PRELIMINARIES
Main Contract: Part A: Information and requirements
Project particulars
Name of project
Short project title to be stated
Nature of project
short description to be stated
Location of project
Full postal address to be stated
Length of contract
Period in weeks to be stated
Names, addresses and points of contact of employer and
consultants email address to be stated
(1) Employer
(2) Project sponsor (e.g. employer's internal project manager)
(3) Project manager (if applicable)
(4) Principal contractor (under CDM Regulations)
(5) Person empowered by the contract to act on behalf of the
employer (person's title to be given (e.g. contract administrator)
(7) Quantity surveyor
(8) Consultants (separately identified)
(9) Clerk of works (if required by the employer)
Drawings
Drawings
List of drawings from which the bill of quantities was prepared
Drawing number, including revision status, drawing title, and
author to be stated.
Exceptions to be stated
Other documents
Pre-construction information
Page 1
Nigerian Institute of Quantity Surveyors
Page 2
BESMM4 PRELIMINARIES BILL
Information Required
Page 3
Nigerian Institute of Quantity Surveyors
Page 4
BESMM4 PRELIMINARIES BILL
Information Required
Page 5