Professional Documents
Culture Documents
of
DV Series
COMPRESSORS
Models 7 ½ and 9 ½
TABLE OF CONTENTS
INSTALLATION
Foundation
Erection
Drive and Motor Starter
Piping
Initial Start
Stopping the Unit
WEAR-IN PROCEDURE
TROUBLESHOOTING
Foundation
Oil Pump Arrangement
Oil Pump Assembly
Capacity Control Assembly
Gas End Assembly
Valve Assemblies
Valve Seat Removal (7 ½ x 5 Model only)
Piston Rod Packing
Crankcase Section Assembly
Starter Circuit Wiring Diagram
PARTS LISTS
Model DV 7 ½ x 5
Model DV 9 ½ x 7
The DV series compressor is designed to compress CO2 vapor. It is a vertical two cylinder, two
stage unit with a double-acting first stage. The compressor is automatically controlled by
pressure and temperature switches. These switches are set to control proper suction, discharge,
and oil pressures as well as discharge gas temperature. Complete information for vendor
supplied equipment is provided at the back of this manual.
The compressor was carefully inspected and checked before leaving the factory. After break-in,
the unit was tested for required capacity at various suction conditions. The actual capacity was
measured with flowmeters and recorded. Gas temperature (in and out), water temperature, water
volume, flowmeter readings, and electrical load data are on permanent record at the factory. This
is your assurance that Union Engineering has supplied you with the best possible equipment.
Should questions arise regarding the machine, our staff is ready to assist in any way possible.
INSTALLATION
The compressor is normally supplied as a complete package. The control equipment, heat
exchangers, moisture separators, traps, and motor assembly are mounted on a steel base. The
unit is ready to install on a suitable foundation. The compressor flywheel, matched V-belts, and
belt guard have been removed for shipping. The motor starter is normally supplied and shipped
separately for remote mounting.
The compressor should be located in a clean, dry area. There should be sufficient clearance to
perform routine maintenance, as well as pulling the piston rod, removing the crankshaft, or other
major repairs.
Foundation:
Soil bearing pressures for reciprocating machinery are much lower than those permitted by
municipal building ordinances. Test holes should be dug at the proposed site to determine the
nature of the soil and subsoil. If doubt exists about soil suitability, consult a foundation engineer.
The engineer will use the unbalanced forces in Table 1 to analyze a foundation problem.
Model 7 ½ x 5 Model 9 ½ x 7
@ 560 RPM @490 rpm
Vertical Primary 1912 lbs (867 kg) 3912 lbs (1774 kg)
Vertical Secondary 554 lbs (251 kg) 985 lbs (447 kg)
The foundation plan shows the recommended anchor bolt layout and a cross section view.
Special applications may require a modified foundation drawing that will be included where
applicable. Tubes should be placed around anchor bolts to allow for any misalignment in the
layout. Concrete should be kept out of these tubes when pouring the foundation.
Use ½ inch (13 mm) deformed steel reinforcing bars on 12 inch (305 mm) centers. The bars
should extend vertically and horizontally near all faces of the foundation. The concrete should be
poured 90º from the floor on the flywheel side. This is necessary for flywheel clearance.
Erection:
After the foundation is thoroughly cured, the unit can be lowered onto the anchor bolts. The
compressor must then be carefully leveled both crosswise and lengthwise. To do this, ¾ inch
(19.1 mm) thick wedges should be placed between the bottom of the base and the top of the
foundation. The wedges should be positioned as close to the anchor bolts as possible. This will
prevent excess strain on the unit when the bolts are drawn tight.
A grouting cement (two parts sand and one part cement) should now be poured under the unit.
Work the cement under the base from one side using a board to force it out the opposite side.
While the grouting is still soft, it should be troweled to slope slightly down from the base. Any oil
that may be spilled will then run off instead of soaking under the base.
All wedges should be removed after the grouting has set. This insures that the unit is bearing on
the grouting and not on the wedge. Fill all wedge holes with grouting cement. The finished
foundation should be coated with a good oil and waterproof cement paint.
The inside of the crankcase should be thoroughly cleaned to remove any dust and dirt that may
have entered. Use only clean lint-free rags for cleaning the crankcase. Fragments from waste or
linty rags may clog the oil strainer or passages. The cleaner the crankcase is, the cleaner the
lubricating oil will be.
