditions.
22
23
INSTRUCTOR NOTE
1. 50 feet of boom.
24
2. Working radius is 16 feet.
3. Reeving is 6 parts with an 880 pound hook block.
4. Lifting slings weigh 800 pounds.
5. Machine is on full outriggers.
What is the max load your crane will lift? 48,520lbs
1. 40 feet of boom.
2. Working radius is 25 feet.
3. Reeving is 4 parts with an 880 pound hook block.
4. Lifting slings weigh 800 pounds.
5. Machine is on mid outriggers.
1. 55 feet of boom.
2. Working radius is 20 feet.
3. Reeving is 6 parts with an 880 pound hook block.
4. Lifting slings weigh 800 pounds.
5. Machine is on full outriggers.
1. 70 feet of boom.
2. Working radius is 45 feet.
3. Reeving is 2 parts with an 880 pound hook block.
4. Lifting slings weigh 800 pounds.
5. Machine is on mid outriggers.
1. 70 feet of boom.
25
2. Boom angle indicator reads 66 degrees.
3. Reeving is 4 parts with an 880 pound hook block
4. Lifting slings weigh 800 pounds.
5. Machine is on full outriggers.
1. Maximum of boom.
2. Reeving is 2 parts with an 880 pound hook block.
3. Working radius is 45 feet.
4. Lifting slings weigh 800 pounds.
5. Machine is on mid outriggers.
1. 30 feet of boom.
2. Working radius is 18 feet.
3. Reeving is 8 parts with an 880 pound hook block.
4. Lifting slings weigh 800 pounds.
5. Machine is on full outriggers.
What is the max load your crane will lift? NOT PERMISSIBLE
INSTRUCTOR NOTE:
26
(ON SLIDE # 127)
1. Extended boom.
2. Hook block 235 lbs
3. 360-degrees.
4. On outriggers.
5. Lift 4,300 lbs.
6. 235lbs hook block
1. Extended boom.
2. Hook block 235 lbs
3. 360-degrees.
4. On outriggers.
5. Lift 5,350 lbs.
6. 235lbs hook block
What is your maximum radius? 20’
27
1. Extended boom.
2. Hook block 235 lbs
3. 360-degrees.
4. On outriggers.
5. Lift 4,200 lbs.
6. 235lbs hook block
7.
What is your minimum boom angle? 27 degrees
1. Retracted Boom.
2. Hook block 235 lbs
3. Over the front.
4. On outriggers.
5. Lift 14,765 lbs.
6. 235lbs hook block
1. Retracted Boom
2. Hook block 235 lbs.
3. Over the side.
4. On outriggers.
5. Lift 8,750 lbs.
6. 235lbs hook block
TRANSITION: Now that we talked about the load charts. Are there
any questions at this point? If there is no further question,
let’s take a break before moving on to the hand and arm signals.
________________________________________________________________
________________________________________________________________
________________________________________________________________
28
INSTRUCTOR DEMONSTRATION (30 min)
The following Hand and arm diagram will be referenced while the
instructor demonstrates.
29
(ON SLIDE # 153)
TRANSITION: Now that we talked about hand and arm signals. Are
there any questions at this point? Then I have some for you.
Then we will take a break.
________________________________________________________________
________________________________________________________________
________________________________________________________________
Arm extended palm down, move arm back and forth horizontally.
30
TRANSITION: We have just the covered hand and arm signals. If
there is no further question, let’s move on to the LRT-110
Crane.
________________________________________________________________
________________________________________________________________
________________________________________________________________
a. Characteristics:
31
(d) Hydraulic tank: Located behind the operators cab,
with a capacity of 23.8 gallons. The entire hydraulic system
holds 45 gallons.
32
(8) Brakes: The brakes are vacuum assisted. If the engine
is not running the crane will not have any brakes.
(11) Load Charts: All cranes, including the LRT 110, are
required to have a load chart in the operator’s cab, visible to
the operator while operating. Load charts represent the maximum
allowable loads that the crane can lift. The LRT 110 crane has
two load charts for working on outriggers. They are retracted
and extended.
