Professional Documents
Culture Documents
Construction Law 2022
Construction Law 2022
Construction
Law 2022
Philippines
Julius Cervantes, Michael Macapagal,
Ramon Miguel Bacani and Jared Amoroso
Quisumbing Torres
practiceguides.chambers.com
PHILIPPINES
Law and Practice
Luzón
Manila Philippines
Contributed by: Mindoro
Samar
Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani Palawan
Panay
Leyte
and Jared Amoroso Negros
Quisumbing Torres see p.22 Mindanao
CONTENTS
1. General p.3 5.3 Remedies in the Event of Delays p.14
1.1 Governing Law p.3 5.4 Extension of Time p.15
1.2 Standard Contracts p.4 5.5 Force Majeure p.15
1.3 COVID-19 p.4 5.6 Unforeseen Circumstances p.15
2
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
3
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
repair, conversion, use, occupancy, mainte- developed two sets of template contracts: (i)
nance, moving, demolition of, and addition to CIAP Document 101, or the “General Conditions
public and private buildings and structures. It of Contract for Government Construction”; and
also serves as a basis for local ordinances enact- (ii) CIAP Document 102, or the “Uniform Gen-
ed by local government units for implementation eral Conditions of Contract for Private Construc-
within their respective territorial jurisdictions. tion”. Although these CIAP template contracts
are rarely used, the Philippine Supreme Court
Presidential Decree No 1445 (Government has, in some instances, considered certain pro-
Auditing Code of the Philippines or GACP) visions of CIAP Document 102 as evidence of
The GACP needs to be considered when dealing prevailing practice in the construction industry,
with construction contracts involving the gov- and has applied these provisions in instances
ernment. where there appear to be gaps or uncertainty
in the parties’ construction contract (see Werr
The GACP specifies that the powers of the Phil- Corp International v Highlands Prime, Inc, 2017).
ippine Commission on Audit (COA) extend to the
examination, audit and settlement of all debts On the other hand, for construction and infra-
and claims of any sort due from or owing to the structure projects procured by the Philippine
government or any of its subdivisions, agencies government, standard forms are normally used
and instrumentalities. This becomes relevant that contain the clauses and terms required
when, in the event of a dispute, a contractor under the relevant laws and regulations. For
obtains a favourable judgment against the gov- example, in construction projects procured
ernment. by the government under the GPRA, or those
undertaken by the government in accordance
There have been several instances in the past with the Build-Operate-Transfer Law (BOT Law),
when a CIAC award against the government standard forms are used that contain the terms
has been modified and reduced by the COA, required under the relevant law and their allied
pursuant to its power to approve money claims regulations. For government infrastructure pro-
against the government. In Taisei Shimizu Joint jects that are funded by way of foreign grants
Venture v COA and DOTr (2020), the Supreme covered by the Official Development Assistance
Court ruled that the COA may not disregard final Act (ODA Act), FIDIC forms are typically used.
and executory judgments rendered by courts
and other adjudicative bodies by disallowing any 1.3 COVID-19
part of such final award. The Philippines construction industry was the
fastest-growing in the Asia-Pacific region prior
1.2 Standard Contracts to the COVID-19 outbreak, but its growth has
The use of standard contracts is not mandatory been severely impacted by the pandemic.
in construction projects procured by a private
(ie, non-government entity) employer, and par- The COVID-19 pandemic has resulted in the
ties are generally free to agree on the form that imposition of varying degrees of health and
will be used. safety protocols across the country. During the
first half of 2020, only essential construction pro-
There have been attempts to come up with tem- jects, ie, those relating to COVID-19 facilities,
plate construction contracts for private projects emergency works, priority public and private
in the Philippines. For instance, the CIAP has infrastructure projects, as defined, and the like,
4
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
were allowed to operate on a skeletal workforce. same, and to carry out or correct the work by
As the policy direction for permissible work dur- itself or through other contractors;
ing the quarantine period stabilised, public and • to obtain title and ownership over all complet-
private construction projects eventually resumed ed works, and over all materials, equipment,
operations at full operating capacity, subject to tools, and supplies for which payment has
compliance with health and safety protocols. been made under the contract; and
• to request variations, in accordance with the
In an effort to adapt to the circumstances, the contract.