After cleaning the crankcase, fill it with the recommended lubricating oil (see “LUBRICATION”
section). Add oil until it rises to ¾ of the oil level gauge. Capacities for each model are shown in
Table 2. When starting for the first time or after a long shut-down, pour oil over each main
bearing and connecting rod bearing. Also, lubricate the crosshead guides with a hand oiler.
DV 7 ½ x 5 8 7.5
DV 9 ½ x 7 12 11.3
Assemble the flywheel sheave to its hub. This assembly will be mounted on the crankshaft.
Before mounting the sheave, clean the hub and sheave mating surfaces. Wipe each surface with
a cloth moistened with light machine oil. Mount the flywheel assembly on the shaft. Tighten the
pull-up bolts alternately until each bolt has reached the torque value shown in Table 3. The
sheave type is stamped on the hub. The direction of rotation is clockwise when facing the
flywheel.
Install the matched V-belts and align the motor by moving it out to establish proper belt tension.
Refer to vendor bulletins section for proper belt tensioning and alignment procedures. It is
important that the compressor and the motor sheave are aligned. Misalignment will result in
reduced bearing and belt life.
Install the motor starter in the desired location. A fused disconnect switch should be installed on
the line side of the starter. Refer to motor nameplate for motor wiring data and information
required to properly size motor leads and fuses. Install control wiring from the compressor control
panel to the starter. See control circuit wiring diagram.
Piping:
Visually inspect the compressor to be sure that all parts are properly adjusted and in working
order. After a thorough check of the compressor, the following connections can be made:
1. Pipe the cooling water outlet to the drain (or to the return in closed systems).
2. Pipe cooling water to the inlet solenoid valve. This water circulates through the intercooler,
the aftercooler, and the compressor water jacket.
3. Pipe the suction to the compressor from the CO2 supply. The suction line must be blown
clean and thoroughly dried before final connection and start-up.
4. Pipe the discharge of the compressor to the remainder of the CO2 system.
5. Pipe the safety valve outlet and unloader solenoid valve to the outside atmosphere. As an
alternate, the unloader valve discharge may be piped into the suction line upstream of the
CO2 water scrubber.
If it is necessary to stop the compressor, place the “Hand – Off – Auto” switch in the “Off”
position.
WEAR-IN PROCEDURE
The compressor should be monitored closely when operating for the first time. Adjust water
control valves to temperature settings as indicated in the “INTERCOOLER AND
AFTERCOOLER” section. Extensive damage will result if any part of the unit overheats. In
addition to the daily checks outlined in the “MAINTENANCE” section, the following checks should
be made:
The compressor is designed to operate automatically. Safety controls are also built in to prevent
damage if a malfunction occurs. Refer to compressor wiring diagram.
A pressure switch (PS-2) controls operation from the suction side. This switch should be set to
close and start the compressor at a predetermined operating pressure (for example, 5 psig). The
switch should be set to open and stop the compressor at a desired minimum pressure (for
example 0.50 psig (0.04 kg/cm 2). Therefore, when CO2 vapor is available to the compressor for
collection, the suction pressure will increase and start the compressor. The compressor will
continue to run as long as the CO2 supply is sufficient to maintain pressure above the stop
setting of the switch.
All of the other switches in series with PS-2 are safety controls and must be closed before the
compressor can start.
The high pressure switch (PS-1) prevents excessive discharge pressure and should be set to
open and stop the compressor at approximately 5 psig (0.4 kg/cm2) above normal operating
pressure. For example, if the system operates normally at 250 psig (17.2 kg/cm 2), the high
pressure switch should be set to stop the compressor at 255 psig (17.6 kg/cm 2). The switch
should then be set to close at 245 psig (16.9 kg/cm 2), allowing the compressor to re-start. Since
control relay (1 TR) is operated by the high pressure switch (PS-1) in a holding circuit, the high
pressure reset button (PB-1) must be pushed to manually reset the circuit after the discharge
pressure drops to the restart pressure setting.
Temperature Switches:
The compressor discharge is controlled by a temperature actuated switch (TS-2). The switch is
set to open and stop the compressor at 300 ºF (149 ºC). The temperature switch should be set to
close and restart the compressor at 275 ºF (135 ºC).
The aftercooler discharge is also controlled by a temperature actuated switch (TS-1). This switch
is set to open and stop the compressor at 140 ºF (60 ºC). It should be set to close and restart the
compressor at 130 ºF (54 ºC).
