Professional Documents
Culture Documents
Semen PC kg 1,340.00
Floor hardener kg 7,500.00
Semen instan Zak 157,700.00 semen ; 1 Zak @ 40 Kg
Semen Beton Hebel Zak 188,000.00 semen untuk bata hebel ; 1 Zak @ 40 Kg
-
5. TANAH Tanah urug / bahan tanah timbunan m3 60,000.00
Tanah Sirtu m3 80,000.00
-
6. LAIN-LAIN Aspal kg 12,550.00
-
-
-
II. BAHAN PENUTUP ATAP
1. SENG BJLS Seng gelombang uk. 5' kpg 31,500.00 uk. 0,8 m x 1,50 m
Seng gelombang uk. 7' kpg 43,500.00 uk. 0,8 m x 2,1 m
Seng gelombang uk. 10' kpg 62,000.00 uk. 0,8 m x 3,0 m
Seng polos m 28,000.00 lebar 88 cm
-
-
2. ASBES Asbes gelombang 5' kpg 55,000.00 lebar 105 cm
Nok asbes bh 45,000.00 panjang 105 cm; satu pasang
-
-
3. GENTENG KERAMI Keramik warna natural bh 12,300.00 setara Kanmuri; 1m 2 @ 14 bh
Keramik warna special bh 18,700.00 setara Kanmuri; 1m 2 @ 14 bh
Nok keramik warna natural bh 23,800.00 setara Kanmuri; 1m @ 3,9 bh
Nok Keramik warna special bh 36,700.00 setara Kanmuri; 1m @ 3,9 bh
-
4. GENTENG METAL Genteng metal uk. 2x4 (0.25mm) lbr 38,000.00 setara Sakura Merpati roof; 1 m2 @ 1,62 lbr
Genteng metal uk. 2x4 (0.3mm) lbr 46,000.00 setara Sakura Elang roof; 1 m2 @ 1,62 lbr
Genteng metal berpasir 2x5 (0,45mm) lbr 98,000.00 setara Multiroof; 1m2 @ 1,3 lbr
-
7. ATAP ZINCALUME Atap Zincalume (t.0,35 mm) m' 64,000.00 uk.lebar 105 cm
Atap Zincalume warna (t. 0,35 mm) m' 72,000.00 uk.lebar 105 cm
Atap Alkan (t.0,35 mm) m' 62,000.00 uk. Lebar 105 cm
Nok Zincalume 0,30 m' 26,000.00 uk. 300x60
Atap Zincalume warna (t.022mm) lbr 52,000.00 uk. 1600 mm x 740 mm, setara soka
Atap Zincalume warna (t.045mm) m' 97,000.00 setara bluecsoope; uk.lebar 105 cm
-
591
-
9. LAIN-LAIN Aluminium foil m2 46,500.00 setara Ika Sunilate; 1 roll @ 1,23 m x 40 m
buah 3,800.00
30 x 30 kotak 50,000.00 setara mulia ; 1 kotak @ 11 kpg
buah 4,545.45
40 x 40 kotak 65,600.00 setara Milan; 1 kotak @ 6 kpg
buah 10,933.33
50x50 kotak 128,000.00 setara Roman; 1 kotak @ 4 kpg
buah 32,000.00
-
2. KERAMIK 20 x 25 kotak 56,000.00 setara Impresso; 1 kotak @ 20 kpg
WARNA/TEKSTUR
bh 2,800.00
20 x 20 (KM/WC) kotak 80,000.00 setara Roman; 1 kotak @ 25 kpg
bh 3,200.00
30 x 30 (tekstur) kotak 141,000.00 setara KIA; 1 kotak @ 11 kpg
bh 12,818.18
30 x 30 kotak 61,200.00 setara KIA Tile; 1 kotak @ 11 kpg
bh 5,563.64
33,5x33,5 (tekstur) kotak 105,000.00 setara Roman; 1 kotak @ 8 kpg
bh 13,125.00
40 x 40 kotak 70,700.00 setara KIA; 1 kotak @ 6 kpg
bh 11,783.33
50x50 kotak 131,000.00 setara Roman; 1 kotak @ 4 kpg
bh 32,750.00
50x50 (tekstur) kotak 131,000.00 setara Roman; 1 kotak @ 4 kpg
bh 32,750.00
30x60 ktk 130,800.00 setara platinum; 1 kotak @ 5 kpg
bh 26,160.00
-
3. GRANITE TILE 60 x 60 kotak 309,600.00 setara Sincere; 1 kotak @ 4 kpg
bh 77,400.00
60 x 60 (tekstur) kotak 533,000.00 setara Indogres; 1 kotak @ 4 kpg
bh 133,250.00
80 x 80 kotak 663,360.00 setara Elegenza; 1 kotak @ 2 kpg
bh 331,680.00
80 x 80 (tekstur) kotak 838,000.00 setara elegenza; 1 kotak @ 2 kpg
bh 419,000.00
Granite Pola uk. 1,2 x 1,2 m ls 2,550,000.00 setara Indecor
Step nosing 30 x 60 bh 92,600.00 setara granito
Step nosing 20 x 60 bh 58,700.00 setara granito
592
1. BUIS BETON Buis beton dia. 100cm m 975,000.00 d0=100 cm; d1=120cm
Buis beton dia. 80cm m 875,000.00 d0=80 cm; d1=100cm
Buis beton dia. 60cm m 625,000.00 d0=60 cm; d1=75cm
Buis beton dia.40cm m 450,000.00 d0=40 cm; d1=48cm
Buis beton dia. 30cm m 345,000.00 d0=30 cm; d1=38cm
Buis beton dia. 20cm m 250,000.00 d0=20 cm; d1=25cm
-
2. ROSTER Roster keramik uk.30x30 bh 61,500.00 setara Trisensa
Roster keramik uk. 20x20 bh 45,000.00 setara Trisensa
Roster terawang bh 8,000.00 uk. 10x20
Roster beton bh 22,500.00 uk. 25x25
-
3. GLASS BLOK Glass block uk. 20x20 bh 26,800.00 setara Tidy
