You are on page 1of 24

Definitive global law guides offering

comparative analysis from top-ranked lawyers

Construction
Law 2022
Philippines
Julius Cervantes, Michael Macapagal,
Ramon Miguel Bacani and Jared Amoroso
Quisumbing Torres

practiceguides.chambers.com
PHILIPPINES
Law and Practice
Luzón

Manila Philippines
Contributed by: Mindoro
Samar
Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani Palawan
Panay
Leyte
and Jared Amoroso Negros
Quisumbing Torres see p.22 Mindanao

CONTENTS
1. General p.3 5.3 Remedies in the Event of Delays p.14
1.1 Governing Law p.3 5.4 Extension of Time p.15
1.2 Standard Contracts p.4 5.5 Force Majeure p.15
1.3 COVID-19 p.4 5.6 Unforeseen Circumstances p.15

2. Parties p.5 6. Liability p.16


2.1 The Employer p.5 6.1 Exclusion of Liability p.16
2.2 The Contractor p.5 6.2 Wilful Misconduct and Gross Negligence p.16
2.3 The Subcontractors p.7 6.3 Limitation of Liability p.16
2.4 The Financiers p.8
7. Risk, Insurance and Securities p.16
3. Works p.9 7.1 Indemnities p.16
3.1 Scope p.9 7.2 Guarantees p.17
3.2 Variations p.9 7.3 Insurance p.17
3.3 Design p.10 7.4 Insolvency p.17
3.4 Construction p.10 7.5 Risk Sharing p.17
3.5 Site Access p.10
8. Contract Administration and Claims p.18
3.6 Permits p.11
8.1 Personnel p.18
3.7 Maintenance p.11
8.2 Subcontracting p.18
3.8 Other Functions p.11
8.3 Intellectual Property p.19
3.9 Tests p.12
3.10 Completion, Takeover, Delivery p.12 9. Remedies and Damages p.20
3.11 Defects and Defects Liability Period p.12 9.1 Remedies p.20
9.2 Restricting Remedies p.20
4. Price p.13
9.3 Sole Remedy Clauses p.20
4.1 Contract Price p.13
9.4 Excluded Damages p.20
4.2 Payment p.13
9.5 Retention and Suspension Rights p.20
4.3 Invoicing p.14
10. Dispute Resolution p.21
5. Time p.14
10.1 Regular Dispute Resolution p.21
5.1 Planning, Programme p.14
10.2 Alternative Dispute Resolution p.21
5.2 Delays p.14

2
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

1. GENERAL original and exclusive jurisdiction over construc-


tion disputes arising from a contract entered into
1.1 Governing Law by parties involved in construction in the Philip-
The principal laws governing the construction pines that contains an arbitration clause.
market in the Philippines are as follows.
Republic Act No 9184 (Government
Philippine Civil Code Procurement Reform Act or GPRA)
The Philippine Civil Code (“Civil Code”) is the The GPRA applies to all branches of the Philip-
general law that governs contractual relations in pine government, and to all procurement activi-
the Philippines, which include construction con- ties involving services and infrastructure pro-
tracts. Construction contracts are governed by jects.
the general rule under the Civil Code that parties
are free to stipulate the terms of their agreement, The GPRA prescribes standard template con-
provided that these are not contrary to law, mor- ditions of contract (also known as the General
als, good customs, public order, or public policy. Conditions of Contract and the Special Con-
ditions of Contract). It affects the overall con-
Consequently, unless otherwise provided by struction contract when a government project
law or contract, a construction contract will be is involved.
governed by the provisions of the Civil Code on
Obligations and Contracts and those applicable The GPRA also applies to foreign-funded infra-
to contracts for a “piece of work”. structure projects, unless otherwise provided by
the relevant treaty, international agreement, or
Presidential Decree No 1746 (PD 1746) executive agreement.
PD 1746 created the Construction Industry
Authority of the Philippines (CIAP) for the pur- Republic Act No 6957, as amended by
pose of regulating the construction industry in Republic Act No 7718 (PPP Law)
the Philippines. PD 1746 also established the The PPP Law governs public-private partnership
Philippine Contractors Accreditation Board (PPP) infrastructure projects, specifically those
(PCAB), the licensing body for persons seeking that are under the following schemes:
to engage in construction activities in the Philip-
pines. • build-operate-and-transfer;
• build-and-transfer;
Republic Act No 4566 (Contractor’s Licence • build-lease-and-transfer;
Law) • build-transfer-and-operate;
The Contractor’s Licence Law requires contrac- • contract-add-and-operate;
tors to obtain a licence from the PCAB (PCAB • develop-operate-and-transfer;
Licence), and also sets out the procedure and • rehabilitate-operate-and-transfer; and
requirements for the issuance of such licence. • rehabilitate-own-and-transfer.

Executive Order No 1008 (Construction Presidential Decree No 1096 (National


Industry Arbitration Law or CIAC Law) Building Code of the Philippines)
The CIAC Law created the Construction Indus- The National Building Code sets out the national
try Arbitration Commission (CIAC), which has its policy and the legal requirements relating to the
own CIAC Rules of Procedure. The CIAC has design, location, siting, construction, alteration,

3
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

repair, conversion, use, occupancy, mainte- developed two sets of template contracts: (i)
nance, moving, demolition of, and addition to CIAP Document 101, or the “General Conditions
public and private buildings and structures. It of Contract for Government Construction”; and
also serves as a basis for local ordinances enact- (ii) CIAP Document 102, or the “Uniform Gen-
ed by local government units for implementation eral Conditions of Contract for Private Construc-
within their respective territorial jurisdictions. tion”. Although these CIAP template contracts
are rarely used, the Philippine Supreme Court
Presidential Decree No 1445 (Government has, in some instances, considered certain pro-
Auditing Code of the Philippines or GACP) visions of CIAP Document 102 as evidence of
The GACP needs to be considered when dealing prevailing practice in the construction industry,
with construction contracts involving the gov- and has applied these provisions in instances
ernment. where there appear to be gaps or uncertainty
in the parties’ construction contract (see Werr
The GACP specifies that the powers of the Phil- Corp International v Highlands Prime, Inc, 2017).
ippine Commission on Audit (COA) extend to the
examination, audit and settlement of all debts On the other hand, for construction and infra-
and claims of any sort due from or owing to the structure projects procured by the Philippine
government or any of its subdivisions, agencies government, standard forms are normally used
and instrumentalities. This becomes relevant that contain the clauses and terms required
when, in the event of a dispute, a contractor under the relevant laws and regulations. For
obtains a favourable judgment against the gov- example, in construction projects procured
ernment. by the government under the GPRA, or those
undertaken by the government in accordance
There have been several instances in the past with the Build-Operate-Transfer Law (BOT Law),
when a CIAC award against the government standard forms are used that contain the terms
has been modified and reduced by the COA, required under the relevant law and their allied
pursuant to its power to approve money claims regulations. For government infrastructure pro-
against the government. In Taisei Shimizu Joint jects that are funded by way of foreign grants
Venture v COA and DOTr (2020), the Supreme covered by the Official Development Assistance
Court ruled that the COA may not disregard final Act (ODA Act), FIDIC forms are typically used.
and executory judgments rendered by courts
and other adjudicative bodies by disallowing any 1.3 COVID-19
part of such final award. The Philippines construction industry was the
fastest-growing in the Asia-Pacific region prior
1.2 Standard Contracts to the COVID-19 outbreak, but its growth has
The use of standard contracts is not mandatory been severely impacted by the pandemic.
in construction projects procured by a private
(ie, non-government entity) employer, and par- The COVID-19 pandemic has resulted in the
ties are generally free to agree on the form that imposition of varying degrees of health and
will be used. safety protocols across the country. During the
first half of 2020, only essential construction pro-
There have been attempts to come up with tem- jects, ie, those relating to COVID-19 facilities,
plate construction contracts for private projects emergency works, priority public and private
in the Philippines. For instance, the CIAP has infrastructure projects, as defined, and the like,