The water supply to the coolers can be adjusted to maintain the gas temperature at the desired
level. To further protect against overheating, a water pressure switch (PS-4) is used. If water
pressure drops below 20 psig (1.4 kg/cm 2), the switch will open and the compressor will stop. It
is set to close and restart the compressor when water pressure rises to 25 psig (1.7 kg/cm 2).
The oil failure protection switch (PS-3) contains two separate switches. One switch is pressure
actuated and the other is a heat actuated time delay switch. Both switches are normally closed.
Oil pressure must build up to 20 psig (1.4 kg/cm 2) and open the time delay heater circuit within a
90 second time period. If this does not happen, the heat actuated switch will open and the
compressor will stop. If oil pressure rises to 20 psig (1.4 kg/cm 2) within the delay period, the time
delay heater is de-energized. The heat actuated switch remains closed and the compressor
continues running. If oil pressure drops to 15 psig (1.0 kg/cm 2) during operation, the time delay
heater will be energized. Unless the oil pressure returns to 20 psig (1.4 kg/cm 2) within 90
seconds, the compressor will stop. The control must be manually reset if the oil failure circuit
stops the compressor.
Unloaded Starting:
The compressor starts unloaded by means of the unloader solenoid valve (SOL-2) which is
normally open and relieves pressure from the compressor when it stops. This solenoid is
operated by a timer relay (1TR) which allows the unloader valve to remain open for approximately
5 seconds after the compressor starts. After the time delay, the timer contacts close, energizing
and closing the unloader valve. The discharge pressure then rises to the normal operating
pressure.
CAPACITY CONTROL
The compressor is normally provided with a means of reducing capacity to prevent frequent
starting and stopping of the compressor. Capacity control is achieved by one of the following
methods:
Valve Unloading:
The head end suction valve in the first stage cylinder is automatically unloaded by a pneumatic
diaphragm operator assembly and a three-way solenoid valve (SOL-4). Discharge gas is
reduced to 15 psig (1.0 kg/cm 2) and piped through the three-way solenoid valve to the diaphragm
operator. A 50% capacity reduction takes place when suction pressure decreases to the cut-in
setting of the capacity control pressure switch (PS-5). The three-way solenoid valve is then
energized and allows gas pressure to operate the diaphragm, pushing the capacity control in and
holding the suction valve open. When the three-way solenoid valve is de-energized, it vents the
diaphragm and this suction valve returns to normal operation.
The capacity control pressure switch (PS-5) is set to cut-in and cut-out within the setting of the
suction pressure switch (PS-2). For example, if the suction pressure switch is set to close and
start the compressor at 5 psig (0.4 kg/cm 2), the capacity control switch would be set to open and
load the compressor 100% at 4.5 psig (0.3 kg/cm 2); and with the suction switch set to open and
atop the compressor at 0.5 psig (0.03 kg/cm 2), the capacity control switch would be set to close
and unload the compressor 50% at 1 psig (0.04 kg/cm 2).
By-Pass Valve:
The compressor may be fitted with a diaphragm operated recycle valve to reduce its capacity.
The valve will by-pass discharge gas back to the compressor suction to maintain a constant
suction pressure. The valve is self-operating and, therefore, by sensing suction pressure directly
on the diaphragm, it will automatically open with a decrease in suction pressure. The recycle
valve must be field adjusted to maintain from 50% to 70% of design suction pressure. For
example, if the design suction pressure is 5 psig (0.4 kg/cm 2), the valve should start to open to
maintain 2.5 to 3.5 psig (0.17 to 0.24 kg/cm 2).
The life of a machine depends almost entirely upon the effectiveness of lubrication. Therefore,
the selection of the proper lubricants should be given considerable thought. For proper
crankcase lubrication, we recommend turbine type oil with rust and oxidation inhibitors such as
Mobil DTE extra heavy. A quality oil with the following ratings may also be used:
Crankcase oil must be maintained at the center of the oil level gauge with the machine operating.
Normal oil pressure should read 30 to 35 psig (2.1 to 2.4 kg/cm 2). The oil circulates rapidly in a
tightly enclosed space and will gradually increase in temperature. Because of this, the crankcase
may become uncomfortably warm to the hand. The case temperature may reach 60 ºF (16 ºC)
above ambient temperature. This is a normal condition and will do no harm. Oil pressure may be
higher than normal until crankcase reaches operating temperature.