-
4. PAGAR BETON Panel beton lebar 50 bh 165,000.00 uk. 50x240
Panel beton lebar 40 bh 137,500.00 uk. 40x240
Kolom beton pracetak m 100,000.00 uk. 16x17
Pagar catur t. 60 bh 20,000.00
-
5. PAVING BLOK Segi enam t. 6 cm bh 2,229.73 1 m2 @ 37 bh; K 200
Persegi panjang t. 6 cm bh 1,875.00 1 m2 @ 44 bh; K200
Segi enam t.8 cm bh 2,500.00 1 m2 @ 37 bh; K 200
Persegi panjang t. 8 cm bh 2,102.27 1 m2 @ 44 bh; K200
Segi enam warna t. 6 cm bh 2,567.57 1 m2 @ 37 bh; K 200
Persegi panjang warna t. 6 cm bh 2,159.09 1 m2 @ 44 bh; K200
Segi enam warna t.8 cm bh 2,837.84 1 m2 @ 37 bh; K 200
Persegi panjang warna t. 8 cm bh 2,386.36 1 m2 @ 44 bh; K200
-
6. KANSTEIN Uk. 60x30x20/12 bh 55,000.00
Uk. 60x30x10/15 bh 52,500.00
Uk.40x20x10/13 bh 32,500.00
Uk. 60x35x18/21 bh 65,000.00 stdr K.250 (LRT)
7. BATACO BETON Bataco uk. 20x40 bh 2,300.00
-
8. JENDELA UPVC Jendela kaca dan kusen UPVC (uk. 1 m x bh 1,500,000.00 dua daun jendela
1,2 m)
Jendela kaca dan kusen UPVC (uk. 0.6 m x bh 995,000.00 satu daun jendela
1,5 m)
-
-
VI BAHAN BESI /BAJA /ALUMINIUM /BAJA RINGAN
Profil C channel 80.75 btg 92,000.00 Tegangan leleh minimum 550 MPa;p. 6 m
Profil C channel 75.75 btg 82,000.00 Tegangan leleh minimum 550 Mpa;p. 6 m
Profil C channel 75.65 btg 73,000.00 Tegangan leleh minimum 550 Mpa;p. 6 m
Pintu KM/WC Aluminium warna urat kayu bh 3,600,000.00 Aluminium 0,75mm ; coating powder 60 micron;
- frame louver (incl. kusen, lever handle uk. 80cm x 200cm; setara solidoor-starmas
stainless steel, engsel aluminium)
Pintu Aluminium warna urat kayu - 5 mm bh 4,300,000.00 Aluminium 0,75mm ; coating powder 60 micron;
ice glass (incl. kusen, lever handle stainless uk. 90cm x 215cm; setara solidoor-starmas
steel, engsel aluminium)
-
-
VII. BAHAN PIPA
1. PIPA PVC Pipa PVC AW 1/2" btg 23,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC AW 3/4" btg 30,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC AW 3" btg 178,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC AW 4" btg 294,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC DW 3" btg 96,000.00 setara Wavin; 1 batang @ 4 m
Pipa PVC DW 4" btg 151,000.00 setara Wavin; 1 batang @ 4 m
-
g346 -
2. PIPA GALVANIS Pipa galvanis 1/2" t.1,9-2,3 mm btg 140,000.00 1 btg @ 6m
Pipa galvanis 3/4" t.1,9-2,3 mm btg 190,000.00 1 btg @ 6m
-
3. LAIN-LAIN Lem pipa btl 8,000.00 1 botol @ 60 gram
-
-
-
VIII. BAHAN LANGIT-LANGIT
-
5. LIST PLAFOND List plafond 1x4 btg 8,000.00 1 batang @ 3,8 m
594
-
4. THINNER Thinner liter 31,800.00 setara Jotun: 1 kaleng @ 1 l
-
5. LAIN-LAIN Kuas 1" bh 10,000.00 setara prima
Kuas 1 1/2" bh 11,500.00 setara prima
Kuas 2" bh 14,000.00 setara prima
Kuas 3" bh 24,900.00 setara ace
Kuas 4" bh 35,900.00 setara ace
Kual roll bh 45,900.00 setara ace
Baki cat bh 16,000.00 NN
Coating batu alam liter 72,500.00 setara AM 152
-
X. BAHAN KACA
-
-
XII. BAHAN PENGUNCI DAN PENGGANTUNG
1 Pekerja OH 95,000.00
2 Tukang OH 125,000.00
3 Kepala Tukang OH 140,000.00
4 Mandor OH 165,000.00
4.3.1 Daftar Harga Satuan Bahan dan Upah Tenaga Kerja
Pekerja OH 145,000
Kepala Tukang OH 180,000
Mandor OH 185,000
Mekanik alat berat OH 150,000
Operator alat berat OH 165,000
Operator komputer/printer/ploter OH 165,000
Operator pompa OH 165,000
Pembantu driller OH 110,000
Pembantu Juru ukur OH 110,000
Pembantu mekanik alat berat OH 110,000
Pembantu operator alat berat OH 110,000
Sopir OH 150,000
Supir kendaraan < 2 ton (termasuk sedan) OH 150,000
Tukang Aspal OH 175,000
Tukang Batu OH 175,000
Tukang Besi OH 175,000
Tukang Besi Konstruksi OH 175,000
Tukang Cat OH 175,000
Tukang Erection OH 175,000
Tukang Gali OH 175,000
Tukang Kayu OH 175,000
Tukang Khusus Aluminium OH 175,000
Tukang Las Biasa OH 175,000