4
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

were allowed to operate on a skeletal workforce. same, and to carry out or correct the work by
As the policy direction for permissible work dur- itself or through other contractors;
ing the quarantine period stabilised, public and • to obtain title and ownership over all complet-
private construction projects eventually resumed ed works, and over all materials, equipment,
operations at full operating capacity, subject to tools, and supplies for which payment has
compliance with health and safety protocols. been made under the contract; and
• to request variations, in accordance with the
In an effort to adapt to the circumstances, the contract.
CIAC issued guidelines on how to conduct online
proceedings in construction arbitration proceed- Obligations
ings, which essentially require the parties to • To pay the contract price;
agree to the conducting of online proceedings. • to provide the contractor access to and pos-
session of the site, to enable the contractor to
The lockdowns have likewise given rise to force perform the construction works;
majeure claims. “Force majeure” under Philip- • to provide pertinent information regarding the
pine law, pertains to events that could not be site that may be needed by the contractor in
foreseen, or though foreseen, were inevitable connection with the construction works;
(Article 1174, Civil Code). This general principle • to obtain relevant government permits and
on force majeure, however, gives way to con- licences needed for the project; and
tractual stipulations by the parties. • to obtain and maintain the relevant insurance
coverages required under the contract.

2 . PA R T I E S General Relations Between the Employer,


Contractor, Subcontractors and Financiers
2.1 The Employer Generally, no principal-agent, employer-employ-
Companies That Act as Employers ee or partnership relationship is created between
Private individuals, privately owned entities, and the employer, on one hand, and the contractor,
government agencies and instrumentalities typi- subcontractors and financiers, on the other
cally act as employers in construction projects hand. The employer is not bound by the acts
in the Philippines. of such parties and its relationship with them
will generally be governed by the terms of the
Rights and Obligations relevant agreements among the parties.
The general rights and obligations of the
employer under a construction contract normally 2.2 The Contractor
include the following. Companies That Act as Contractors
The entities that typically act as contractors in
Rights construction projects are Philippine stock corpo-
• To inspect the works or any portion thereof; rations that secure the appropriate licence from
• to require the correction of defects due to the PCAB.
faulty materials, equipment, or workmanship
that may appear within a certain period upon There are also instances where multiple contrac-
completion of the works; tors, each holding a PCAB licence, form an unin-
• to stop the works or any portion thereof, if corporated joint venture (UJV) to undertake only
the contractor fails to complete or correct the

5
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

a single specific project. In such cases, the UJV ular Licence with Annotation, which is a sub-type
itself must obtain its own PCAB licence. of Regular Licence under the Quadruple A Cat-
egory (“Quadruple-A Licence”). A Quadruple-A
A consortium between a PCAB-licensed con- Licence may be issued to a corporation organ-
tractor and a non-contractor may also be formed ised under Philippine law, including ones that
to undertake only a single specific project. In are up to 100% foreign-owned. An applicant for
such a case, the consortium itself must obtain a Quadruple-A Licence must have a minimum
its own PCAB licence. paid-up capitalisation of at least PHP1 billion at
the time it applies for the licence. The holder
Entities that act as contractors are also normally of a Quadruple-A Licence may undertake only
required by employers to satisfy certain legal, specific types of vertical and horizontal projects,
financial and technical eligibility requirements. each with a prescribed minimum contract value.

Types of PCAB Licences Recent court ruling


There are two main types of PCAB licence: a In a recent Supreme Court decision, PCAB v
Regular Licence and a Special Licence. Manila Water Company, Inc (2020), the foreign
ownership restrictions applicable to PCAB Reg-
Regular Licence ular Licences were declared invalid. It was held
Under the Implementing Rules (IRR) of the Con- that while the Contractor’s Licence Law author-
tractors’ Licence Law, a Regular Licence may ises the PCAB to adopt rules to effect classi-
be issued only to Filipino sole proprietorships, fication of contractors as may be necessary,
and to partnerships and corporations that have the intention is not for such law to discriminate
at least 60% Filipino equity participation and against foreign contractors. The classification of
are organised under Philippine law. A Regular contractors is limited only to the classifications
Licence authorises the licensee to engage in specifically provided under the Contractor’s
construction contracting within the field and Licence Law, which excludes nationality-based
scope of the licence classification during the classification. Moreover, the court held that the
licence’s validity, renewable annually. constitutional provision that limits the practice of
professions to Filipino citizens is inapplicable to
Special Licence the licensing of contractors in the construction
On the other hand, a Special Licence may be industry.
issued to a joint venture, a consortium, a foreign
constructor or a project owner, and only author- In a 2021 Resolution, the Supreme Court denied
ises the licensee to engage in the construction PCAB’s Motion for Reconsideration and the
of a single, specific project. It must be renewed intervention of several non-parties, and upheld
annually for as long as the project is in progress. its 2020 Decision. PCAB has yet to implement
The number of renewals is limited to the period the ruling of the Supreme Court, because one
until the completion of the specific project for of the intervenors in the case has also filed a
which the licence was issued. Motion for Reconsideration of the 2021 Resolu-
tion, which remains pending.
Regular Licence with Annotation – the
Quadruple-A Licence
In 2015, the IRR of the Contractor’s Licence Law
was amended to allow for the issuance of a Reg-

6
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

Rights and Obligations Under a Construction • to ensure security and safety at the site; and
Contract • to procure and maintain appropriate bonds
The general rights and obligations of the con- and insurance from reputable and financially
tractor under a construction contract normally sound companies acceptable to the employ-
include the following. er.