Lubrication System:
The frame end of the compressor is lubricated by a force-feed (pressure) system. A gear-type
pump (see oil pump assembly drawing), driven from the crankshaft, draws oil through a
reinforced wire mesh strainer in the sump. It is then forced through drilled holes in the shaft.
From here, the oil is conducted to the main bearings, crankpin bearing, and through a drilled hole
in the connecting rod. Oil is then passed, under pressure, to the inside of the crosshead pin. It
is finally conducted to the sidewalls of the crosshead. The overflow from the pump is piped back
to the crankcase through an oil filter and pressure regulating valve.
The oil head is provided with a piston rod seal. The crankcase oil head is also fitted with a pair of
full metallic oil wiper rings. This completely seals the piston rod and isolates the crankcase. The
seal and rings prevent oil seepage along the piston rod. In addition, the crankcase is separated
from the gas end by a distance piece.
In a new machine, the oil should be examined after the first eight hours of operation. This is
important because the oil will wash out dust and dirt not removed during the initial cleaning.
Carefully examine the oil strainer in the sump of the frame. If it is dirty, it should be removed
immediately and cleaned.
The oil reservoir should be drained every 5,000 hours. Whenever the oil is completely drained,
clean the inside and bottom of the frame and remove any sediment prior to refilling.
Oil Pressure:
The oil pressure regulator valve is on the pump side of the compressor (see diagram). The oil
pressure is set at the factory but, if it is found necessary to adjust the oil pressure, loosen the jam
nut and adjust the screw to proper pressure; then retighten the jam nut. Refer to bulletins for
valve details. Under no circumstances allow the pressure to drop below 20 psig (1.4 kg/cm 2). If
this occurs, shut down the compressor. Investigate the cause and correct before restarting the
compressor.
Heat is produced as the gas is compressed in the first and second stages. This heat is removed
by heat exchangers. An intercooler cools the gas between stages of compression. An
aftercooler cools the gas as it leaves the compressor.
Be certain there is enough cooling water flowing through the cylinder jackets and coolers. The
temperature of the water from the high pressure cylinder head should be about 110 ºF (43 ºC).
The gas temperature exiting the intercooler should be maintained approximately 10-15 ºF (5-8 ºC)
higher than the suction gas temperature. The gas temperature exiting the aftercooler should be
approximately 100 ºF (38 ºC).
Both the intercooler and aftercooler are constructed of stainless steel with removable tube
bundles. The hot gas enters the top of the exchanger’s shell and exits the bottom along with
condensate.
The cooling water flow rate to the coolers and cylinder jacket are maintained by individual self-
powered temperature regulators after initial adjustment. Gas and water temperatures should be
checked on a regular basis and the temperature regulators serviced as required.
MAINTENANCE
A regular inspection and maintenance schedule will extend compressor life and reduce operating
costs. Table 5 is a guide that should be followed by maintenance personnel. Any inspection or
service performed on the compressor should be recorded.
The compressor piston is made up of several parts with the low pressure and high pressure
sections integrally assembled. See Gas (Upper) End Assembly drawing. The low pressure
section uses two compression rings. The high pressure section uses three compression rings
and one bull ring. The compression rings have a step cut and the bull ring is butt cut.
New rings should be checked for proper end gap. Place the ring squarely in the cylinder bore
and measure the gap. When checking rings for wear, the end gap should not exceed 60% of the
step cut. Roll each ring around in its grooves and make certain that it does not bind at any point.
The piston ring grooves should be checked periodically for taper in the shoulders. A new ring
cannot seat properly in a badly worn groove. Improper seating causes a poor seal which, in turn,
reduces capacity. Table 6 shows the proper ring gap and ring groove clearance.
Model DV 7 ½ x 5 Model DV 9 ½ x 7
Cylinder Bore 7.5” (191mm) 4.375” (111 mm) 9.5” (241 mm) 5.5” (140 mm)
Ring Gap .078” (1.981 mm) .078” (1.981 mm) .078” (1.981 mm) .078” (1.981 mm)
The clearance between the piston and the cylinder head should be checked if the piston is
removed for service. When the cylinders are cold, the clearance must be greater at the upper
end than at the frame end. This difference allows for the expansion of the piston due to heat.
When adjusting or checking the clearance, remove one of the valves on each end of the cylinder.
Insert a piece of 1/8” (3.2 mm) diameter solder between the piston and the head. Then hand
rotate the machine until top dead center has been passed and the solder is crushed. Hand rotate
the machine and check at the opposite end to see that the piston does not bump the head. Also
make sure that the clearance is greater at the top than at the frame end.
