Professional Documents
Culture Documents
ABOUT US
Coolnet Power, the leading provider of
critical power supply and cooling system,
specialized in the manufacturing of
Precision Air Conditioner, Uninterrupted
Power Supply (UPS) and Data Center
Solution products in China.
4
1
Part
Company Introduction
Events
5
1
Part
Company Introduction
Techno Strength
Foundation:
The factory covers an area of 21,000 square meters with a floor height of 25
meters. It has a sheet metal workshop, assembly workshops, a painting
workshop, an assembly workshop, an inspection center, and a testing center.
.Output: The factory provides data center full life cycle product solutions,
infrastructure equipment manufacturing Current annual
6
1
Part
Company Introduction
Factory
7
1
Part
Company Introduction
Factory
Diversified Product
Sheet Mental
金方圆自动数字折弯设备 Printing Evaporator & Condenser PAC Assembly Assembly
8
1
Part
Company Introduction
Certificate
Certificate of Certificate for China Energy Saving ISO Occupational ISO Environment ISO Quality
Compliance Compulsory Product Certificate Health
Certification
9
1
Part
Company Introduction
Partners
10
02
Product Introduction
2
Part
Product Introduction
Product Introduction
PA C UPS Battery
12
2
Part
Product Introduction
Cool-Smart Series Precision Air Conditioning
Introduction
Introduction>>
The Cool-smart Series Computer Room Air Conditioner Is Designed For Small And
Medium-sized Computer Rooms, Base Stations, Equipment Rooms, Etc., Micro-cool Has
The Characteristics Of High Air Volume And Small Enthalpy With High Reliablity , High
Efficiency, Long Working Life And Energy Saving Advantages.
Features Applications
13
2
Part
Product Introduction
Cyber Master Series Precision Air Conditioning
Introduction
Introduction>>
Cyber Master Series precision air conditioning is specially designed for data centers,
telecommunication equipment rooms equipment and other application scenarios that
require precise environment with constant temperature and humidity. continuously
operation 24 hours*265 days. Cabinet structure design, cooling capacity range 4-200kW,
air cooled or chilled water cooled, widely installed for small, medium and large data
centers.
Features Applications
14
2
Part
Product Introduction
Lab High Precision Series Precision Air Conditioning
Introduction
Introduction>>
Coolnet Cyber Master HP Series high-precision Lab air conditioner is developed to meet
the high-precision temperature and humidity requirements in special environments. The
temperature control accuracy reaches ±0.2°C, and the humidity control accuracy reaches
±2%. It can be widely used in precision instrument laboratories, textile workshops, paper
workshops, tobacco companies, archives, etc.
Features Applications
15
2
Part
Product Introduction
In-row Precision Air Conditioning
PA C Introduction
Introduction>>
Cool Row Series Precision Air Conditioning is a row-level cooling solution for data centers
requires higher density and higher efficiency, The air conditioning unit and the server are
arranged in parallel and arranged between the servers. Since it is closer to the heat load,
the energy consumption of air supply will be greatly reduced, Effectively reduce the PUE of
data center, In-row structure design, cooling capacity range 12-60kW, air cooled or chilled
water cooled, dedicated design for micro data centers.
Features Applications
Power Supply &
Distribution
l Close to the Heat Resource u Data center (IDC)
l Electronically Commutated Compressor u High heat density computer room
l EC Fan u Modular Data Center
l Electronic Expansion Valve u container data center
l Cooling Capacity :13-60KW
16
2
Part
Product Introduction
Rack Mounted Precision Air Conditioning
PA C Introduction U>>
IntroductionPS
Cool Rack series rack-mounted air conditioner is a cabinet-level temperature control
product specially designed for integrated cabinets data center, modules data center or
high heat density data centers. It can be placed in the cabinet close to the heat source
and can accurately handle the output of the equipment in the cabinet. The high sensible
heat can effectively prevent the generation of local hot spots, reduce the return air
distance, increase the return air temperature, and improve the energy efficiency ratio.