Rights General Relations Between the Contractor


• To receive the contract price; and Employer
• to be given access to and possession of the See 2.1 The Employer.
site, to enable the contractor to perform the
construction works; General Relations Between the Contractor
• to receive pertinent information regarding the and Subcontractors
site that may be needed by the contractor in The contractor is normally responsible for all the
connection with the construction works; and acts of its subcontractors, including any negli-
• to receive an extension of time, where appli- gent, wilful or reckless acts or omissions on the
cable, in accordance with the terms of the part of any subcontractor, its agents or employ-
contract. ees, as if they were the acts, negligence and
omissions of the contractor.
Obligations
• To perform and complete the works within General Relations Between the Contractor
the timelines provided in the contract and, at and Financiers
completion date, to hand over the sites and See 2.1 The Employer.
the completed works to the employer;
• to perform the works using materials, goods, 2.3 The Subcontractors
equipment and methods of constructions of Companies That Act as Subcontractors
the quality and standards required under the See 2.2 The Contractor for the kinds of entities
contract; that typically act as contractors in construction
• to provide and pay for all labour, materials, projects.
equipment, tools, construction equipment,
and all machinery, transportation, and other Rights and Obligations Under a Construction
facilities and services necessary for the prop- Contract
er execution and completion of the works; The rights and obligations of a subcontractor
• to obtain the permits necessary for the works are governed, not by the construction contract
from the relevant government agencies; between the employer and the contractor, but
• to warrant that the works conform with the by its own agreements with the contractor. Nor-
requirements of the applicable law, the con- mally, in the agreements between the contrac-
tract and other requirements of the employer, tor and the subcontractor, the subcontractor will
and are free from hidden defects, imperfec- have the same rights and obligations as those of
tions or faults; the contractor under the latter’s contract with the
• to rectify or remedy any defect or deficiency employer, to the extent applicable to the portion
during the construction period or within a of the works subcontracted to the contractor.
period of time thereafter; However, the contractor would not be relieved
• to comply with all relevant labour laws apply- of its obligations towards the employer with
ing to its employees; respect to the subcontracted works.

7
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

General Relations Between the Subcontractor direct government appropriations and financ-
and Employer ing arrangements secured from private financial
Construction contracts may or may not allow the institutions. Another typical source of financing
contractor to subcontract the whole or a por- for construction projects procured by the gov-
tion of the works, or may require the contractor ernment would be Official Development Assis-
to obtain the employer’s consent prior to such tance (ODA) in the form of loans and/or grants
subcontracting. secured from foreign governments and/or from
international financial institutions such as the
If subcontracting is allowed, it is generally the World Bank and the Asian Development Bank.
contractor that remains liable to the employer for
all the acts of its subcontractors, including any Rights and Obligations Under a Construction
negligent, wilful or reckless acts or omissions Contract
on the part of any subcontractor. It is also the Financiers are not typically made parties to
contractor, and not the employer, that is typically the construction contract. However, there are
responsible for the proper and timely payment of instances where the construction contract would
all subcontractors. expressly provide that the financiers are entitled
to certain rights, such as the following:
General Relations Between the Subcontractor
and Contractor • extensive information, auditing and inspection
See 2.2 The Contractor with regard to general rights;
relations between the contractor and subcon- • granting of a security interest over the project;
tractors. • to cure the breach on behalf of the defaulting
party; and
General Relations Between the Subcontractor • to nominate a third party (which may be the
and Financier financier itself) to assume the rights of the
Generally, no principal-agent, employer-employ- defaulting party.
ee or partnership relationship is created between
subcontractors and financiers. The subcontrac- Construction contracts do not usually provide
tors’ relationship with the financiers will generally for obligations of financiers.
be governed by the terms of the agreements (if
any) that may exist between them. General Relations Between the Financier and
Employer
2.4 The Financiers The relationship between the employer and the
Companies and/or Institutions That Act as financier would normally be governed not by the
Financiers construction contract, but by the financing or
For construction projects procured by a private other similar agreement between the employer
(ie, non-government entity) employer, the financ- and the financier. However, as mentioned above,
ing required by the employer and/or the con- certain rights may be granted to the financier
tractor is usually secured from private financial under the construction contract, in order to pro-
institutions, such as banks. tect the financier’s financial interest in the pro-
ject.
On the other hand, for construction projects pro-
cured by the government, the financier would
normally be the government itself through

8
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

General Relations Between the Financier, • extra work or alterations, additions to or


Contractor and Subcontractors deductions from the scope of the work; and
Normally, there would be no direct relationship • the need for additional or a different type of
between the financier and the contractor and work resulting from materially different sub-
subcontractors. However, as mentioned above, surface conditions from those shown in the
certain rights may be granted to the financier drawings, specifications, or contract docu-
under the construction contract, in order to pro- ments.
tect the financier’s financial interest in the pro-
ject. In determining the price of the variation, the val-
ue of any extra work or change is usually deter-
mined by the employer in any one or more of the
3. WORKS following ways:

3.1 Scope • by a lump sum acceptable to the contractor;


Typically, the scope of the works is determined by • by unit prices either stipulated in the contract
the employer and its relevant consultants based or subsequently agreed upon; and/or
on the former’s requirements, and is included in • by actual direct cost plus value added tax, if
the tender documents for the project. However, any, and a fixed percentage for the contrac-
it is also common for the scope of the works to tor’s profit and overheads (eg, 15%).
be prepared jointly by the employer (and its rel-
evant consultants) and the contractor, and once Scope and Price of Variations Requested by
agreed and finalised, to be incorporated in the the Contractor
construction contract. Generally, the parties may contractually agree
on the determination of the scope and price of
Methods of description used for the scope of the variations requested by the contractor.
works include the following:
The usual procedure adopted is that the con-
• programme of works; tractor proposes a variation to be adopted by
• terms of reference; the employer. Once approved, the variation will
• drawings (including supplementary details then be valued by the parties by agreement or
and shop drawings) and specifications pre- through a third party (eg, an engineer).
pared by the architect and/or other relevant
consultants; and It must be noted that under Philippine law (Civ-
• project schedules and milestones. il Code, Article 1724), a contractor can only
demand an increase in the price if there is a
3.2 Variations change in the plans and specifications under
Scope and Price of Variations Requested by the following conditions:
the Employer
In practice, the scope of variations requested by • the variation is authorised by the employer in
the employer would typically include: writing; and
• the additional price to be paid to the contrac-
• changes in quantities or an increase in the tor has been determined in writing by both
scope of the work of the contractor resulting parties.
from adjustments in work drawings;