Tukang Las Konstruksi OH 175,000
Tukang Listrik OH 175,000
Tukang Pipa OH 175,000
Tukang Vibrator OH 175,000
B. MATERIAL KAYU
Dolken kayu gelam Ø 8-10 cm, pjg 3 m batang 15,000
Dolken kayu gelam Ø 6-8 cm, pjg 3 m batang 10,000
Formika Uk. 244 cm x 122 cm lembar 150,000
Kayu Kelas II m³ 4,300,000
Kayu Kelas III m³ 2,600,000
Kayu Kelas IV m³ 2,500,000
Kayu Bekisting/Perancah m² 2,250,000
List kayu profil m' 22,000
Multiplek tebal 6 mm lembar 78,000
Multiplek tebal 9 mm lembar 140,000
Multiplek tebal 18 mm lembar 375,000
Phenol film 12mm lembar 225,000
Plywood 4 mm lembar 70,000
Plywood 12 mm (120x240) lembar 185,000
Plywood 9 mm (120x240) lembar 150,000
Teakwood 4 mm (90x220) lembar 45,000
Teakwood 9 mm (90x210) lembar 67,000
Tripleks t=4mm, 120x240 cm lembar 70,000
D. MATERIAL PAVING
Kanstin K-200, 10x20x50 cm buah 32,000
Paving block 6 cm abu-abu K-200 m² 82,000
Paving block 6 cm warna K-200 m² 90,000
Paving block 8 cm abu-abu K-200 m² 105,000
Paving block 8 cm warna K-200 m² 115,000
E. MATERIAL DRAINASE
Buis beton Ø 20 cm d0=20 cm; d1=25cm; p=100 cm buah 250,000
Buis beton Ø 30 cm d0=30 cm; d1=38cm buah 335,000
Buis beton Ø 40 cm d0=40 cm; d1=48cm buah 425,000
Buis beton Ø 60 cm d0=60 cm; d1=75cm buah 600,000
Buis beton Ø 80 cm d0=80 cm; d1=100cm buah 850,000
Buis beton Ø 100 cm d0=100 cm; d1=120cm buah 950,000
Penutup U - Ditch 100 HD tebal 12 cm, panjang 0,6 m unit 825,000
Penutup U - Ditch 100 LD tebal 12 cm, panjang 0,6 m unit 725,000
Penutup U - Ditch 120, panjang 0,6 m unit 1,000,000
Penutup U - Ditch 20, panjang 0,6 m unit 55,000
Penutup U - Ditch 30, panjang 0,6 m unit 145,000
Penutup U - Ditch 40, panjang 0,6 m unit 215,000
Penutup U - Ditch 50, panjang 0,6 m unit 275,000
Penutup U - Ditch 60, panjang 0,6 m unit 330,000
Penutup U - Ditch 80 HD tebal 10 cm, panjang 0,6 m unit 650,000
Penutup U - Ditch 80 LD tebal 10 cm, panjang 0,6 m unit 380,000
U - Ditch - 100, panjang 1,2 m unit 2,785,000
U - Ditch - 120, panjang 1,2 m unit 3,500,000
U - Ditch - 140, panjang 1,2 m unit 4,400,000
U - Ditch - 20, panjang 1,2 m unit 390,000
U - Ditch - 30, panjang 1,2 m unit 660,000
U - Ditch - 40, panjang 1,2 m unit 1,000,000
U - Ditch - 50, panjang 1,2 m unit 1,050,000
U - Ditch - 60, panjang 1,2 m unit 1,200,000
U - Ditch - 80, panjang 1,2 m unit 1,950,000
F. MATERIAL PRECAST
Kolom beton pracetak 320 x 17 x 17 cm btg 370,000
Kolom beton pracetak 280 x 17 x 17 cm btg 305,000
Panel beton pracetak 5x50x240 cm buah 140,000
Panel beton pracetak 5x40x240 cm buah 120,000
H. MATERIAL PLAFOND
Akustik ukuran 30 cm x 30 cm lembar 10,000
Akustik ukuran 30 cm x 60 cm lembar 14,000
Akustik Ukuran 60 cm x 120 cm lembar 62,000
Asbes 1,00 x 1,00 m lembar 22,000
Bahan plafond PVC m2 85,000
Kalsiborad (120 cm x 240 cm x 5 mm) lembar 75,000
Kalsiboard (120 cm x 240 cm x 3,5 mm) lembar 55,000
Gypsum Board (120 cm x 240 cm x 12 mm) lembar 95,000
Gypsum Board (120 cm x 240 cm x 9 mm) lembar 75,000
List gypsum 1 batang @ 1,7 m m' 10,000
Listplank GRC (20 cm x 244 cm x 9 mm ) m2 75,000
List Profil plafond PVC M' 20,000
Pelat asbes tebal 3,5 mm lembar 41,000
Pelat asbes tebal 4 mm lembar 67,000
J. MATERIAL PEREKAT
Compound gypsum kg 15,500
Compound hardboard kg 84,000
Flexible waterproofing kg 30,000
Kassa m' 750
Kapur m3 1,750,000
Lem Serbaguna kg 92,000
Lem kayu kg 33,000
Lem silikon kg 25,000
Lem vinyl kg 30,000
Mortar siap pakai/perekat bata ringan kg 3,500
Paper tape hardboard m' 1,000
Pengisi khusus rongga nat kg 16,000
Perekat khusus penutup dinding kg 6,300
Perekat khusus penutup lantai kg 6,300
Perekat untuk wallpaper kg 180,000
NO. JENIS BARANG / BAHAN / UPAH URAIAN SATUAN HARGA
K. MATERIAL CAT
Amplas lembar 8,000