17
2
Part
Product Introduction
Rack Data Center & MDC
18
2
Part
Product Introduction
Micro Data Center
Introduction U>>
IntroductionPS
The Micro Data Center is also called the intelligent cabinet or the integrated All-in-one
cabinet. It is a highly integrated intelligent, including the power supply system,
intelligent The environment maintains constant temperature and humidity. It is
configured with access control and cabinet door status monitoring systems, as well as
remote centralized control and other functions.
Advantages
• Construction: it can realize plug-and-play in the true sense and rapid deployment.
• Cooling efficiency: rack-mounted air conditioners are used to isolate the impact of
external space
• Appearance: Air conditioner, UPS, power distribution, etc. are integrated inside,
the cabinet door is made of transparent glass, and the built-in ambient light is
convenient for observing the status of the equipment.
19
2
Part
Product Introduction
Micro Data Center Product Categories
Multiple racks
Single Rack
20
2
Part
Product Introduction
Design Features for Single Rack
P IT Server P
Rack-
42URack D IT Server D
mounted U U
PDU IT Server
IT Server Servers,
1U Blank Panel Network
UPS
1U Blank Panel
Battery
Power
S Distribution
e Module
n 3/6kW UPS
Rack-mounted PAC o UPS
Microenviron Sr 2U Battery Pack Battery
ment se
n Rack-mounted
monitoring ss PAC
PAC
o
r
21
2
Part
Product Introduction
Design Features of Multiple racks
Hot Aisle
Cold Aisle
Controller+Display
42URack
UPS
Battery
22
2
Part
Product Introduction
Micro Data Center Components
7 Rail 60KG
8 Laminate 60-150KG
23
2
Part
Product Introduction
MDC Product
Introduction U>>
IntroductionPS
MDC is a commonly used overall solution for current data center construction. It is
highly integrated. A single MDC can include cabinets, closed passages, power supply
and distribution, cooling, DCIM, and wiring systems. One module can meet all the
basics for the stable operation of IT loads.
Advantages
24
2
Part
Product Introduction
MDC Product Categories
Dual-row
Single
25
2
Part
Product Introduction
MDC-Rack Production
The weld seam is neat and uniform, without defects such as cracks, undercuts, gaps, burn-
through, etc. The appearance of the weld seam has no defects such as slag inclusions, pores,
dry spots, pits, etc. After welding, it is polished, and the surface roughness meets the relevant
industry standards.
The surface of the coating layer of The standard color of the cabinet is
the cabinet is smooth and clean, black RAL9005, matte, and there is
with uniform color, no sag, and no no dizziness under the light of the
exposed bottom. Metal parts have cabinet. Other colors can be
no burrs and no rust. All parts have customized.
no sharp edges and corners, which
The surface of the cabinet is treated
can avoid harm to the human body.
with degreasing, pickling, anti-rust
The cabinet door and side panels phosphating, pure water cleaning,
are flat, without distortion, electrostatic spraying, etc., without
deformation, or obvious vibration;
the door panels have even
02 paint stripping, acid and alkali
resistance, solvent resistance,
openings. corrosion resistance, not affected by
hand sweat, adhesion 100%, anti-
The cabinet and its accessories, corrosion Shock, safety protection up
coatings, signs, decorations, etc. to IP20 standard.
are all made of flame retardant The surface spraying of the outer
and non-combustible materials. parts conforms to the European
ROSH standard and meets the
Surface treatment adopts professional high-hardness powder electrostatic national non-toxic and harmless
spraying to ensure anti-static and BS6497 international standards. The spraying standard.
surface spray thickness reaches 70-130µm. No blisters, no cracks, no
orange peel, no burrs and modifications on metal parts, anti-static.
26
2
Part
Product Introduction
MDC-Rack Structure
27
2
Part
Product Introduction
Modular Data Center Rack Specification
28
2
Part
Product Introduction
MDC-Rack Dimension & Configuration
29
2
Part
Product Introduction
Rack Other parts
30
2
Part
Product Introduction
MDC Components
(1) The built-in lighting system of the flip sunroof has an LED lighting strip on each side
(2) The H-type trunking integrates three slots of strong, weak current and optical fiber, and the number of slots can be modified
according to requirements, and the width of the slot can be adjusted.