9
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

3.3 Design were the acts, negligence and omissions of the


It is more common in the Philippines for design contractor itself.
works to be separately contracted by the
employer to a design consultant. In such cases, The employer, on the other hand, is generally
the construction contract will typically provide liable only to pay the contract price to the con-
that the employer is fully responsible for the ade- tractor, and allow the contractor and subcon-
quacy of the design. The drawings and specifi- tractor access to the site to perform the works.
cations prepared by the architect or the design The employer is generally not involved in the
consultant are normally attached to, and an inte- performance of the works.
gral part of, the construction contract, and must
be adhered to by the contractor in their perfor- 3.5 Site Access
mance of the works. It is also usually stipulated Prior to Construction
in construction contracts that the architect or Responsibility for matters relating to the status
the design consultant shall inspect the works of the site prior to construction is normally stipu-
to determine compliance with the drawings and lated in the contract. The contract may provide
specifications. The employer may require the that any remedial works needed to prepare the
rectification of works that the architect or design site for construction are included in the scope of
consultant determines to be non-compliant. the contractor’s works, or that any such remedial
works shall be the responsibility of the employer
However, there are also instances where the (through its other contractors) prior to the com-
employer and the contractor agree that a part mencement of the works.
or the whole of the works shall be designed by
the contractor. In such cases, the contractor is However, contractors typically visit the project
responsible for the adequacy of the design, and site prior to the bidding and awarding of the con-
all such responsibilities normally assigned to tract in order to assess the facilities that would
the owner in relation to the design are instead be needed and the difficulties that could poten-
assigned to the contractor. tially attend the execution of the works. Most
contracts also require the employer to provide
3.4 Construction the contractor with a geodetic survey and sub-
The contractor is generally responsible for the surface exploration.
performance of all the works, and their comple-
tion within the timelines provided under the con- The employer is normally responsible for any
struction contract, and is normally expected to violation of environmental laws and regulations
supply all the materials, goods and equipment relating to the status of the site prior to con-
needed for the works. It is also the contractor’s struction. Accordingly, any regulatory penalties
responsibility to rectify or remedy any defect or that may result from such violations would be
deficiency that may arise during the construction imposed on the employer.
period and/or within a certain period thereafter.
Construction contracts often provide that all
If allowed under the contract, the contractor archaeological finds, and other similar items
may subcontract a portion of the works. In such found on the site, shall be considered the prop-
cases, the contractor normally remains respon- erty of the employer.
sible for all acts of its subcontractors, as if they

10
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

During Construction 3.7 Maintenance


On the other hand, construction contracts nor- The maintenance of the works is normally gov-
mally provide that, while performing the works erned by a contract between the employer and
during the construction period, the contractor is another service provider. The maintenance con-
responsible for the site and must comply with all tract is typically separate from the construction
applicable environmental laws and regulations. contract, but there are also instances where the
The contractor may also be held responsible for construction, operation and maintenance of the
violations under environmental laws and regula- project are integrated in a single contract (eg, in
tions if the violation arises from its own acts or public-private partnership projects between the
omissions. government and private proponents that involve
the construction, operation and maintenance of
3.6 Permits infrastructure facilities).
The following are the primary permits required
for a construction project: The scope of operation and maintenance works
varies depending on the type of project involved,
• Contractor’s Licence from the Philippine Con- and is generally dependent on the agreement of
tractor’s Accreditation Board; the parties. However, the scope of maintenance
• Environmental Compliance Certificate (and works usually involves the regular scheduled
allied permits) or Certificate of Non-Coverage maintenance of the works, day-to-day admin-
(as may be applicable) from the Department istration, management, upkeep, repairs, over-
of Environment and Natural Resources; hauls, improvements and replacements that are
• zoning/locational clearance, building per- necessary for the safe and proper operation of
mit (and other related permits; eg, electrical the works.
permits, mechanical permits) and occupancy
permit, from the relevant local government The construction contract may provide that the
unit; manual for the maintenance works shall be pre-
• fire safety evaluation clearance, from the pared by the contractor and turned over to the
Bureau of Fire Protection; employer on completion of the construction.
• for projects near airports, a height clearance
permit from the Civil Aviation Authority of the 3.8 Other Functions
Philippines; and Other functions in the construction process are
• such other permits as may be required under usually contracted by the employer to third par-
applicable special laws and/or regulations. ties.

Except for the Contractor’s Licence (which the Operational services are usually covered by a
contractor must obtain and hold in its own name), separate agreement between the employer and
all the permits required for the construction pro- an operation and maintenance service provider
ject would normally be issued in the employer’s (which may or may not be the contractor). See
name. However, the contract usually provides 3.7 Maintenance.
that the contractor is responsible for obtaining
such permits for and on behalf of the employer. Financing arrangements are also usually cov-
ered by a separate financing agreement and
are independent of the construction. However,
the financier may also be provided with certain

11
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

rights (see 2.4 The Financiers), which may be to inspect the works. If the employer finds that
exercised in accordance with the terms of the Substantial Completion has indeed been met, it
construction contract. will issue a Certificate of Substantial Completion.
If the employer finds that Substantial Comple-
The transfer of the project from the contractor to tion has not been met, it will notify and allow the
the employer is normally governed by the terms contractor to perform the works necessary to
of the construction contract. achieve Substantial Completion.

3.9 Tests After issuance of the Certificate of Substantial


Upon completion of the works, the contrac- Completion, the works and the site would be
tor will normally request the employer to con- turned over to the employer.
duct an inspection. The employer (through its
relevant consultants) may conduct tests, at its Final Completion
own expense, to determine whether the con- If the contractor determines that it has met
tractor has satisfactorily completed the works Final Completion, it will request the employer
in accordance with the contract and the employ- to inspect the works. If the employer finds that
er’s instructions. Final Completion has indeed been met, it will
issue a Certificate of Final Completion. If there
If the tests reveal that the contractor has not sat- are any defective of non-compliant works, the
isfactorily completed the works, it would be the employer may issue a “punch list” identifying
contractor’s responsibility to promptly replace such works. Upon the contractor’s completion
or repair the works at its own expense. In such of the punch list to the employer’s satisfaction,
cases, the contractor would also typically shoul- the employer will issue the Certificate of Final
der the expenses that will be incurred to conduct Completion.
further tests until the works are satisfactorily
completed. 3.11 Defects and Defects Liability
Period
If the tests determine that the works have already The construction contract usually provides for
been satisfactorily completed, the employer a defects liability period where the contractor
will certify such completion in accordance with can be held liable for defects in the works upon
mechanics set out in the construction contract. notice by the employer. Typically, the defects
liability period would be for a period of one year
3.10 Completion, Takeover, Delivery counted from Substantial or Final Completion.
The contracts would provide separate mile-
stones for Substantial Completion and Final In the event that defects are discovered during
Completion. Substantial Completion typically the defects liability period, the employer may
entails completion of at least 95% of the works, require that the defects be remedied at the sole
which already allows the employer to use the cost of the contractor. If the contractor fails to
site. Final Completion refers to the completion remedy the defects, the employer may (i) rem-
of all the works under the contract. edy the defects or request another party to do
so, and (ii) claim from the warranty security or
Substantial Completion retention an amount to defray the costs for such
If the contractor determines that it has met Sub- rectification.
stantial Completion, it will request the employer

12
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

In the absence of any contractual stipulation, that are typically used are cost plus fixed per-
the defects liability period under the Civil Code centage, and with lesser frequency, cost plus
(Article 1723) applies. fixed fee.

