Professional Documents
Culture Documents
ITH-FP1-F03181-M-SPE-0001 - A01 - Signed
ITH-FP1-F03181-M-SPE-0001 - A01 - Signed
Facility: FPF1
This Document is the property of Petrofac Facilities Management Ltd. and is not to be copied nor shown to a third party without written consent
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
ABBREVIATIONS
BS British Standard
SI Système Internationale
HOLDS
Page 2 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
CONTENTS
Page 3 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 4 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
1.0 INTRODUCTION
1.1 General
FPF1 has 2 x 50% Export Gas Compressor Trains (S-1154A/B). The compressors are MAN
diesel and Turbo RB type compressors which are driven by Solar Turbines Mars 90-13000S
Mechanical Drive.
The two parallel, three-stage centrifugal compression trains compress gas from the
Stella and Hurricane HP separator and the LP Production Separator. A common gas
dehydration package is situated between the MP (2nd) and HP (3rd) stages to dry the
gas to within CATS export specification.
The Export Gas Compressor (EGC) Seal systems are designed to API 692.
The original seal gas system utilised an external seal gas supply on start-up, provided
by the HP separators via the fuel gas start-up cooler and fuel gas system. This system
was positively isolated in 2018.
Since the system was isolated, it has not been possible to ensure clean, dry gas to the
EGC seals on start-up.
Ultimately these issues have led to the contamination of the dry gas seals on both
compressors’ multiple times. The lifespan of the dry gas seals is very poor: The expected
life is 5 years compared with only 18months average. Recently there has also been
sudden catastrophic failures on start-up of the compressors due to liquid drop out in the
seal gas, causing shearing of the seal faces. The root cause is poor quality fuel gas taken
from the second stage impeller on the LP stage, which does not meet superheat
requirements of API-692 (20°C). This causes the liquid drop out and contamination of
the seals during pressure holds and cold weather.
To exacerbate matters, the seal gas coalescing filter drain line is orientated vertically
so any liquids which do condense (due to the cooling effect of the gas purge across the
orifice) will accumulate in the low point of the pipework.
This specification defines the requirements for supply of new seal gas conditioning
equipment for Trains A and B in self-contained skids upstream of the two existing LP/MP
Gas Export Compressor seal gas conditioning racks.
The overall Process requirements are outlined in ITH-FP1-P03181-B-SPE-0001 Process
Specification for DGS Booster and Heater Package.
1.2 Supplier Responsibility
The Supplier (see section 1.4 for definitions) shall be responsible for the supply of the
new equipment, materials, and services in accordance with the requirements of this
specification and attachments.
1.3 Sub-Suppliers
Sub-Suppliers are subject to approval by the Company or his authorised representative.
Page 5 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
1.4 Definitions
Within this document, the following definitions apply:
- COMPANY: Ithaca Energy
- CONTRACTOR: Petrofac Asset Solutions
- PURCHASER: The Company or Contractor acting on behalf of the Company
- SUPPLIER: The party who manufactures or supplies the equipment
Within this document the following words shall have the following meanings:
- ‘Shall’ is used where a provision is mandatory
- ‘Should’ is used where a provision is preferred
- ‘May’ is used where alternatives are equally acceptable
- ‘Approve’ and ‘Approval’ are used where Purchaser does not wish an activity to
proceed unless certain features have been agreed with the Supplier in writing.
1.5 Units
SI units shall be used throughout with the exceptions of pressure, where Bar may be
used instead of Pascals (Pa), and nominal pipe sizes, where inches shall be used instead
of millimetres. Dual units (SI with Imperial units in parentheses) are permissible. This
shall apply to all documentation supplied by the Supplier in connection with the enquiry
and, if selected, the Purchase Order.
1.6 Language
All project correspondence and documentation shall be in the English language.
Page 6 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
The Control of Noise at Work Regulations 2005, Statutory Instrument 2005 No.
1643
Dry Gas Sealing Systems for Axial, Centrifugal, and Rotary Screw
API 692
Compressors and Expanders
Page 7 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 8 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 9 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 10 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Support points / bolt hole locations for skid holding down bolts.
Power and instrumentation cable connections at motor terminal boxes, skid edge
junction boxes and emergency stop stations.
Discipline engineering
Fabrication
Assembly
Delivery
Page 11 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 12 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Fluid Categorisation
Service Fluid
State Group
Gas compression Hydrocarbon Gas Gas 1
Page 13 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 14 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Horizontal tugger points (2 per side) will be required to facilitate orientation during
installation.
Each skid base shall have 4 off lifting points, each designed with a DAF of 2. The bases
shall be able to withstand an offshore marine lift with all the tanks/pumps/piping
installed.
The skid bases shall be provided with 2-off M12 earthing bosses at diagonally opposed
corners for earthing at site. Earth bosses shall also be provided within withing skids for
all equipment, junction boxes and cables trays etc as required.
Refer to Section 8.1 for painting/coating requirements.