Cat anti karat kg 45,000
Cat dasar (cat besi) kg 60,000
Cat coating liter 64,000
Cat dasar tembok (sealer) kg 43,000
Cat dasar (cat kayu) kg 30,000
Cat genteng kg 40,000
Cat penutup (cat besi) kg 54,000
Cat penutup (cat kayu) kg 54,000
Cat penutup (cat tembok) untuk interior (dalam) kg 28,000
Cat penutup (cat tembok) untuk eksterior (luar) kg 97,000
Cat penutup (cat plafond) Biasa kg 24,000
Cat pelapis anti bocor kg 51,000
Dempul kg 34,000
Dempul kayu kg 10,000
Kalkarium kg 11,500
Kuas 1" buah 10,000
Kuas 2" buah 20,000
Kuas 3" buah 30,000
Kuas 4" buah 40,000
Meni besi kg 34,000
Meni kayu kg 24,000
Pengencer cat kayu/besi kg 28,000
Plamir kayu kg 18,000
Plamir tembok kg 18,000
Politur liter 43,000
Politur jadi liter 62,000
Politur melamic kg 47,000
Sanding kg 68,000
Vernis liter 32,000
M. MATERIAL KACA
Jendela nako m2 275,000
Kaca buram 12 mm m2 1,200,000
Kaca cermin 5 mm m2 220,000
Kaca cermin 6 mm m2 340,000
Kaca cermin 8 mm m2 920,000
Kaca gravire 5 mm m2 750,000
Kaca gravire putih 5 mm m2 850,000
Kaca lukis alur 5 mm m2 780,000
Kaca patri 5 mm m2 1,850,000
Kaca polos 3 mm m2 110,000
Kaca polos 5 mm m2 150,000
Kaca polos 8 mm m2 350,000
Kaca polos 12 mm m2 525,000
Kaca tanpa tripel 5 mm m2 2,650,000
Kaca triple 5 mm m2 3,250,000
Kaca triple platinum 5 mm m2 3,400,000
Kaca wireglass 5 mm m2 175,000
Profil kaca m¹ 15,000
Kaca Ray Band 3mm m2 625,000
Kaca Ray Band 5mm m2 825,000
N. MATERIAL SANITAIR
Batchcuip buah 6,500,000
Bak cuci piring stainless steel buah 350,000
Bak fiberglass 70 x 70 x 66 cm buah 655,000
Bak reservoir fibreglass (kapasitas 1000 liter) buah 1,320,000
Floor drain stainless steel buah 350,000
Floor drain plastik buah 35,000
Kloset duduk/monoblok buah 5,200,000
Kloset jongkok porselen buah 240,000
Kloset jongkok teraso buah 105,000
Kran air buah 47,000
Tempat sabun gantung buah 95,000
Tempat sabun tanam buah 40,000
Urinoir buah 2,500,000
Wastafel buah 750,000
Water drain + asesories set 265,000
O. MATERIAL MINYAK
Bensin liter 7,600
Minyak bekisting liter 11,000
Minyak Pelumas liter 35,000
Minyak tanah liter 13,000
NO. JENIS BARANG / BAHAN / UPAH URAIAN SATUAN HARGA
R. MATERIAL PERALATAN
Alat bantu set 60,000
Sewa alat las jam 35,000
Sewa crane sewa per hari unit 650,000
Sewa pipe suport sewa per bulan unit 12,800
Sewa scaffolding : sewa per bulan unit 45,000
S. MATERIAL LISTRIK
Box Panel 40 x 50 x 20 cm buah 475,000
Box Panel 30 x 40 x 20 cm buah 350,000
Box Panel 50 x 60 x 20 cm buah 750,000
Box panel 68 x 80 x 30 cm buah 1,200,000
Exhaust fan buah 500,000
Inbow dus buah 7,000
Isolasi buah 10,500
Kabel NYA 1 x 1.5 setara supreme; 1 roll @ 100 m m¹ 3,750
Kabel NYA 1 x 2.5 setara supreme; 1 roll @ 100 m m¹ 5,200
Kabel NYM 2 x 1.5 setara supreme; 1 roll @ 50 m m¹ 8,500
Kabel NYM 2 x 2,5 setara supreme; 1 roll @ 50 m m¹ 13,000
NO. JENIS BARANG / BAHAN / UPAH URAIAN SATUAN HARGA
T. MATERIAL LAIN-LAIN
Additive liter 30,000
Air liter 36
Alang - alang ikat 6,000
Aluminium foil 1 roll @ 1,20 m x 50 m roll 650,000
Aluminium Composite Panel (ACP) m2 425,000
Aspal curah kg 12,550
Batako (ukuran 40x20x10) buah 2,800
Batako (ukuran 40x20x12) buah 2,800
Batako (ukuran 40x20x15) buah 2,800
Batako (ukuran 40x20x20) buah 2,800
Bambu dia. 6 - 8 /600 cm Btg 35,000
Dinabolt dia 12mm (10-15cm) buah 13,500
Formica uk. 122 cm x 244 cm lembar 150,000
Formtie/penjaga jarak bekesting/spacer buah 10,000
Gebalan Rumput m2 15,000
Geotekstil m2 22,000
Glass Block buah 24,000
Hebel Block (ukuran 60x20x10 cm) buah 12,500
Hebel Block (ukuran 60x20x15 cm) buah 12,500
Hebel Block (ukuran 60x20x20 cm) buah 12,500
Ijuk m3 45,000
Jendela nako (rangka + kaca 5 mm) m2 325,000
Kalsiplank btg 47,000
Kapur m3 1,750,000