• The engineer or architect who drew up the Milestone Payments


plans and specifications for a building is It is also common for construction contracts to
liable for damages if within 15 years from the provide for milestone payments. Each milestone
completion of the structure, the same should payment is usually subject to verification or test-
collapse by reason of a defect in those plans ing by the employer prior to payment. Contracts
and specifications, or due to the defects in also often provide for a down payment, normally
the ground. upon delivery of the performance bond required
• The contractor is responsible for damages if under the contract and after the necessary per-
the edifice falls, within 15 years, on account mits and licences have been obtained from the
of defects in the construction or the use of relevant government agencies. Full payment of
materials of inferior quality furnished by the the contract price is made upon Final Comple-
contractor, or due to any violation of the tion, subject to any agreement relating to any
terms of the contract. retention amount.

Actions under either of the above must be 4.2 Payment


brought within ten years following the collapse Parties are free to stipulate the conditions of
of the building. late or non-payment, which may include the
payment of interest or penalties, and may also
The Civil Code does not provide for a period constitute a ground for the suspension of work
within which to report discovered defects after or termination of the contract.
the initial defects liability period.
The following measures are typically applied in
case of late or non-payment:
4. PRICE
• within an agreed period after a receipt of
4.1 Contract Price request for payment from the contractor, the
The contract price is typically expressed as a employer shall pay the amount as certified;
lump sum or a fixed amount in the contract, sub- • where the employer fails to pay the amount
ject only to adjustments as may be needed in due on time, the employer shall pay, in addi-
case of variations, and as may be agreed upon tion to the amount due, interest thereon;
by the parties. The contract price would already • a delay in the payment of any progress billing
consider all costs and expenses that the con- shall automatically extend the Completion
tractor may incur for the proper execution, com- Time by a period equal to the delay;
pletion and performance of the works. • the contractor has the right to suspend work
or terminate the contract upon written notice
Cost-Plus Contracts to the employer, if the employer fails to pay
Cost-plus contracts are also regularly used in the contractor the approved request for pay-
the Philippines, particularly in instances where ment; and/or
the scope of the works has not been clearly • if the contractor incurs a delay in the mobi-
defined. The variations of cost-plus contracts lisation and/or in the progress of the work

13
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

for reasons attributable to the employer, the and the works would need to be performed in
contractor may be entitled to a claim for extra accordance with its terms.
cost, and delay in said payment shall entitle
the contractor to an extension of time and to In either case, any amendment to the plans,
payment of interest. schedules and milestones requires approval by
the employer and the contractor.
Advance payments, delayed payments and/or
interim payments are schemes that are gener- The completion of milestones is subject to
ally used and may be stipulated in construction verification and testing (see 3.9 Tests and 3.10
contracts. For instance, the parties may mutu- Completion, Takeover, Delivery). Milestone
ally agree on the amount of advance payment certificates would also usually be issued by the
to be made by the employer, subject to the con- employer to evidence the completion of mile-
tractor’s posting of a surety bond of equivalent stones.
amount to guarantee repayment. The advance
payment is used for mobilisation, purchase of 5.2 Delays
materials, etc. In relation to delay in payments, see 4.2 Pay-
ment.
4.3 Invoicing
The particular means and form of invoicing are Parties are free to stipulate what constitutes a
not normally provided in the contract. However, delay in performance and the effects of the delay
in milestone payments, approval by the employer on the respective obligations of the parties.
is generally required before the contractor may
issue invoices to the employer for the particular A party is generally required to notify the other
payment. party that the latter is causing a delay. This is
consistent with Article 1169 of the Civil Code,
which states that those obliged to deliver or
5. TIME do something incur a delay from the time the
demand is made. However, demand is not nec-
5.1 Planning, Programme essary for the delay to exist when the law or obli-
Generally, the plans, schedules and milestones gation expressly so declares, such as express
are arranged and determined by the employer, stipulation in the agreement as to the contract
and finalised and incorporated into the contract key dates or timeline. Nevertheless, a notifica-
upon agreement with the contractor. Inputs from tion requirement is common practice in order to
the architect and the employer’s other consult- determine the period from which an extension of
ants may also be taken into account in preparing time or additional cost claim shall be based, if
the plans, schedules and milestones. any. After notification, the claiming party is gen-
erally required to substantiate the impact of the
In some instances, the contract may also pro- delay and its corresponding entitlement to an
vide that the contractor should prepare a con- extension of time and/or additional cost claim.
tractor’s plan, consistent with the scope of the
work and the requirements of the employer, for 5.3 Remedies in the Event of Delays
approval by the employer. Once approved, the The employer would typically be entitled to the
contractor’s plan is binding between the parties, payment of liquidated damages and other con-
sequential costs (which may be collected from

14
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

the performance bond) in the event of delay by within any place; rationing or allocation, whether
the contractor. Substantial delay may also be imposed by law, decree, or regulation; etc.
cause for the employer to terminate the con-
struction contract. Nonetheless, parties are free to contractually
limit or exclude certain circumstances from
5.4 Extension of Time being qualified as force majeure events.
In practice, if the contractor is obstructed or
delayed in the completion of the work by reasons 5.6 Unforeseen Circumstances
not attributable to the contractor (ie, employer’s Unforeseen circumstances may be in the follow-
action, neglect, delay or fault; third-party strikes ing forms: fortuitous events, as discussed under
or lockouts; an act of God or force majeure; etc), 5.5 Force Majeure, legal or physical impossi-
the contractor is entitled to an equitable adjust- bility, or difficulty beyond the contemplation of
ment of the completion time. the parties. The provisions of the Civil Code are
deemed written into the contract. Unless the
The contractor must, within a period specified parties stipulate otherwise, the provisions of the
under the contract, notify the employer. In turn, Civil Code will govern.
the employer must, within a similar specified
period, give the contractor an equitable adjust- Under the Civil Code, a debtor in obligation to
ment of the completion time, subject to the perform a service will be released when the obli-
employer’s determination as to the period. If the gation becomes legally or physically impossible
contractor and the employer cannot agree on without any fault on the part of the obligor. Legal
the proposed period, the contract may provide impossibility refers to instances where an act is
mechanisms to settle the dispute. The parties prohibited or prevented by law, while a physical
may also stipulate that the employer’s failure impossibility is where an act can no longer be
to reply to the contractor may be deemed as accomplished by reason of its nature.
approval by the employer of the adjustment
requested by the contractor. As for difficulty beyond the contemplation of the
parties, the Civil Code provides that when the
5.5 Force Majeure service has become so difficult as to be mani-
Under the principle of force majeure (also known festly beyond the contemplation of the parties,
as fortuitous events) in Philippine law, no person the obligor may also be released from the obliga-
is responsible for events that could not be fore- tion, in whole or in part. The scenario contem-
seen or that, although foreseen, were inevita- plated includes exceptional changes in circum-
ble. The most common force majeure events in stances, taking into account the risks assumed
construction contracts in the Philippines include: by the parties at the inception of the contract.
war, riot, sabotage, acts of terrorism, insurrec-
tions, acts of public enemies; strike, industrial Unforeseen circumstances may be classified
dispute, blockade, labour dispute, lockout; fire, as force majeure or a change in legislation that
explosion, flood, typhoon, tornado, epidemic would entitle the contractor to an extension of
or pandemic, earthquakes, or other natural dis- time, and/or additional cost, depending on the
asters; export or import restrictions; closing of circumstances and the ability of the contractor
harbours, docks, canals, or other assistance to to substantiate its claims.
or adjuncts of the shipping or navigation of or