CIAC issued guidelines on how to conduct online
proceedings in construction arbitration proceed- Obligations
ings, which essentially require the parties to • To pay the contract price;
agree to the conducting of online proceedings. • to provide the contractor access to and pos-
session of the site, to enable the contractor to
The lockdowns have likewise given rise to force perform the construction works;
majeure claims. “Force majeure” under Philip- • to provide pertinent information regarding the
pine law, pertains to events that could not be site that may be needed by the contractor in
foreseen, or though foreseen, were inevitable connection with the construction works;
(Article 1174, Civil Code). This general principle • to obtain relevant government permits and
on force majeure, however, gives way to con- licences needed for the project; and
tractual stipulations by the parties. • to obtain and maintain the relevant insurance
coverages required under the contract.
5
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
a single specific project. In such cases, the UJV ular Licence with Annotation, which is a sub-type
itself must obtain its own PCAB licence. of Regular Licence under the Quadruple A Cat-
egory (“Quadruple-A Licence”). A Quadruple-A
A consortium between a PCAB-licensed con- Licence may be issued to a corporation organ-
tractor and a non-contractor may also be formed ised under Philippine law, including ones that
to undertake only a single specific project. In are up to 100% foreign-owned. An applicant for
such a case, the consortium itself must obtain a Quadruple-A Licence must have a minimum
its own PCAB licence. paid-up capitalisation of at least PHP1 billion at
the time it applies for the licence. The holder
Entities that act as contractors are also normally of a Quadruple-A Licence may undertake only
required by employers to satisfy certain legal, specific types of vertical and horizontal projects,
financial and technical eligibility requirements. each with a prescribed minimum contract value.
6
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
Rights and Obligations Under a Construction • to ensure security and safety at the site; and
Contract • to procure and maintain appropriate bonds
The general rights and obligations of the con- and insurance from reputable and financially
tractor under a construction contract normally sound companies acceptable to the employ-
include the following. er.
7
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
General Relations Between the Subcontractor direct government appropriations and financ-
and Employer ing arrangements secured from private financial
Construction contracts may or may not allow the institutions. Another typical source of financing
contractor to subcontract the whole or a por- for construction projects procured by the gov-
tion of the works, or may require the contractor ernment would be Official Development Assis-
to obtain the employer’s consent prior to such tance (ODA) in the form of loans and/or grants
subcontracting. secured from foreign governments and/or from
international financial institutions such as the
If subcontracting is allowed, it is generally the World Bank and the Asian Development Bank.
contractor that remains liable to the employer for
all the acts of its subcontractors, including any Rights and Obligations Under a Construction
negligent, wilful or reckless acts or omissions Contract
on the part of any subcontractor. It is also the Financiers are not typically made parties to
contractor, and not the employer, that is typically the construction contract. However, there are
responsible for the proper and timely payment of instances where the construction contract would
all subcontractors. expressly provide that the financiers are entitled
to certain rights, such as the following:
General Relations Between the Subcontractor
and Contractor • extensive information, auditing and inspection
See 2.2 The Contractor with regard to general rights;
relations between the contractor and subcon- • granting of a security interest over the project;
tractors. • to cure the breach on behalf of the defaulting
party; and
General Relations Between the Subcontractor • to nominate a third party (which may be the
and Financier financier itself) to assume the rights of the
Generally, no principal-agent, employer-employ- defaulting party.
ee or partnership relationship is created between
subcontractors and financiers. The subcontrac- Construction contracts do not usually provide
tors’ relationship with the financiers will generally for obligations of financiers.
be governed by the terms of the agreements (if
any) that may exist between them. General Relations Between the Financier and
Employer
2.4 The Financiers The relationship between the employer and the
Companies and/or Institutions That Act as financier would normally be governed not by the
Financiers construction contract, but by the financing or
For construction projects procured by a private other similar agreement between the employer
(ie, non-government entity) employer, the financ- and the financier. However, as mentioned above,
ing required by the employer and/or the con- certain rights may be granted to the financier
tractor is usually secured from private financial under the construction contract, in order to pro-
institutions, such as banks. tect the financier’s financial interest in the pro-
ject.