NO. JENIS BARANG / BAHAN / UPAH URAIAN SATUAN HARGA
Kapur Kg 6,000
Karung goni buah 10,000
Karung plastik buah 5,000
Lapisan galvanis kg 10,000
Lapisan coating primer membran bitumen pelapis anti bocor sistem bakar kg 42,000
Membran bitumen pelapis anti bocor sistem baakar 1 roll @ 1 m x 10 m, t. 3 mm roll 750,000
Nako per daun buah 10,500
Penampung / tangki air 900 ml bahan fiber buah 1,250,000
Penampung / tangki air 1200 ml bahan fiber buah 1,350,000
Penampung / tangki air 1100 ml bahan stainless buah 4,450,000
Pintu KM/WC bahan PVC bh 750,000
Pintu lipat (folding door) bahan plastik/PVC m2 275,000
Pipa HDPE 40/33 mm m¹ 12,000
Pipa screen pvc Ø 4" m¹ 115,000
Pipa tanah Ø 15 cm 1 btg @ 6 m btg 700,000
Pipa tanah Ø 20 cm 1 btg @ 6 m btg 1,075,000
Pipa tanah Ø 30 cm 1 btg @ 6 m btg 2,650,000
Plastic aerator buah 25,000
Plastik cor 1 roll @ 20m x 1,2m m2 3,250
Ramset/dina bolt buah 4,500
Rooster tanah uk. 10x20 buah 3,350
Rooster beton uk. 20x20 buah 7,700
Rooster keramik lukis uk. 20x20 buah 38,000
Sabun Kg 18,000
Seal tape buah 3,500
Sealant tube 40,000
Sealant kaca kg 85,000
Soda api kg 40,000
Sesek bambu (2x1,5m) 1 lembar @ 2 m x 3 m lembar 175,000
Shower bidet kloset / jet shower bh 210,000
Shower mandi set bh 798,000
Skrup fixer buah 1,650
Tali ijuk kg 35,000
Venetian blinds dan vertical blinds (tirai) m2 38,000
Wallpaper lebar 100 cm 1 roll @ 1 m x 15 m m 67,000
Wallpaper lebar 50cm 1 roll @ 0,5 m x 10 m m 48,000
Assesoris PVC m¹ 5,000
Pipa PVC tipe AW Ø 1/2" panjang 4 m batang 24,000
Pipa PVC tipe AW Ø 3/4" panjang 4 m batang 32,000
Pipa PVC tipe AW Ø 1" panjang 4 m batang 42,000
Pipa PVC tipe AW Ø 1 1/2" panjang 4 m batang 72,000
Pipa PVC tipe AW Ø 2" panjang 4 m batang 95,000
Pipa PVC tipe AW Ø 21/2" panjang 4 m batang 135,000
Pipa PVC tipe AW Ø 3" panjang 4 m batang 185,000
Pipa PVC tipe AW Ø 4" panjang 4 m batang 320,000
Pipa PVC tipe D Ø 1 1/4" panjang 4 m batang 40,000
Pipa PVC tipe D Ø 1 1/2" panjang 4 m batang 46,000
Pipa PVC tipe D Ø 2" panjang 4 m batang 59,000
Pipa PVC tipe D Ø 2 1/2" panjang 4 m batang 79,000
Pipa PVC tipe D Ø 3" panjang 4 m batang 105,000
Pipa PVC tipe D Ø 4" panjang 4 m batang 166,000
Pipa PVC tipe D Ø 5" panjang 4 m batang 256,000
Pipa PVC tipe D Ø 6" panjang 4 m batang 338,000
Pipa PVC tipe D Ø 8" panjang 4 m batang 594,000
NO. JENIS BARANG / BAHAN / UPAH URAIAN SATUAN HARGA
a b c d e
a b c d e
###
II. HARGA SATUAN PEKERJAAN TANAH
13.8 Pemasangan 1 bh pintu KM/WC aluminium warna lengkap kunci engsel setara dekson)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 145,000.00 7,250.00
Tukang L.02 OH 0.500 175,000.00 87,500.00
Kepala Tukang L.03 OH 0.050 180,000.00 9,000.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 104,305.00
B BAHAN
Pintu aluminium warna lengkap bh 1.000 3,500,000.00 3,500,000.00
Sealent tube 0.432 3,500.00 1,512.00
JUMLAH TENAGA BAHAN 3,501,512.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
I PEKERJAAN PERSIAPAN
1.1 Pekerjaan Pembersihan
Panjang = 34.00 m
Lebar = 23.50 m
Volume = 799.00 m2
24
Arah Y D22-100 mm
Jumlah Titik Tiang Pancang = 35.00 bh
Panjang Pile Cap = 1.80 m Tebal Selimut beton 75 mm
Tinggi Pile Cap = 0.50 m Tebal Selimut beton 75 mm
Jarak Tulangan = 0.10 m
Panjang Tulangan = 4.70
Panjang Total = 79.90
Berat D22 = 2.98 kg/m
Jumlah Tulangan = 17.00 bh
Berat Tulangan = 8,333.57 kg 8333.57 kg
Total Berat Tulangan = 16667.1 kg
- Bekisting Pilecap
Jumlah = 35.00 bh
Panjang = 1.80 m
Lebar = 1.80 m tebal papan bekisting 4 cm
Tinggi = 0.50 m
Luas = (2 x (p x l)) x t x jumlah
= 126.00
Total Bekisting Pile Cap 126.00 m2
LAPANGAN
Panjang Sloof = 5.50 m
Banyak Tulangan = 3.00 bh
Jumlah Sloof = 10.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 491.70 kg