15
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

6. LIABILITY vide for a limitation of liability, the cap is usu-


ally set at an amount equivalent to the contract
6.1 Exclusion of Liability price, or an agreed percentage of the contract
Liability for future fraud cannot be contractu- price.
ally excluded under mandatory law (Civil Code,
Article 1171). In addition, limitation of liability for In addition, in the absence of any agreement to
gross negligence and wilful misconduct may be the contrary, parties are also generally not liable
considered void, as it is contrary to public policy. for events of force majeure.

6.2 Wilful Misconduct and Gross However, it is not possible to limit liability if it
Negligence arises from a fraudulent act or an act consti-
Wilful misconduct and gross negligence are gov- tuting gross negligence or wilful misconduct.
erned by the Civil Code provisions on tort. Gross Such a stipulation would be considered void, as
negligence has been interpreted by the Supreme explained in 6.1 Exclusion of Liability.
Court to be the “want of even slight care and
diligence” and “such entire want of care as to
raise a presumption that the person in fault is 7. RISK, INSURANCE AND
conscious of the probable consequences of SECURITIES
carelessness, and is indifferent, or worse, to the
danger of injury to person or property of others”. 7.1 Indemnities
Indemnities are normally used to limit risk in
Under Article 2176 of the Civil Code, whoever construction contracts. Typically, indemnities
by act or omission causes damage to another, are given by the contractor to the employer for
there being fault or negligence, is obliged to pay the following:
for the damage done. Meanwhile, in addition to
actual damages, a party that acts with gross • the failure of the contractor or subcontrac-
negligence may also be liable for exemplary tors to perform their obligations pursuant to
damages under Article 2231 of the Civil Code. the contract or in accordance with applicable
laws and regulations;
As explained in 6.1 Exclusion of Liability, limi- • the failure of the contractor to complete the
tation of liability for gross negligence and wilful works within the agreed period;
misconduct may be considered void. • the contractor’s or subcontractor’s negli-
gence, errors, omissions, negligent supervi-
6.3 Limitation of Liability sion, and negligent construction administra-
Parties may contractually limit their liability. Typi- tion;
cally, limitations on liability expressly pertain to • breach of warranties and of confidentiality
the liabilities of the contractor in general under obligations under the contract;
the contract. Parties also usually agree to limit • infringement or violation of the intellectual
liabilities for certain types of consequential dam- property rights of third persons;
ages, such as lost profits. In these cases, parties • death, disease or injury to the contractor’s or
typically agree that these damages cannot be subcontractor’s employees, or damage to any
claimed by one party against another, subject property arising from the construction works,
to statutory limits on limitations of liability (eg, which are attributable to the contractor;
fraud, gross negligence). When contracts pro-

16
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

• employment-related claims of the contractor’s ance companies acceptable to the employer.


employees; The policies required normally include:
• unpaid bills for labour and materials; and
• damage caused by the contractor or its • contractor’s all-risk insurance – against all
employees to any property of the employer risks, including fire, earthquake, typhoon, hur-
and the adjoining property. ricane, windstorm, any other similar perils, or
any other cause;
7.2 Guarantees • third-party liability insurance – against all
The contractor generally guarantees the works claims for bodily or personal injury, death
performed in the contract against defects in and/or damage to property;
workmanship and material for a certain period of • professional liability insurance – against loss-
time counted from the completion of the works. es suffered from negligence, wrong advice
The guarantees usually include: and other similar acts of advisers; and
• automobile liability insurance – against bodily
• that the works conform to the requirements injury, death and property damage arising
of applicable law, the contract, and the rel- from owned, non-owned and hired vehicles.
evant requirements of the employer, and that
the same shall be free from hidden defects, 7.4 Insolvency
imperfections, or faults; The insolvency of a party is normally considered
• that all materials, facilities and equipment an event of default that would entitle the other
used in the works (if supplied by the con- party to terminate the contract, in accordance
tractor) are standard products of trade and with the terms of the contract. This remedy is
comply with the standards provided in the usually afforded to both the employer and con-
contract, and are free from defects; and tractor.
• that all civil works and installation of materi-
als, facilities and equipment are carried out In the event of insolvency of the employer, the
in a workmanlike manner according to the contractor is also usually given the right to cease
standards provided in the contract or sound all work immediately.
professional practices.
7.5 Risk Sharing
A certain amount of the contract price may also Risks arising from the construction works are
be subject to retention by the employer after generally the responsibility of the contractor.
completion of the works, which will cover any In line with this, contracts usually provide that
violation of warranties within the warranty peri- the contractor is fully responsible for the care
od. Alternatively, the contractor may be required of the works from the commencement of the
to deliver a warranty security (eg, a bond or letter works until handover to the employer, at which
of credit) to the employer, which shall remain in time the responsibility for the care of the works
force until the warranty period expires. would pass to the employer. However, even after
handover to the employer, the contractor would
7.3 Insurance still normally be liable for any loss or damage
Construction contracts often require the con- caused by its actions, and for loss or damage
tractors to obtain and maintain insurance poli- that may be the result of a previous event for
cies from reputable and financially sound insur- which the contractor was liable.

17
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

Risks that may possibly be shared by the par- Depending on the specific type of employment
ties would include force majeure and unforeseen under which the worker is engaged, employ-
circumstances (refer to 5.5 Force Majeure and ment contracts normally provide for the effec-
5.6 Unforeseen Circumstances). The parties tive date/duration of the employment relation-
would typically provide that losses or damages ship, the compensation and benefits granted to
arising out of force majeure or unforeseen cir- the employee, the reporting structure and work
cumstances shall not be the responsibility of the schedule, job description, rules on employment
contractor. termination, and other company rules and poli-
cies affecting the employee.