(12) Boom, winch, and outrigger controls: The LRT 110 has
five hydraulic controls located on the dash. From left to right
they are the swing, boom telescope, boom hoist, winch, and
outrigger levers.
33
(d) Winch lever: Raises or lowers the hook block.
Push the lever to lower your hook block or load and pull to
raise hook block.
34
(f) When traveling more than 2 miles off road or 5
miles on pavement, remove anti-two block weight and chain from
the ATB switch. Failure to do so may cause damage to the hook
block switch.
b. Capabilities:
c. Limitations:
(2) The winch capacity is 350 feet of 1/2 inch wire rope.
35
d. Employment of the LRT-110 7.5-ton crane has two
attachments, the hook block and the aerial personnel basket. The
uses of the hook block include:
(BREAK 10min)
INSTRUCTOR NOTE
STUDENT ROLE: The students will gather around the LRT 110 with
student handouts and observe the instructors demonstration.
Students will be encouraged to ask questions.
36
guides will be utilized when necessary. In case of mishap
students will move to the classroom and instructor will call
emergency personnel.
2. Supervision and Guidance: The instructor will demonstrate the
following.
INSTRUCTOR NOTE
(BREAK 10min)
INSTRUCTOR NOTE
37
PRACTICE: Each student will be assigned a piece of equipment to
operate; an additional student will be assigned to that piece of
equipment as a ground guide for the student operating. Students
are allowed to use hand outs and ask questions. The students
will practice the following task.
38
a. The boom has a maximum boom length of ______ feet, and a
minimum boom length of _______ feet?
6000 pounds
e. The LRT 110 crane has two load charts for working on
outriggers. What are they?
a. Characteristics:
39
(1) The MAC 50 is powered by an in-line 6 cylinder,
turbocharged Cummins diesel engine that outputs 333 HP @ 2,000
RPM and 305 HP @ 2,200 RPM. The engine has the capability of
being started at temperatures as low as -25 degrees Fahrenheit.
(8) There are three major components that make up the MAC
50 crane. The chassis refers to the frame, axles, lower or
40
driving cab, and engine. The superstructure is the upper or
operating cab, turntable, and winch assembly. The boom is the
lifting arm of the equipment and has three telescoping sections.
41
________________________________________________________________
________________________________________________________________
________________________________________________________________
580 feet
42
(ON SLIDE # 207, 208)
43
(ON SLIDE # 209)
45
(1) Dolly Indicator (NOT USED)
(2) Hydraulic Oil Filter Warning
(3) Hydraulic Oil Temperature Warning
(4) Steering Circuit-1 (off when parking brake is
disengaged)
(5) Steering Circuit-2 (off at 6 MPH)
(6) Steering Circuit-3 (NOT USED)
(7) Front Left Suspension
(8) Rear Left Suspension
(9) Front Right Suspension
(10) Rear Right Suspension
46
(1) Outrigger Lighting
(2) Front Axle Suspension
(3) Left Rear Axle Suspension
(4) Right Rear Axle Suspension
(5) All Axle Suspension
(6) Air Conditioner
(7) Independent Rear Axle Steering
(8) All-Wheel Drive Lock
(9) Axle Differential Lock
(10) Transfer Case
(11) Engine Ignition
(12) Engine RPMs
(13) Four-Way Hazard Lights
47
INTERIM TRANSISTION: Are there any more questions? Then let’s
move on.
________________________________________________________________
________________________________________________________________
________________________________________________________________
49
(9) Windshield Washer
(10) Engine Ignition
(11) Engine Shutoff
(12) Engine RPM
(13) Dashboard Lighting
(14) Outrigger Lighting
(15) Exterior Lighting
50
(9) Boom 0% Extension
(10) Battery
(11) Hydraulic Filter
(12) WARNING!
(13) STOP!
(14) Glow Plug
(15) Chassis Warning light
51
(ON SLIDE # 223)
(a) Ensure that all four OUTTER and INNER pins are
retracted
52
(c) Engage the OUTTER pin to lock outrigger
(5) After dun-age is placed, raise the MAC 50 off the deck
using the vertical outrigger control. The chassis will need to
be level before any further operations are performed. This will
be accomplished by raising the crane to the highest position and
then leveling down. Leveling will be obtained by using the
round bubble level on the right console and double checked by a
second level placed both parallel and perpendicular to the
crane’s frame.