Total = 819.50 kg
Sloof Memanjang
Ukuran 30/60 Panjang 5 M
TUMPUAN
Panjang Sloof = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Sloof = 20.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 596.00 kg
LAPANGAN
Panjang Sloof = 5.00 m
Banyak Tulangan = 3.00 bh
Jumlah Sloof = 20.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 894.00 kg
Total = 1,490.00 kg
Sengkang Ø13-215 5 M
Panjang Tulangan = 1.41 m
Banyak Sengkang = 24.00 bh
Jumlah Sloof = 20.00 bh
Berat Ø13 = 1.04 kg/m
Berat sengkang = 703.87 kg
Berat Total Tulangan = 2193.87 kg
Sloof Melintang
Ukuran 30/60 Panjang 2.25 M
TUMPUAN
Panjang Sloof = 2.25 m
Banyak Tulangan = 2.00 bh
Jumlah Sloof = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 187.74 kg
LAPANGAN
Panjang Sloof = 2.25 m
Banyak Tulangan = 5.00 bh
Jumlah Sloof = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 469.35 kg
Total = 657.09 kg
Sloof Melintang
Ukuran 30/60 Panjang 8 M
TUMPUAN
Panjang Sloof = 8.00 m
Banyak Tulangan = 2.00 bh
Jumlah Sloof = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 667.52 kg
LAPANGAN
Panjang Sloof = 8.00 m
Banyak Tulangan = 2.00 bh
Jumlah Sloof = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 667.52 kg
Total = 1,335.04 kg
Sengkang Ø13-215 8 M
Panjang Tulangan = 1.41 m
Banyak Sengkang = 32.00 bh
Jumlah Sloof = 14.00 bh
Berat Ø13 = 1.04 kg/m
Berat sengkang = 656.95 kg
Berat Total Tulangan = 1991.99 kg
Berat Total Tulangan Sloof 6073.41
Bekisting Sloof
Sloof 30/60 PANJANG 8 M
Panjang = 8.00 m
Tinggi = 0.60 m
Jumlah = 14.00 bh
Lebar = 0.30 m
Luas = nggi x 2) x Panjang x Jumlah
= 134.40
PANJANG 5,5 M
Panjang = 6.50 m
Tinggi = 0.60 m
Jumlah = 10.00 bh
Lebar = 0.30 m
Luas = nggi x 2) x Panjang x Jumlah
= 78.00
PANJANG 5 M
Panjang = 3.00 m
Tinggi = 0.60 m
Jumlah = 20.00 bh
Lebar = 0.30 m
Luas = nggi x 2) x Panjang x Jumlah
= 72.00
PANJANG 2.25 M
Panjang = 3.00 m
Tinggi = 0.60 m
Jumlah = 14.00 bh
Lebar = 0.30 m
Luas = nggi x 2) x Panjang x Jumlah
= 50.40
Total Bekisting Sloof 262.80 m2
Beton Sloof
Sloof 30/60 PANJANG 8 M
Panjang = 8.00 m
Tinggi = 0.60 m
Lebar = 0.30 m
Jumlah = 14.00 bh
Volume = 20.16 m3
PANJANG 5,5 M
Panjang = 5.50 m
Tinggi = 0.60 m
Lebar = 0.30 m
Jumlah = 10.00 bh
Volume = 9.90 m3
PANJANG 5 M
Panjang = 5.00 m
Tinggi = 0.60 m
Lebar = 0.30 m
605
Jumlah = 20.00 bh
Volume = 18.00 m3
PANJANG 2.25 M
Panjang = 2.25 m
Tinggi = 0.60 m
Lebar = 0.30 m
Jumlah = 14.00 bh
Volume = 5.67 m3
Panel 2
Jumlah Panel = 8.00 bh
Lx = 2.25 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 1.13 m
Panjang Total tulangan Lapangan x = 22.50 m
2
Jumlah Tulangan Lapangan y = 9.00 bh
Panjang Tulangan Lapangan y = 2.50 m
Panjang Total tulangan Lapangan y = 22.50 m
Jumlah Tulangan Tumpuan x = 20.00 bh
Panjang Tulangan Tumpuan x = 1.13 m
Panjang Total tulangan Tumpuan x = 22.50 m
Jumlah Tulangan Tumpuan y = 9.00 bh
Panjang Tulangan Tumpuan y = 2.50 m
Panjang Total tulangan Tumpuan y = 22.50 m
Panjang Total tulangan Pelat = 90.00 m
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 444.24 kg
Berat Total Tulangan Panel 2 = 444.24 kg
Panel 3
Jumlah Panel = 6.00 bh
Lx = 4.00 m
Ly = 5.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.23 m Tulangan Ø10-225 mm
Jarak Lapangan y = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan x = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan y = 0.23 m Tulangan Ø10-225 mm
Jumlah Tulangan Lapangan x = 25.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 50.00 m
Jumlah Tulangan Lapangan y = 18.00 bh
Panjang Tulangan Lapangan y = 2.75 m
3 Panjang Total tulangan Lapangan y
Jumlah Tulangan Tumpuan x
=
=
49.50
25.00
m
bh
Panjang Tulangan Tumpuan x = 2.00 m
Panjang Total tulangan Tumpuan x = 50.00 m