8. CONTRACT 8.2 Subcontracting


A D M I N I S T R AT I O N A N D Contracting and subcontracting are legally
CLAIMS permitted and are usual market practice in the
construction industry. Construction projects
8.1 Personnel are normally farmed out to contractor compa-
Party Responsible for Personnel nies and, subject to the agreement between the
The contractor would usually be responsible for employer and the contractor, portions or phases
providing and paying for all labour and manpow- of the project may be further subcontracted to
er needed for the performance and completion another entity.
of the works, and for ensuring that all relevant
labour laws applying to its employees are com- In a contracting/subcontracting arrangement,
plied with. workers of the contractor/subcontractor are
assigned and/or deployed to the project to per-
The contractor would also be required to imple- form the work under the construction contract/s.
ment an appropriate construction safety and
health programme at the contract site and For a contracting arrangement to be valid and
require all its employees to obey all applicable for the contractor to be considered a legitimate/
laws and regulations concerning safety at work. independent contractor, the following conditions
must be satisfied:
Consequently, contracts often provide that the
employer should not be answerable or account- • the contractor is engaged in a distinct and
able for the payment of wages, all applicable independent business and undertakes to per-
workers’ compensation, disability and other form the job/work on its own responsibility,
employment benefits, and any liabilities relating according to its own manner and method;
to the employment of the contractor’s employ- • the contractor has substantial capital to carry
ees. out the job on its own account, manner and
method, and investment in the form of tools,
Employment Arrangements equipment, machinery and supervision;
Workers in the construction industry are usually • the contractor is free from control and/or
engaged on project employment. Nevertheless, direction of a principal in all matters connect-
such workers may also be engaged under other ed with the performance of the work except
types of employment such as on a regular, cas- as to the result thereof; and
ual, fixed-term, or piece-work basis.

18
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

• a service agreement ensures compliance with • delineation of the IP to be retained by the


all the rights and benefits of the contractor’s contractor and employer, usually for IP
employees under labour laws. developed before and after the construction
engagement;
Furthermore, the elements of an employment • granting of permission to use pre-existing IP
relationship should not be present between the or IP retained by parties, without payment
employer and the contractor’s employees, par- (due to strict “technology transfer agree-
ticularly: ment” regulations, “licensing” of IP is usually
avoided);
• selection and engagement of the individual; • an agreement concerning ownership of jointly
• payment of wages to the individual; developed IP;
• power to dismiss or impose other disciplinary • an agreement concerning ownership of modi-
action on the individual; and fications of IP;
• power to control the individual with respect to • the confidential treatment of all IP disclosed
the means and method by which the work is and shared between the contractor and
to be accomplished (“control test”). employer;
• the automatic assignment of IP created dur-
The most important element to determine the ing engagement;
existence of an employer-employee relationship • a provision requiring execution of neces-
is the so-called “control test”. The presence of sary documents to effect/complete/formalise
such power of control will indicate an employ- record assignments of IP;
ment relationship, while its absence indicates • a provision to co-operate in enforcement of
an independent contracting relationship. Even assigned IP;
though no actual control is exercised, there • an agreement to subsequently assign IP that
can still be an employment relationship if there may not be covered by provisions on auto-
is a right to exercise control. Thus, the princi- matic assignment;
pal should be interested only in the results of • a waiver of moral rights, except where such
the performance of the agreed services by the waiver shall permit another:
contractor’s employees. The absence of such (a) to use the name of the author, or the title
control should be evident both in the agreement of their work, or otherwise make use of
with the contractor and in the day-to-day inter- their reputation with respect to any ver-
action between the principal and the contrac- sion or adaptation of their work which,
tor’s employees. because of alterations therein, would
substantially injure the literary or artistic
8.3 Intellectual Property reputation of another author; or
Intellectual property (IP) clauses typically found (b) to use the name of the author with re-
in construction contracts in the Philippines spect to a work they did not create; and
include: • provisions as to the ownership of IP rights in
feedback.
• a comprehensive description of “intellectual
property” should include trade marks, copy-
rights, designs, patents, or other IP recog-
nised anywhere in the world;

19
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

9. REMEDIES AND remedies available to each party in case of


DAMAGES breach. The only limitation would be mandatory
laws applicable to limitations of liability and pub-
9.1 Remedies lic policy, such as those prohibiting:
Philippine general contract law states that in the
event of a breach of contract, the injured party • waiver of remedies/actions arising from future
may choose between fulfilment of the obligation, fraud; and
otherwise referred to as “specific performance”, • waiver of remedies/actions involving gross
and the rescission of the obligation (if the breach negligence or wilful misconduct.
is substantial), with the payment of damages in
either case. The law further provides that those 9.3 Sole Remedy Clauses
who, in the performance of their obligations, are Sole remedy clauses are not typically used in
guilty of fraud, negligence or delay, and those construction contracts in the Philippines. How-
who in any manner contravene the intention ever, waivers of rights and remedies are gen-
behind such obligation, are liable for damages. erally allowed under Philippine law, and thus
enforcement of such waivers is possible.
The remedies of specific performance, rescis-
sion and damages are available to all relevant Nevertheless, sole remedy clauses may, in cer-
parties in a construction contract. Nevertheless, tain circumstances, be considered void and
the parties may contractually agree to limit or unenforceable if they essentially limit claims/
expand the available remedies of the parties. remedies in situations where limitations of liabil-
Aside from the statutory remedies, parties typi- ity are disallowed (eg, fraud).
cally agree that the following remedies are avail-
able in case of breach: 9.4 Excluded Damages
As mentioned in 6.3 Limitation of Liability,
• payment of liquidated damages by the con- parties usually agree to limit liabilities for certain
tractor, in case of delay; types of consequential damages, such as lost
• suspension of work by the contractor in case profits. In such cases, parties typically agree that
of the employer’s breach, in which case the these damages cannot be claimed by one party
contractor is entitled to an equitable adjust- against another, subject to statutory limits on
ment of the completion time and/or contract limitations of liability (eg, fraud).
price;
• the employer’s right to order suspension of 9.5 Retention and Suspension Rights
work due to the contractor’s breach; and Construction contracts typically allow the
• termination of contract for specified causes, employer to retain a portion of the contract sum
such as bankruptcy or insolvency and nega- for a specified period after the completion of
tive slippage of the contractor. the works, until the lapse of the agreed defects
liability period.
See 4.2 Payment and 5.3 Remedies in the
Event of Delays. Suspension rights are usually allowed and are
not typically contractually excluded. Normally,
9.2 Restricting Remedies the contractor is given the right to suspend work
It is common practice for parties to a construc- or terminate the contract on written notice to the
tion contract in the Philippines to agree on the employer, if the employer fails to pay the con-