The clearances must be measured when the compressor is cold. Refer to the Table on the Gas
(Upper) End Assembly drawing for clearances. The upper clearance (“C”) should never be less
than .070” (1.78 mm). If it is, the piston may strike the head during operation.
To adjust piston clearances, first remove the compressor nameplate. Next, remove the screws
that hold the oil head in place. The oil head can be held out of the way by raising it up along the
piston rod and inserting two rods into the drilled holes provided in the distance piece. These rods
will support the oil head. Loosen the set screw and copper plug and loosen the crosshead nut.
The clearance at the frame end can be set by turning the rod in or out of the crosshead with a
wrench. Never use a wrench that will mar the rod. This will cause damage to the packing.
The rod has a ceramic coating in the area of the packing. This coating prevents scoring that
would otherwise be caused by lack of packing lubrication. Care should be exercised, when
handling the rod, to prevent cracking or chipping.
The first stage piston is held in place by the piston rod and nut. The second stage piston is bolted
to the first stage piston. The second stage piston must be removed to gain access to the piston
rod nut. Remove the oil scrapers before removing the piston rod. If the rod is withdrawn through
the scrapers, the lips will be damaged. Examine the lips and reinstall them face down. Table 7
shows the seating torque for piston rod nuts. Table 8 shows the seating torque for piston cap
screws, as well as other screws used on the compressor.
1” – 14 117 16
1 1/2” – 6 190 26
1 1/2” – 12 275 38
1 3/4” – 12 370 51
2” – 12 480 66
If any part of the piston assembly is replaced, the alignment of the entire assembly must be
checked. To do this, place the piston assembly between the centers of a lathe. Measure
eccentricity and squareness at a few points along the length of the assembly. These
measurements should not exceed .005” (0.13 mm) total indicator reading.
Valve parts must be in good condition for efficient compressor operation. Capacity can be
affected if these parts are not thoroughly inspected every 500 hours. Inspection may be more or
less frequent according to conditions. See “Valve Assemblies” drawing for parts breakdown of
low and high pressure valves.
The first and second stage valves are stainless steel. A different grade of steel is selected for
each component part. This insures maximum valve durability and efficiency. The valve disc is
guided by replaceable Teflon buttons that reduce wear.
To remove a valve from the cylinder, remove the valve screw cap and loosen the valve screw that
holds down the valve retainer. Next, remove the cover nuts, the cover, and the valve retainer.
The valve assembly may now be lifted out of the valve port. When removing an unloader valve,
remove the diaphragm holder, spring, and unloader nut. Then loosen the valve screw and
remove the valve from the port.
Disassemble the valve completely for cleaning and inspection. The valve guard is held firmly to
the seat by a threaded central post. Never distort a valve by clamping the assembly in a vise. A
stressed valve may later leak or fracture and drop pieces of steel into the cylinder.
The valve guard must be held while removing the seat. Prepare a block of wood as shown in the
drawing “Valve Seat Removal”. Cut the heads off four large nails. Drive the nails into the blocks
so they line up with the slots in the valve guard. The nails hold the guard from turning while the
seat is removed. A special wrench must be used on the DV 7 ½ x 5 second stage valve guards.
Suggested wrench detail can be found in the “Valve Seat Removal” drawing.
If the parts do not come apart easily, soak them in kerosene. Remove the valve discs and
spring. Check the Teflon guide buttons for wear. Carefully scrape and brush all foreign matter
from the parts, making sure the spring socket and valve guides are clean. Valve parts must not
be scratched or gouged. If the contact surfaces are damaged, the valves will leak when re-
assembled.
Examine valve parts thoroughly. Wear marks will be seen where valve parts slide against each
other. The marks are normal unless they are deep or rough. If a good deal of metal has been
worn off, new parts should be installed. If valve discs are worn, replace them. Look for worn or
broken springs and replace them.
If the compressor is equipped with an inlet unloader valve, examine the diaphragm carefully. If
any leakage or rupture is noticed, replace the defective diaphragms. Always keep spare
diaphragms on hand. Ordinary materials are not satisfactory and should not be used.
When reassembling the valve, make sure that the valve discs engage the pin and can be lifted
freely against their springs. The discs must also return squarely to their seats. To test this, insert
a screwdriver through a slot in the seat and push the valve disc off its seat.