On the other hand, for construction projects pro-
cured by the government, the financier would
normally be the government itself through
8
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
9
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
10
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
Except for the Contractor’s Licence (which the Operational services are usually covered by a
contractor must obtain and hold in its own name), separate agreement between the employer and
all the permits required for the construction pro- an operation and maintenance service provider
ject would normally be issued in the employer’s (which may or may not be the contractor). See
name. However, the contract usually provides 3.7 Maintenance.
that the contractor is responsible for obtaining
such permits for and on behalf of the employer. Financing arrangements are also usually cov-
ered by a separate financing agreement and
are independent of the construction. However,
the financier may also be provided with certain
11
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
rights (see 2.4 The Financiers), which may be to inspect the works. If the employer finds that
exercised in accordance with the terms of the Substantial Completion has indeed been met, it
construction contract. will issue a Certificate of Substantial Completion.
If the employer finds that Substantial Comple-
The transfer of the project from the contractor to tion has not been met, it will notify and allow the
the employer is normally governed by the terms contractor to perform the works necessary to
of the construction contract. achieve Substantial Completion.
12
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
In the absence of any contractual stipulation, that are typically used are cost plus fixed per-
the defects liability period under the Civil Code centage, and with lesser frequency, cost plus
(Article 1723) applies. fixed fee.
13
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
for reasons attributable to the employer, the and the works would need to be performed in
contractor may be entitled to a claim for extra accordance with its terms.
cost, and delay in said payment shall entitle
the contractor to an extension of time and to In either case, any amendment to the plans,
payment of interest. schedules and milestones requires approval by
the employer and the contractor.
Advance payments, delayed payments and/or
interim payments are schemes that are gener- The completion of milestones is subject to
ally used and may be stipulated in construction verification and testing (see 3.9 Tests and 3.10
contracts. For instance, the parties may mutu- Completion, Takeover, Delivery). Milestone
ally agree on the amount of advance payment certificates would also usually be issued by the
to be made by the employer, subject to the con- employer to evidence the completion of mile-
tractor’s posting of a surety bond of equivalent stones.
amount to guarantee repayment. The advance
payment is used for mobilisation, purchase of 5.2 Delays
materials, etc. In relation to delay in payments, see 4.2 Pay-
ment.
4.3 Invoicing
The particular means and form of invoicing are Parties are free to stipulate what constitutes a
not normally provided in the contract. However, delay in performance and the effects of the delay
in milestone payments, approval by the employer on the respective obligations of the parties.
is generally required before the contractor may
issue invoices to the employer for the particular A party is generally required to notify the other
payment. party that the latter is causing a delay. This is
consistent with Article 1169 of the Civil Code,
which states that those obliged to deliver or
5. TIME do something incur a delay from the time the
demand is made. However, demand is not nec-
5.1 Planning, Programme essary for the delay to exist when the law or obli-
Generally, the plans, schedules and milestones gation expressly so declares, such as express
are arranged and determined by the employer, stipulation in the agreement as to the contract
and finalised and incorporated into the contract key dates or timeline. Nevertheless, a notifica-
upon agreement with the contractor. Inputs from tion requirement is common practice in order to
the architect and the employer’s other consult- determine the period from which an extension of
ants may also be taken into account in preparing time or additional cost claim shall be based, if
the plans, schedules and milestones. any. After notification, the claiming party is gen-
erally required to substantiate the impact of the
In some instances, the contract may also pro- delay and its corresponding entitlement to an
vide that the contractor should prepare a con- extension of time and/or additional cost claim.
tractor’s plan, consistent with the scope of the
work and the requirements of the employer, for 5.3 Remedies in the Event of Delays
approval by the employer. Once approved, the The employer would typically be entitled to the
contractor’s plan is binding between the parties, payment of liquidated damages and other con-
sequential costs (which may be collected from
14
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
the performance bond) in the event of delay by within any place; rationing or allocation, whether
the contractor. Substantial delay may also be imposed by law, decree, or regulation; etc.
cause for the employer to terminate the con-
struction contract. Nonetheless, parties are free to contractually
limit or exclude certain circumstances from
5.4 Extension of Time being qualified as force majeure events.
In practice, if the contractor is obstructed or
delayed in the completion of the work by reasons 5.6 Unforeseen Circumstances
not attributable to the contractor (ie, employer’s Unforeseen circumstances may be in the follow-
action, neglect, delay or fault; third-party strikes ing forms: fortuitous events, as discussed under
or lockouts; an act of God or force majeure; etc), 5.5 Force Majeure, legal or physical impossi-
the contractor is entitled to an equitable adjust- bility, or difficulty beyond the contemplation of
ment of the completion time. the parties. The provisions of the Civil Code are
deemed written into the contract. Unless the
The contractor must, within a period specified parties stipulate otherwise, the provisions of the
under the contract, notify the employer. In turn, Civil Code will govern.