Jumlah Tulangan Tumpuan y = 18.00 bh
Panjang Tulangan Tumpuan y = 2.75 m
Panjang Total tulangan Tumpuan y = 49.50 m
Panjang Total tulangan Pelat = 199.00 m
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 736.70 kg
Berat Total Tulangan Panel 3 = 736.70 kg
Panel 4
Jumlah Panel = 16.00 bh
Lx = 4.00 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 40.00 m
Jumlah Tulangan Lapangan y = 16.00 bh
Panjang Tulangan Lapangan y = 2.50 m
4
607
Panel 5
Jumlah Panel = 4.00 bh
Lx = 1.80 m
Ly = 4.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 18.00 bh
Panjang Tulangan Lapangan x = 0.90 m
Panjang Total tulangan Lapangan x = 16.20 m
Sengkang Ø10-110
Panjang Tulangan = 0.96 m
Banyak Sengkang = 41.00 bh
Jumlah Kolom = 35.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 849.98 kg
Berat Total Pembesian Kolom 3616.10 kg
Kolom 40/40
Tinggi Kolom = 4.45 m
Tinggi Balok Lantai = 0.60 m
Tinggi Kolom Bersih = 3.85 m
Lebar = 0.40 m Tebal papan bekisting 4 cm
Panjang = 0.40 m
Jumlah = 35.00 bh
Luas = ng ) + ( 2 x Tinggi x Lebar )
= 215.60 m2
Total Bekisting Kolom Lt.Dasar 215.60 m2
608
Pelat Tangga
Panjang = 1.50 m
Lebar = 1.12 m
Tebal = 0.15 m
Jumlah = 2.00 bh
Jumlah Tulangan Bagi = 11.20 bh Tulangan Bagi Ø10-155
Jumlah Tulangan Utama = 13.64 bh Tulangan Utama D16-110
- Berat Ø10 = 0.62 kg/m
Berat Ø16 = 1.58 kg/m
Total 1 Lapis = 80.19 kg
Total 2 Lapis = 160.38 kg
Berat Tulangan Pelat Tangga = 160.38 kg
Bordes
Panjang = 2.25 m
Lebar = 2.34 m
Jumlah bordes = 3.00 bh
Tebal = 0.10 m
Jumlah Tulangan Utama = 14.62 bh Tulangan Utama D16-215
Jumlah Tulangan Bagi = 20.45 bh Tulangan Bagi Ø16-110
Total Berat = 82.61 kg
Berat Tulangan Bordes = 82.61 kg
Balok Bordes
Panjang = 4.40 m
Lebar Balok = 0.30 m
Tebal Balok = 0.12 m
Berat D16 = 1.58 kg/m
Jumlah Tulangan = 2.00 bh Tulangan 2D10
Total Berat = 13.90 kg
Berat Tulangan Balok Bordes = 13.90 kg
Bekisting Tangga
Anak Tangga
Lebar = 1.12 m
Optrede = 0.17 m
Jumlah = 20.00 bh
Luas = 3.81 m2 3.81 m2
609
Pelat Tangga
Cetakan Bawah
Lebar = 2.25 m
Panjang = 2.34 m
Jumlah = 2.00 bh
Luas = 10.53 m2 10.53 m2
Cetakan Samping
Panjang = 2.15 m
Tinggi = 0.17 m
Jumlah = 2.00 bh
Luas = 1.46 m2 1.46 m2
Bordes
Panjang = 2.25 m
Lebar = 2.34 m
Tinggi = 0.20 m
Luas = 5.27 m2 5.27 m2
Balok Bordes
Panjang = 4.40 m
Tebal = 0.10 m
Lebar = 0.30 m
Luas = 2.20 m2 2.20 m2
Beton Tangga
Anak Tangga
Lebar = 1.12 m
Optrede = 0.17 m
- Antrade = 0.30 m
Jumlah = 20.00 bh
Volume = (Lebar x Optrede x Antrede) 1.14 m3
Pelat Tangga
Lebar = 1.12 m
Tinggi = 0.20 m
Panjang = 2.15 m
Jumlah = 2.00 bh
Volume = ng x Tinggi x Lebar x Jumlah 0.96 m3
Bordes
Panjang = 2.25 m
Lebar = 2.34 m
Tinggi = 0.20 m
Jumlah = 3.00 bh
Volume = ng x Lebar x Tinggi x Jumlah 3.16 m3
Balok Bordes
Panjang = 4.40 m
Tebal = 0.15 m
Lebar = 0.30 m 0.66 m3
Volume = Panjang x Lebar x Tinggi
LANTAI 2
4.4 Pekerjaan Balok Lantai 2
Pekerjaan Pembesian Balok Induk
Balok Memanjang
Ukuran 30/60 Panjang 5.5 M
TUMPUAN
Panjang Balok = 5.50 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 458.92 kg
LAPANGAN
Panjang Balok = 5.50 m
Banyak Tulangan = 3.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 688.38 kg
Total = 1,147.30 kg
Balok Memanjang
Ukuran 30/60 Panjang 5 M
TUMPUAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 28.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 834.40 kg
LAPANGAN
Panjang Balok = 5.00 m
Banyak Tulangan = 3.00 bh
Jumlah Balok = 28.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 1,251.60 kg
Total = 2,086.00 kg
Balok Melintang
Ukuran 30/60 Panjang 8 M
TUMPUAN
Panjang Balok = 8.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 667.52 kg
LAPANGAN
Panjang Balok = 8.00 m
Banyak Tulangan = 5.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 1,668.80 kg