(3) The jumping ladder between columns adopts a splicing structure and is used for cable jumping of double-row channels.
(4) The assembled base bracket is convenient for transportation and free of welding, which can help rapid construction and equipment
placement on site.
31
2
Part
Product Introduction
MDC Components
(1) The skylight support plate has a built-in ambient light, which can be replaced with the decorative panel at the rear of the cabinet.
(2) The MDC controller integrates end doors, lighting power supply, skylight, ambient light control, and fire protection linkage functions, and
can open the sunroof with one key.
32
2
Part
Product Introduction
MDC Components
(1) Ambient lights are embedded in the passage end door, and the door head is equip a
laser-cut color-changing LOGO lintel.
33
2
Part
Product Introduction
MDC Design Features
Skylight support
H-type trunking
panel
Decorative
hoarding LOGO
IT Racks Controller
Display
Frameless
In-row AC glass
34
2
Part
Product Introduction
MDC Components
1 Cabinet and cabinet parts Standard cabinet accessories for easy installation
2 L-shaped rail Carrying equipment without rails, divided into left and right pairs
It is used to isolate the hot and cold airflow inside the cabinet to prevent the airflow disorder in the cabinet, 1U
3 1U blank plate
tool-free installation
It is suitable for 1200mm depth racks, the load-bearing capacity is not more than 100KG, and the color is
4 Fixed shelf
consistent with the cabinets.
5 Cable management Installed directly on the mounting hole of the U column, used to manage horizontal cables, used with switches
Vertical cable management, installed vertically at the rear of the cabinet, the current cabinet is equipped with 2
6 Vertical cable management board
by default, mainly for installing PDUs
7 Cable slot on the top of the cabinet H-shaped channel, can be divided into strong current, weak current, optical fiber
Flip all-glass skylight with 95% light transmittance and built-in lighting module. This type of skylight does not
12 Movable skylight
need to be equipped with lamps. It is equipped with a 600-wide cabinet
13 Side doors Block the glass door and install a large screen to increase the aesthetics
14 Modular UPS Host 90-300KVA Modular UPS with standard 30KVA module
35
03
Projects Introduction
3
Part
Projects Introduction
Coolnet Case
Telkom Indonesia
Project Background: Telkom Indonesia is Indonesia’ s largest
state-owned telecom company and the global communication
service provider. Since 2010, Coolnet has started the
cooperation with Telkom Indonesia and appoint Coolnet as the
only provide of the precision cooling system for 10 years,
Annual purchase quantity is 50 sets.
Project Configurations: 12.6KW Precision Cooling System
15.6KW Precision Cooling System 31.5KW Precision Cooling
System
37
3
Part
Projects Introduction
Coolnet Case
38
3
Part
Projects Introduction
Coolnet Case
39
3
Part
Projects Introduction
Coolnet Case
Fluor USA
40
3
Part
Projects Introduction
Coolnet Case
Project Background:
National Autonomous University of Mexico, founded in 1551,
is Mexico and Latin America’ s oldest and largest
comprehensive university, one of the largest university in the
world, located in Mexico City, also one of the largest public
universities.
41
3
Part
Projects Introduction
Coolnet Case
Project Background:
Sinus-Dochi LLC is a leading HVAC service company in
Mongolia, boasting a team of technical engineers who
specialize in the field of refrigeration. We COOLNET
collaborated with the client on their existing data center
project to develop a comprehensive cooling system
design solution for their facility.
42
3
Part
Projects Introduction
Coolnet Case
Project Background:
Open DC Malaysia is a prominent cloud service network
technology company , specializing in server storage
services for its customers.