the employer must, within a similar specified
period, give the contractor an equitable adjust- Under the Civil Code, a debtor in obligation to
ment of the completion time, subject to the perform a service will be released when the obli-
employer’s determination as to the period. If the gation becomes legally or physically impossible
contractor and the employer cannot agree on without any fault on the part of the obligor. Legal
the proposed period, the contract may provide impossibility refers to instances where an act is
mechanisms to settle the dispute. The parties prohibited or prevented by law, while a physical
may also stipulate that the employer’s failure impossibility is where an act can no longer be
to reply to the contractor may be deemed as accomplished by reason of its nature.
approval by the employer of the adjustment
requested by the contractor. As for difficulty beyond the contemplation of the
parties, the Civil Code provides that when the
5.5 Force Majeure service has become so difficult as to be mani-
Under the principle of force majeure (also known festly beyond the contemplation of the parties,
as fortuitous events) in Philippine law, no person the obligor may also be released from the obliga-
is responsible for events that could not be fore- tion, in whole or in part. The scenario contem-
seen or that, although foreseen, were inevita- plated includes exceptional changes in circum-
ble. The most common force majeure events in stances, taking into account the risks assumed
construction contracts in the Philippines include: by the parties at the inception of the contract.
war, riot, sabotage, acts of terrorism, insurrec-
tions, acts of public enemies; strike, industrial Unforeseen circumstances may be classified
dispute, blockade, labour dispute, lockout; fire, as force majeure or a change in legislation that
explosion, flood, typhoon, tornado, epidemic would entitle the contractor to an extension of
or pandemic, earthquakes, or other natural dis- time, and/or additional cost, depending on the
asters; export or import restrictions; closing of circumstances and the ability of the contractor
harbours, docks, canals, or other assistance to to substantiate its claims.
or adjuncts of the shipping or navigation of or
15
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
6.2 Wilful Misconduct and Gross However, it is not possible to limit liability if it
Negligence arises from a fraudulent act or an act consti-
Wilful misconduct and gross negligence are gov- tuting gross negligence or wilful misconduct.
erned by the Civil Code provisions on tort. Gross Such a stipulation would be considered void, as
negligence has been interpreted by the Supreme explained in 6.1 Exclusion of Liability.
Court to be the “want of even slight care and
diligence” and “such entire want of care as to
raise a presumption that the person in fault is 7. RISK, INSURANCE AND
conscious of the probable consequences of SECURITIES
carelessness, and is indifferent, or worse, to the
danger of injury to person or property of others”. 7.1 Indemnities
Indemnities are normally used to limit risk in
Under Article 2176 of the Civil Code, whoever construction contracts. Typically, indemnities
by act or omission causes damage to another, are given by the contractor to the employer for
there being fault or negligence, is obliged to pay the following:
for the damage done. Meanwhile, in addition to
actual damages, a party that acts with gross • the failure of the contractor or subcontrac-
negligence may also be liable for exemplary tors to perform their obligations pursuant to
damages under Article 2231 of the Civil Code. the contract or in accordance with applicable
laws and regulations;
As explained in 6.1 Exclusion of Liability, limi- • the failure of the contractor to complete the
tation of liability for gross negligence and wilful works within the agreed period;
misconduct may be considered void. • the contractor’s or subcontractor’s negli-
gence, errors, omissions, negligent supervi-
6.3 Limitation of Liability sion, and negligent construction administra-
Parties may contractually limit their liability. Typi- tion;
cally, limitations on liability expressly pertain to • breach of warranties and of confidentiality
the liabilities of the contractor in general under obligations under the contract;
the contract. Parties also usually agree to limit • infringement or violation of the intellectual
liabilities for certain types of consequential dam- property rights of third persons;
ages, such as lost profits. In these cases, parties • death, disease or injury to the contractor’s or
typically agree that these damages cannot be subcontractor’s employees, or damage to any
claimed by one party against another, subject property arising from the construction works,
to statutory limits on limitations of liability (eg, which are attributable to the contractor;
fraud, gross negligence). When contracts pro-
16
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
17
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
Risks that may possibly be shared by the par- Depending on the specific type of employment
ties would include force majeure and unforeseen under which the worker is engaged, employ-
circumstances (refer to 5.5 Force Majeure and ment contracts normally provide for the effec-
5.6 Unforeseen Circumstances). The parties tive date/duration of the employment relation-
would typically provide that losses or damages ship, the compensation and benefits granted to
arising out of force majeure or unforeseen cir- the employee, the reporting structure and work
cumstances shall not be the responsibility of the schedule, job description, rules on employment
contractor. termination, and other company rules and poli-
cies affecting the employee.