5.3.4 Heat Conservation / Personnel Protection
Package equipment and pipework to be heat traced and insulted by the supplier in
accordance with Ithaca Specification FPF1-ST-G00001-E-SPE-0010 for Electrical Heat
Tracing (HOLD 3)
5.4 Piping
Pipework design and fabrication shall be carried out in accordance with ASME B31.3
Interconnecting pipework shall be 1” 900# RTJ Sch.80S in 316/316L stainless steel in
accordance with Ithaca Piping Specification FPF1-ST-G00001-E-SPE-0007, Piping Class
S9A.
Discharge lines shall terminate at skid edge with a bolted flange connection to match
the off-skid piping specification.
Pipework bolting shall be in accordance with the relevant piping specification.
All pipework and tubing shall be adequately supported. Pipe support bolting shall utilise
carbon steel structural grade bolting to BS.3692 Gr. 8.8 and proprietary pipe support
components from approved Sub-Contractors. These items shall be galvanised or coated
with an equivalent proprietary system.
Stainless steel pipework and tubing shall be insulated from carbon steel supports.
The Supplier shall submit inspection procedures for approval. Inspection personnel shall
be suitably independently qualified for the various inspection techniques. Defect
acceptance criteria shall be in accordance with ASME B31.3 Process Piping.
Pipework to be identified with colour coded tape indicating pipe contents and flow
direction in accordance with (HOLD 3).
Refer to Section 8.1 for painting/coating requirements.
5.5 Electrical
All electrical equipment shall be ATEX certified suitable for use in a Zone 2 hazardous
area, be CE marked and have a minimum IP rating of IP56.
Earthing of equipment, piping, cable tray, junction boxes, etc. to the skid bases shall
be Supplier responsibility.
All cable entries to electrical equipment shall be bottom entry.
Page 15 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 16 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
5.7 Structural
The assembled skids shall be designed to support all equipment, piping & valve
assemblies, pipe supports, walkways/gratings and nozzle loads at the tie-in points.
The package shall be designed to withstand the design loadings indicated in Section 4.0
during sea transportation and operation.
The Supplier shall advise the proposed structural design code with their proposal.
Fabrication shall be undertaken in accordance with EEMUA 197
Materials shall be carbon steel to EN 10225, or equivalents. Lifting padeyes shall be
made from a suitable grade of charpy-tested material.
Skid base full penetration welds shall be subject to 100% ultrasonic examination and
MPI, fillet welds shall be subject to 100% MPI.
Each skid structure and contained equipment together with the padeyes shall be
designed to accommodate a DAF of 2 during lifts.
All lifting equipment and skid lifting lugs shall be load tested and certified and shall
comply with the requirements of the LOLER regulations (1998).
The padeyes and attachment points on the skid shall have guaranteed through thickness
properties and be proof load tested to 2 x SWL. They shall be 100% UT examined for the
presence of laminations and 100% MP examined for the presence of surface defects after
load testing, as a minimum.
Each skid base shall be supplied with single point lift rigging. If multi leg slings or a
spreader beam is supplied, then racking shall be considered during their design and
specification.
Each skid base shall contain a fully welded drip tray, which will be designed to cover all
on-skid items with a 2” 150# RF drain connection located at skid edge.
Each skid base shall be supplied with 8 off sea fastening and 8 off skidding points each.
Structural bolting shall be to BS3692 Grade 8.8 with Grade 8 nuts, sherardized to BS
4921, or equivalent.
Page 17 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
The skid bases and attachments shall be painted in accordance with the specification
quoted in Section 8.0.
5.7.1 Package Dimensions and Weight
The Supplier to propose the layout of the skids ensuring there is adequate access to all
equipment for operation and maintenance.
The Supplier shall supply, with their bid, an outline General Arrangement drawing for
the package detailing overall dimensions and weight for the Purchaser’s review.
5.8 Materials Selection
Materials of construction shall be in accordance with the relevant Piping and Structural
Specifications.
Where specified, materials of construction shall be in accordance with the mechanical
datasheet for the equipment supplied.
Bids shall specify materials of all parts for Purchaser evaluation. Materials shall comply
with relevant EU/CE directives.
The Supplier shall verify suitability of all materials for the intended service.
5.9 Noise
The system shall be engineered so that the maximum noise level shall not exceed
85dB(A) at one metre distance from the equipment when operating at maximum
capacity.
5.10 Weight and Centre of Gravity
The Supplier shall complete and submit a Weight and CoG datasheet.
The Supplier shall weigh the completed pump and attachments before dispatch.
Page 18 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 19 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
7.2 Inspection
The Supplier shall provide free access to his works and that of his Sub-Suppliers for the
authorised representative of the Purchaser, or nominee.
All necessary certification on materials, workshop test data, inspection reports,
calibrations, etc., shall be made available to verify that the requirements of the
purchase order are being met.
Equipment surfaces shall not be painted until inspection, NDT and hydro-testing is
complete.
Fully assembled equipment shall be inspected for Mechanical Completeness,
Dimensional Accuracy and Painting Integrity.
7.3 Hydrostatic Testing
Equipment shall be hydro tested in accordance with the appropriate design code
requirements and PER (where applicable) with potable water after shop fabrication.