Project Configuration: 2 sets of 100KW air-cooled air
conditioners
Project Summary :The client was retrofitting an existing
data center and required two room-level air-cooled air
conditioners. However, due to the small and outdated
size of the data center, conventional precision air
conditioners could not be carried in properly.
Fortunately, COOLNET's precision air conditioners for
large server rooms are designed with modular
components, allowing for easy installation on-site and
tailored to the customer's requirements. This flexibility
and versatility are among the many strengths of
COOLNET's air conditioning solutions, enabling us to
meet the diverse needs of our customers.
43
3
Part
Projects Introduction
Coolnet Case
Project Summary :
The precision air conditioner requirement in this tender, issued by
the local government, is for a large-scale project and specifically
aimed at meeting the cooling needs of a data center.
During the tender process, the client conducted a comprehensive
evaluation of the supplier, including qualification, comprehensive
product performance, delivery time and after-sales service
capabilities. COOLNET established a professional team to
conduct extensive market research, comprehensive product
analysis, and online technical communication, resulting in their
selection as the supplier of precision air conditioners for the
project. Their commitment to delivering high-quality products and
exceptional customer service proved instrumental in securing this
partnership, showcasing COOLNET's expertise in the industry.
44
3
Part
Projects Introduction
Coolnet Case
Project Background:
SUNGROW is a listed PV inverter company, with inverter
equipment selling well in more than 150 countries around the world
and is a leading enterprise in Anhui Province.
Project Summary :
• Approximately 2,000 sets of specially customized white server
cabinets
• 800 sets of in-row precision air conditioners,
• large modular UPS
• Integrated DCIM system.
• Each cold aisle module is equipped with a double pull-out
Precision Power Distribution Cabinet.
45
3
Part
Projects Introduction
Coolnet Case
Project Background:
Our company has successfully established a partnership as a UPS
supplier for Saudi Aramco. Our first shipment of 100 UPS units has
been exported, and we are proud to see that our innovative
strength has once again been recognized. Moving forward, we
remain committed to providing reliable UPS power solutions to
support Saudi Aramco's projects.
46
3
Part
Projects Introduction
Coolnet Case
MDC-SUNGROW
Project Background:
This project is a 18-rack Cold Aisle Containment for Northwest
University of Political and Law.
Project Summary :
• Configuration: 1 set Dual-row MDC(18 racks)
• Rack: Size:600*1200*2000mm, 14 units IT racks
• Cooling: 2 sets 40KW In-row precision air conditioning
• Power: Row Modular UPS, 1 set
• Power Distribution Cabinet 1 set, DCIM 1 set
47
3
Part Coolnet Case
Project Background:
This is a IDC project for China Unicom-Changsha Branch
Project Summary :
• Configuration: 5 sets of 32-racks Double-row MDC
• Rack: Size: 600*1200*2000mm, IT racks: 110 units
• Cooling: 40 sets of 50KW in-row precision air conditioning
• Power; 2 sets of Modular UPS System
• Power Distribution Cabinets: 10 sets
• DCIM 1set
48
3
Part
Projects Introduction
Coolnet Case
Project Background:
This is a Container Data Center for University of Traditional
Chinese Medicine。
Project Summary :
• Configuration: 2 sets 20 ft CDC(11 racks)
• Rack: Size:600*1200*2000mm
• Cooling: 2 sets of 40KW In-row PAC for each Container
49
3
Part
Projects Introduction
Coolnet Case
Project Background:
The Jianyang court information construction project is located on
the 3rd floor of the newly built office building. Total power
consumption exceeds 100KW of high thermal density cold aisles.
The purpose of the IDC is to promote the innovation of court
administrative management, improve the court decision-making
system, promote the reform of industry management methods, and
then improve the level and efficiency of business management.
Project Summary :
• Configuration: 2 sets 11-rack Cold Aisle Containment
• Rack: Size:600*1200*2000mm
• Cooling: 3 sets 40KW In-row precision air conditioning
• Power: 175 KVA Modular UPS, 1 set
• Power Distribution Cabinet 1 set, DCIM 1 set
50
Thanks!