18
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
19
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
20
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
tractor an approved request for payment. The 11 May 2021), the Philippine Supreme Court
employer is also usually given the right to order limited the grounds to appeal arbitral awards in
suspension of work due to a breach on the part construction disputes presided over by tribu-
of the contractor. nals under the CIAC. Factual issues may still be
appealed to the Philippine Court of Appeals, but
only on grounds that pertain to (a) challenges
10. DISPUTE RESOLUTION to the integrity of the composition of the arbi-
tral tribunal such as allegations of corruption,
10.1 Regular Dispute Resolution fraud, misconduct, evident partiality, incapacity,
Disputes arising out of construction contracts or excess of powers; and (b) allegations that the
that have no arbitration clauses are resolved tribunal violated the Constitution or positive law
through ordinary court litigation, before the first in the conduct of the arbitral process. Mean-
and second-level courts in the Philippines. while, issues involving pure questions of law are
to be resolved by the Supreme Court. Previously,
If a construction contract provides for arbitration the practice was to appeal all factual and legal
as the mode of dispute resolution, the dispute issues to the Court of Appeals, which allowed a
will be resolved via arbitration before the CIAC, re-examination of a CIAC arbitral award.
regardless of whether another institution is cho-
sen. The Philippine Supreme Court has held that 10.2 Alternative Dispute Resolution
“as long as the parties agree to submit their dis- Republic Act No 9285 (The Alternative Dispute
pute to voluntary arbitration, regardless of what Resolution Act of 2004) recognises mediation,
forum they may choose, their agreement will fall arbitration and other forms of alternative dispute
within the jurisdiction of the CIAC, such that, resolution mechanisms.
even if they specifically choose another forum,
the parties will not be precluded from electing Arbitration, mediation and the use of Dispute
to submit their dispute before the CIAC because Boards are alternative means of dispute resolu-
this right has been vested by law” (National Irri- tion available to parties to a construction con-
gation Administration v Court of Appeals, 1999). tract. These are commonly used in the Philip-
pines, subject to the limitation that, where a
Where a construction contract involves a project construction contract involves an arbitration
under the PPP Law, the revised IRR of the PPP clause, it is the CIAC that has jurisdiction over a
Law says that “acts and decisions of Regulators dispute arising therefrom.
shall not be subject to arbitration”.
Dispute Boards are also becoming popular in
Recent Court Ruling construction contracts in the Philippines, par-
In Global Medical Center of Laguna v Ross Sys- ticularly those that adopt, or are based on, a
tems International (GR Nos 230112 & 230119, FIDIC contract.
21
Law and Practice PHILIPPINES
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
Quisumbing Torres is a member firm of Baker vises and assists on acquisitions and disposi-
& McKenzie International, a Swiss verein. Es- tions, commercial leasing, development and
tablished in 1963, it has nearly six decades of construction law, construction litigation/arbitra-
experience advising and assisting multinational tion, hotels, resorts and tourism, planning and
companies on various areas of real estate, in- land use, real estate management agreements,
cluding construction. Lawyers are organised real estate finance, real estate tax and REITs.
into distinct focus groups that can help address The firm published a Philippine primer on con-
specific client needs. One such group is the struction contract management that provides a
real estate (RE) team. The RE team has special- high-level presentation of the various features
ised legal expertise across all critical elements of Philippine construction law and of common
of real estate and construction. The team ad- issues encountered in construction projects.
AUTHORS
22
PHILIPPINES Law and Practice
Contributed by: Julius Cervantes, Michael Macapagal, Ramon Miguel Bacani and Jared Amoroso,
Quisumbing Torres
Quisumbing Torres
16th Floor, One/NEO Building
26th Street corner 3rd Avenue
Crescent Park West
Bonifacio Global City
Taguig City
Philippines 1634
23
Chambers Global Practice Guides
practiceguides.chambers.com