Chloride content of water used to test austenitic stainless-steel components shall be 30
ppm maximum.
The Supplier will provide a chart recorder to record both the pressure and water
temperature during all required hydrotests.
Bolting and gaskets shall be identical to service bolting and gaskets. Service bolting and
gaskets shall not be used for hydrotest.
On completion of test all equipment shall be dried and cleaned.
7.4 Functional and Performance Tests
The Supplier shall conduct functional and performance tests as part of the Factory
Acceptance Test (FAT) for the package assembly.
Test procedures shall be approved by Purchaser prior to conducting testing.
Page 20 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 21 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
8.0 NAMEPLATES
Equipment shall be provided with stainless steel nameplates, suitably located and
permanently fixed, so as to be easily visible.
Data provided shall include the following as a minimum, in addition to any applicable
Design Code or EU Directive requirements:
Manufacturer’s Name
Equipment Title
Design Code/Specification
Year Of Manufacture
Design Capacity
Design Pressure
Design Temperature
Weight Empty/Operating
Page 22 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 23 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
All items shall be properly packed and protected from damage during shipment to an
offshore marine environment. Each crate shall be clearly identified with the purchase
order number and identification symbol.
Small items shall be bagged, tagged and boxed for shipment. The boxes shall be suitably
labelled for traceability and identification of contents.
Lifting slings and any frames/lifting beams are to be fitted with packaging/crating in
place. Copies of lifting equipment certificates shall be supplied with the equipment.
9.4 On-Site Construction
The Supplier may be requested to supply suitably qualified personnel to assist with on-
site construction/commissioning activities. Any such request shall be subject to a
separate purchase order.
Page 24 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Monitoring and Witness points - where work will be offered by the Supplier but
where in the event of non-attendance by Purchaser, work can continue when
Page 25 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Hold points - where the work will be offered by the Supplier (5 working days
minimum notice) and must be witnessed by Purchaser’s representative before work
can continue.
Once accepted by Purchaser, the Inspection and Test Plan shall be incorporated into the
Contract without additional conditions by the Supplier and duly implemented.
Manufacturing shall not commence prior to the acceptance of this Inspection and Test
Plan. The approved Inspection and Test Plan will supersede the typical plan submitted
in the Tender.
10.4 Quality Audits
A schedule of quality audits to be carried out by the Supplier on his own activities and
those of his Sub-Supplier’s shall be provided.
10.5 Non Conformance
Supplier to include his proposed non-conformance procedure on the project
incorporating all Purchaser requirements.
Supplier shall Notify Purchaser immediately when potentially non-conforming
product/work is identified which requires repair or a concession. Purchaser will review
the potential non-conformance or non-conformance and either agree with Supplier’s
proposed repair procedure and agree with a concession request, or reject the
product/work. Non-conformances and proposed corrective actions shall be properly and
systematically documented for Purchaser’s approval.
10.6 Quality Assurance Evaluation
Purchaser may perform an assessment of Supplier’s technical and QA capabilities based
on the requirements set out in the Contract.
The Supplier shall confirm that access will be given to Supplier’s and potential sub-
Supplier’s facilities for the purpose of such evaluation; any reservation shall be clearly
stated.
In the event of a Contract being awarded, Purchaser reserves the right to demand
corrective action by the Supplier within specified time limits if any of the stated system
requirements are not met.
10.7 Quality Surveillance
General
In the event of a Contract being awarded, Purchaser may perform QA audits, technical
reviews, test witness, and inspections at source in order to verify compliance with
Contract requirements.
Audits/Reviews
Purchaser reserves the right to audit at source at any time during the duration of the
Contract by giving two weeks notice. The Supplier shall undertake to close out any
finding raised as part of such an audit.
Page 26 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
The Supplier shall co-operate in the provision of information and make available all
necessary personnel (Supplier/Sub-Supplier) to allow Purchaser to perform a
meaningful audit/review.
The results of any internal audits/reviews conducted by Supplier and Sub-Supplier shall
be documented and made available to Purchaser within two weeks after the completion
of such audits/reviews.
10.8 Test witness and Inspection
To achieve co-ordination of Purchaser’s surveillance with Supplier’s quality control
activities, Purchaser and Supplier will agree to Witness/Hold points for important
inspections and tests as listed in the Inspection and Test Plan established by the
Supplier.
Where Third Party Inspection (i.e. Purchaser or Purchaser’s appointed Representative)
is specified:
The Third Party Inspector shall issue an “Inspection Release Note” upon satisfactory
fulfilment of the Contract requirements. The issue of this note does not relieve the
Supplier of the responsibility for product quality or of any other obligations under
the Contract.
Goods shall not be despatched from Supplier’s premises until the “Inspection Release
Note” has been received. Should the goods be despatched prior to the receipt of this
note, Purchaser reserves the right to refuse delivery and to return the goods to the
Supplier.
Page 27 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 28 of 29
Mechanical Specification – Dry Gas Seal Booster & Heater Package ITH-FP1-F03181-M-SPE-0001 Rev A01
Page 29 of 29