(a) Once the frame is level, raise the axles all the
way up by using the axle raise/lower switch.
53
1-Current weight with graph 7-Change setup/confirm
2-Two-block warning 8-Display select toggle
3-90% capacity warning 9-Display select toggle
4-100% capacity warning 10-Display screen contrast
5-Setup code (four options)* 11-Display screen contrast
6-Parts-of-line 12-Alarm override
(5) Stowing and un-stowing of the boom and slings can only
be accomplished by having the SLI in Rigging/Travel mode. When
the boom is lower than 29 degrees the SLI will disengage the
54
controls if not in Rigging/Travel mode. While in this mode the
SLI safety features are completely overridden.
(6) After the slings are attached to the hook block and/or
the boom is above 29 degrees on the boom angle indicator the SLI
must be configured at this time.
CAUTION: WHEN UNSTOWING THE BOOM, THE FIRST AND ONLY FUNCTION
DONE WILL BE TO RAISE THE BOOM OUT OF ITS CARRIAGE. If any other
function is accidentally performed the lower cab could be
damaged and/or the winch cable will backlash on the drum.
CAUTION: WHEN STOWING THE BOOM, ENSURE THAT THE BOOM IS FULLY
RETRACTED VIA ASSISTANT AND BOOM 0% EXTENSION INDICATOR LIGHT ON
THE DASHBOARD. If this is forgotten when the boom is being
lowered into the carriage, the boom will crush the roof of the
lower cab.
55
(ON SLIDE # 250)
56
The right joystick is equipped with a vibrating clicker that
allows the operator to feel/hear how much and at what rate wire
rope is paid out (as the rate increases the clicking gets faster
and vice-versa).
j. Limitations:
To turn off engine from lower cab, then restart engine from
upper cab.
57
b. The MAC 50 is limited to raising a maximum load of
________________ at a 10 ft. working radius on mid outriggers?
58
(3) Loading of bulk material into vehicles
(BREAK 10 min)
INSTRUCTOR NOTE
59
STUDENT ROLE: The students will gather around the Mac 50 with
student handouts and observe the instructors demonstration.
Students will be encouraged to ask questions.
INSTRUCTOR NOTE
INSTRUCTOR NOTE
STUDENT ROLE: The students will gather around the Mac 50 with
student handouts and observe the instructors demonstration.
Students will be encouraged to ask questions.
a. The LRT 110 should not have less than how many feet of
wire rope to be mission capable?
180 ft
82’ 3”
62
process. Prior to the crane be operated you must conduct your
360 walk around, but once a year you are required to conduct a
condition inspection followed by a load test and non destructive
test every five years. If there are no questions, let us start
by talking about the background.
________________________________________________________________
________________________________________________________________
________________________________________________________________
INSTRUCTOR NOTE
This refers back to when the Marine Corps did Annual Load
tests on equipment (late 80’s early 90’s)
63
b. Commanding Generals (CG) shall designate specific 3rd
Echelon capable organizations to provide inspection and testing
services for units without the organic resources/maintenance
authority to conduct those inspections and tests.
INSTRUCTOR NOTE
Hand out a copy of the Annual Condition Inspection
checklist to the students; also have the students refer to
TM 4700-15/1 pg 2-25-1 through 2-25-3 or MCO P11262.2 pg 4-
9 through 4-11.
64
testing is not required. Prior to initial use, however, all,
newly manufactured, extensively repaired or altered
cranes/aerial personnel devices shall be load tested.
65
will not require load testing of the crane portion. Outriggers
will be considered as part of the lifting portion of a
crane/aerial personnel device.
66
j. Marking. Load lifting equipment shall be stenciled, in a
position clearly visible to the operator, with certification
data indicating the test status.