20
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

tractor an approved request for payment. The 11 May 2021), the Philippine Supreme Court
employer is also usually given the right to order limited the grounds to appeal arbitral awards in
suspension of work due to a breach on the part construction disputes presided over by tribu-
of the contractor. nals under the CIAC. Factual issues may still be
appealed to the Philippine Court of Appeals, but
only on grounds that pertain to (a) challenges
10. DISPUTE RESOLUTION to the integrity of the composition of the arbi-
tral tribunal such as allegations of corruption,
10.1 Regular Dispute Resolution fraud, misconduct, evident partiality, incapacity,
Disputes arising out of construction contracts or excess of powers; and (b) allegations that the
that have no arbitration clauses are resolved tribunal violated the Constitution or positive law
through ordinary court litigation, before the first in the conduct of the arbitral process. Mean-
and second-level courts in the Philippines. while, issues involving pure questions of law are
to be resolved by the Supreme Court. Previously,
If a construction contract provides for arbitration the practice was to appeal all factual and legal
as the mode of dispute resolution, the dispute issues to the Court of Appeals, which allowed a
will be resolved via arbitration before the CIAC, re-examination of a CIAC arbitral award.
regardless of whether another institution is cho-
sen. The Philippine Supreme Court has held that 10.2 Alternative Dispute Resolution
“as long as the parties agree to submit their dis- Republic Act No 9285 (The Alternative Dispute
pute to voluntary arbitration, regardless of what Resolution Act of 2004) recognises mediation,
forum they may choose, their agreement will fall arbitration and other forms of alternative dispute
within the jurisdiction of the CIAC, such that, resolution mechanisms.
even if they specifically choose another forum,
the parties will not be precluded from electing Arbitration, mediation and the use of Dispute
to submit their dispute before the CIAC because Boards are alternative means of dispute resolu-
this right has been vested by law” (National Irri- tion available to parties to a construction con-
gation Administration v Court of Appeals, 1999). tract. These are commonly used in the Philip-
pines, subject to the limitation that, where a
Where a construction contract involves a project construction contract involves an arbitration
under the PPP Law, the revised IRR of the PPP clause, it is the CIAC that has jurisdiction over a
Law says that “acts and decisions of Regulators dispute arising therefrom.
shall not be subject to arbitration”.
Dispute Boards are also becoming popular in
Recent Court Ruling construction contracts in the Philippines, par-
In Global Medical Center of Laguna v Ross Sys- ticularly those that adopt, or are based on, a
tems International (GR Nos 230112 & 230119, FIDIC contract.

21
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

Quisumbing Torres is a member firm of Baker vises and assists on acquisitions and disposi-
& McKenzie International, a Swiss verein. Es- tions, commercial leasing, development and
tablished in 1963, it has nearly six decades of construction law, construction litigation/arbitra-
experience advising and assisting multinational tion, hotels, resorts and tourism, planning and
companies on various areas of real estate, in- land use, real estate management agreements,
cluding construction. Lawyers are organised real estate finance, real estate tax and REITs.
into distinct focus groups that can help address The firm published a Philippine primer on con-
specific client needs. One such group is the struction contract management that provides a
real estate (RE) team. The RE team has special- high-level presentation of the various features
ised legal expertise across all critical elements of Philippine construction law and of common
of real estate and construction. The team ad- issues encountered in construction projects.

AUTHORS

Julius Cervantes is a partner in Michael Macapagal is a partner


Quisumbing Torres’ corporate in Quisumbing Torres’ dispute
and commercial/M&A practice resolution practice group. He is
group and heads the real estate a member of the energy, mining
focus group. He is a member of and infrastructure industry
the restructuring and insolvency group, and the compliance and
focus group, and the industrials, manufacturing competition focus groups. He has 13 years of
and transportation group, as well as the legal practice involving arbitration,
consumer goods and retail industry group. He construction, healthcare disputes, compliance,
has been engaged in corporate and civil and criminal litigation, labour law,
commercial law practice for over 19 years, and intellectual property law, public-private
is experienced in M&A, real estate partnerships, project finance and joint venture
transactions, joint ventures, corporate matters. He is a member and deputy secretary-
restructuring, foreign direct investments, general for case administration of the
commercial agreements and contracts, Philippine International Center for Conflict
construction law, public procurement, and Resolution (PICCR), where he is also an
regulatory matters. He is a private sector accredited arbitrator.
representative to the Sub-Task Force on
Registering Property of the Philippine
government’s Ease of Doing Business and
Anti-Red Tape Advisory Council.

22
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres

Ramon Miguel Bacani is a Jared Amoroso is a senior


senior associate in Quisumbing associate in Quisumbing Torres’
Torres’ corporate and dispute resolution practice
commercial/M&A practice group. He heads the firm’s
group. He is also a member of transportation and logistics
the firm’s energy, mining and industry group subsector. Jared
infrastructure industry group and the real has 11 years of litigation experience, with a
estate focus group. He has 11 years of particular focus on criminal litigation and
experience advising foreign and domestic arbitration. He is one of a handful of Philippine
clients in M&A, joint ventures, corporate Fellows of the Chartered Institute of Arbitrators
restructuring, foreign investments, government and the Philippine Institute of Arbitrators. He is
procurement, infrastructure, energy, mining an accredited arbitrator of the Philippine
and natural resources, real estate, and general Dispute Resolution Center Inc, the Office for
corporate law matters. He represents clients Alternative Dispute Resolution, and the
across a range of industries, including Philippine Wholesale Electricity Spot Market
infrastructure, energy, mining and natural (WESM). Jared sat as an arbitrator in the first
resources, real estate, logistics, transportation, WESM arbitrations in the Philippines, and has
technology, media and telecommunications, acted as counsel in ad hoc and institutional
gaming, consumer goods and retail, and arbitrations.
industrial manufacturing.

Quisumbing Torres
16th Floor, One/NEO Building
26th Street corner 3rd Avenue
Crescent Park West
Bonifacio Global City
Taguig City
Philippines 1634

Tel: +63 2 8819 4700


Fax: +63 2 8819 4626
Email: QTinfodesk@quisumbingtorres.com
Web: www.quisumbingtorres.com

23
Chambers Global Practice Guides

Chambers Global Practice Guides bring you up-to-date, expert


legal commentary on the main practice areas from around the
globe.
Focusing on the practical legal issues affecting businesses, the
guides enable readers to compare legislation and procedure and
read trend forecasts from legal experts from across key jurisdic-
tions.

To find out more information about how we select contributors,


email Katie.Burrington@chambers.com

practiceguides.chambers.com

You might also like