Clean all the dirt from the valve seat before reinstalling the valve assembly into the compressor
valve port. When replacing the valve cover, make sure that the valve screw is backed off until the
cover cap screws are tightened.
The piston rod stuffing box is of a non-lubricated design. It consists of three sections of annular
case packing which are retained by a gland. Each section consists of one pair of Teflon rings.
The rings float freely and are not adjustable. Garter springs are used to seat the packing against
the rod. This design provides a tight seal even as the rings wear. Refer to “Typical Piston Rod
Packing Arrangement” drawing for a sketch of the packing arrangement.
Packing rings should be replaced when excessive leakage occurs. When installing packing rings,
thoroughly clean the stuffing box and piston rod. Remove any foreign matter from sealing
surfaces. Always inspect the O-ring in the bottom of the stuffing box. Replace the ring if it is
damaged.
Bearings:
The compressor bearings are run in before the compressor leaves the factory. The two main
bearings are double row roller bearings positioned at both ends of the shaft. They are extra large
engine bearings and should last the lift of the machine. The bearings are self-aligning and need
no adjustment. The main bearing on the drive end is locked in position by two plates. It is
important that the two plates are properly installed and the proper thickness gaskets are used on
the drive end bearing housing, as this is what determines the location of the crankshaft journal in
the center of the crosshead guide. The pump end bearing is free to float end wise. This provides
tolerance for any expansion of the frame due to heat.
The connecting rod is fitted with a bushing bearing at the crosshead end. A split bearing is used
at the crankpin end. The running clearance for the split bearing is from .002” to .003” (0.05 mm to
0.08 mm). ANY WORN BEARINGS SHOULD BE REPLACED IMMEDIATELY.
Crosshead:
Each crosshead is tin plated cast iron. They are cast in one piece and precision turned to fit the
guides. Grooves are machined into the crosshead for pressure lubrication. The crosshead
overtravels the guides. This results in uniform, negligible wear even after years of service. The
running clearance for the crosshead is one thousandth per inch of diameter.
The crosshead pin is alloy steel. It is hardened and ground to a precision fit. The pin is retained
by two snap rings that sit in a groove on each end of the pin. A set screw locks the pin and
prevents it from turning.
Oil Scrapers:
The crankcase is fitted with an oil tight cover through which the piston rod travels. There are two
oil scrapers in the cover to prevent oil from traveling up the rod into the gas section. A set of
cartridge seals prevents oil leakage from the crankcase. These seals also prevent contaminants
from entering the crankcase.
If compressor problems occur, the cause may be found in the following troubleshooting chart.
Always begin with simple troubleshooting checks and move toward more complex procedures.
By following this rule, the time you spend repairing the compressor will be minimized.
Compressor starts; then stops Low oil pressure Check oil pressure regulator.
Check switch setting.
Compressor starts and stops CO2 supply to suction inadequate Check CO2 supply from generator or
too frequently fermenters.
Low oil pressure Low oil level Fill oil to required level.
High oil pressure Oil viscosity too high Check manual for proper
specifications.
Piston rod / packing wear excessive Rod scored or worn Replace rod.
High interstage pressure Leaking second stage valves Repair or renew valves.
Check piston rings.
When ordering spare parts, please specify model number, serial number and sales order
number from “DV” series compressor nameplate, along with spare part item number, part
number, description and quantity of each part required.
ELECTRICAL PARTS:
Original motors, switches and overload heaters are specified by the user according to individual
power source characteristics. Replacements for these items can be ordered by the part
description and electrical rating.
SPARE PARTS:
Union Engineering recommends that each user of a “DV” series compressor keep at least a
small stock of certain spare parts on hand. These parts are identified by (S) in the “QUANTITY”
column of the following list:
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
Continued:
Continued:
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
ELECTRICAL PARTS:
Original motors, switches and overload heaters are specified by the user according to individual
power source characteristics. Replacements for these items can be ordered by the part
description and electrical rating.
SPARE PARTS:
Union Engineering recommends that each user of a “DV” series compressor keep at least a
small stock of certain spare parts on hand. These parts are identified by (S) in the “QUANTITY”
column of the following list:
CODE/
ITEM NO. DESCRIPTION QTY. PART NUMBER
Continued:
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
PISTON ASSEMBLY
CODE #15-1 – STOCK CODE #A0000075
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
CODE/
ITEM NO. DESCRIPTION QTY. STOCK CODE
NOTE: Above assemblies are completely assembled and ready for installation.