2 year period
(BREAK 10 MIN)
INSTRUCTOR NOTE
The following standards are from ASME (American Society of
Mechanical Engineers) B56.1-1993
68
e. Check electrical, gasoline, and diesel systems for signs
of malfunction, excessive deterioration, dirt or moisture
accumulation, and compliance with applicable safety regulations.
3 degrees.
69
b. Inspection performed in addition to those required by
TM’s?
ACI
(BREAK 10 MIN)
INSTRUCTOR NOTE
Use hook training aids
70
(6) If the hook is visually bent or twisted, it shall be
discarded. No attempt shall be made to straighten a bent or
twisted hook.
INSTRUCTOR NOTE
Perform the following demonstration.
a. What are two types of hook block inspections and what are
the intervals?
Discard it.
(BREAK – 10 Min)
72
TRANSITION: Now that we have covered the annual condition
inspection and hook inspection let us now talk about the
inspection of wire rope and hardware.
________________________________________________________________
________________________________________________________________
_________________________________________________
INSTRUCTOR NOTE
Show students examples of wire rope and show parts of the
wire rope.
c. Broken Wires.
73
or three broken wires in one strand in one lay. Replace the end
connection if there is one or more broken wires adjacent to the
end connection.
(2) Standing, Guy, and Boom Pendant Ropes. More than two
broken wires in one lay in sections beyond the end connection or
one or more broken wires at an end connection.
74
(BREAK 10 MIN)
TRANSITION: Now that we have covered the wire rope and hardware
inspection are there any question? Now let’s continue on with
the remaining components.
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
b. Condition Inspection.
1. General Information:
TRANSITION: Now that we have covered all the checks for the
annual condition inspection are there any questions? Now we are
going to cover the recording requirements.
________________________________________________________________
________________________________________________________________
_________________________________________________
76
2. QUESTION TO THE CLASS:
INTERIM TRANSITION: Are there any more question? Let’s move into
the demonstration
_________________________________________________________________
_________________________________________________________________
_________________________________________________________________
INSTRUCTOR NOTE
Perform the following demonstration.
77
1. Safety Brief: Ensure the training aid is in constant
contact with the table to prevent it from falling.
2. Supervision & Guidance: Students will be encouraged to ask
questions and make notes on their application.
3. Debrief: Are there any questions or comments concerning the
inspection, rejection, documentation or record defects?
(BREAK 10 MIN)
78
________________________________________________________________
________________________________________________________________
_________________________________________________
INSTRUCTOR NOTE
Brief students on the “Interim policy and procedures for
the inspection, testing, and certification of Marine Corps
tactical ground load lifting equipment during continuous
combat operations.” Dated 15 Apr 2011
NONE
(BREAK 5 MIN)
b. No-Load Test
(1) Hoist:
(a) Raise and lower the hook through the full working
distance of hook travel.
80
(b) Run the hoist block into the limit switch(es)
(where installed) at slow speed.
(2) Boom:
(a) Raise and lower the boom through the full working
range.
(b) Raise the boom into the upper limit switch (where
installed) Raise the boom past the boom upper limit switch,
using the bypass switch.
81
decrease load until wire rope is barely slack. Repeat this test
once more. The hook will be inspected per the procedures in
paragraph 5 of this student outline. This will serve as the
nondestructive hook test.
(a) Choose any load from the load chart below the
black (bold) line of the rated load 3600 chart. All weights
above the bold line are in the structural strength portion of
the load chart, and all weight below the bold line are in the
stability portion. The test load must be able to clear
outriggers during full 3600 rotation.
82
(h) Swing the crane through the 3600 rotation.
By actual measurement.
110%
83
(3) Carefully inspect all safety devices, including all
specialized features.
(3) With the lower arm at the maximum travel from the
towed position and the upper arm both horizontal and 450 to the
side of the vehicle, or over the four corners of the vehicle,
rotate the turntable both clockwise and counterclockwise with
the test load through 3600 for a minimum of 15 minutes.
84
Twice the rated working load.
15 Minutes
INSTRUCTOR NOTE
Introduce the following Practical Application.
85
TRANSITION: Are there any questions concerning the practical
application or anything else we have covered?
INSTRUCTOR NOTE
86
REFERENCES:
87