Total = 2,336.32 kg
Sengkang Ø10-250 8 M
Panjang Tulangan = 1.48 m
Banyak Sengkang = 34.00 bh
Jumlah Balok = 14.00 bh
Berat D10 = 0.62 kg/m
Berat sengkang = 434.66 kg
Berat Total Tulangan = 2770.98
Balok Melintang Ukuran 30/60 Panjang 2.25 M
TUMPUAN
Panjang Balok = 2.25 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 187.74 kg
LAPANGAN
Panjang Balok = 2.25 m
Banyak Tulangan = 5.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 469.35 kg
Total = 657.09 kg
LAPANGAN
Panjang Balok = 5.50 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 4.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 69.52 kg
Total = 139.04 kg
Balok Memanjang
Ukuran 250/350 Panjang 5 M
TUMPUAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 8.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 126.40 kg
LAPANGAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 8.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 126.40 kg
Total = 252.80 kg
Sengkang Ø10-150 5 M
Panjang Tulangan = 1.03 m
Banyak Sengkang = 5.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 25.42 kg
Berat Total Tulangan = 278.22 kg
Berat Total Pembesian Balok Anak Lantai 2 427.43 kg
= 16.50 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/60 PANJANG 8 M
Panjang = 8.00 m
Jumlah balok = 14.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.50 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 16.80 m²
Total Beton Balok Induk = 16.80 m²
612
Beton Balok
Beton Balok Induk
Balok Induk 30/55 PANJANG 5,5 M
Panjang = 5.50 m
Jumlah balok = 28.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.50 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 23.10 m²
Total Beton Balok Induk = 23.10 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/60 PANJANG 5 M
Panjang = 5.00 m
Jumlah balok = 10.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.45 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 6.75 m²
Total Beton Balok Induk = 6.75 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/60 PANJANG 5 M
Panjang = 2.25 m
Jumlah balok = 14.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.50 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 4.73 m²
Total Beton Balok Induk = 4.73 m²
PANJANG 5 M
Panjang = 5.00 m
Jumlah balok = 8.00 bh
Lebar = 0.28 m Tebal papan bekisting 4 cm
Tinggi = 0.25 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 2.75 m² 2.75 m²
1
Jumlah Tulangan Lapangan y = 15.00 bh
Panjang Tulangan Lapangan y = 2.75 m
Panjang Total tulangan Lapangan y = 41.25 m
Jumlah Tulangan Tumpuan x = 15.00 bh
Panjang Tulangan Tumpuan x = 1.13 m
Panjang Total tulangan Tumpuan x = 16.88 m
Jumlah Tulangan Tumpuan y = 15.00 bh
Panjang Tulangan Tumpuan y = 2.75 m
Panjang Total tulangan Tumpuan y = 41.25 m
Panjang Total tulangan Pelat = 141.00 m
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 347.99 kg
Berat Total Tulangan Panel 1 = 347.99 kg
- Panel 2
Jumlah Panel = 8.00 bh
Lx = 2.25 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 1.13 m
Panel 3
Jumlah Panel = 6.00 bh
Lx = 4.00 m
- Ly = 5.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.23 m Tulangan Ø10-225 mm
Jarak Lapangan y = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan x = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan y = 0.23 m Tulangan Ø10-225 mm
Jumlah Tulangan Lapangan x = 25.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 50.00 m
Jumlah Tulangan Lapangan y = 18.00 bh
Panel 4
Jumlah Panel = 16.00 bh
Lx = 4.00 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 40.00 m
Jumlah Tulangan Lapangan y = 16.00 bh
Panjang Tulangan Lapangan y = 2.50 m
Panjang Total tulangan Lapangan y = 40.00 m
Jumlah Tulangan Tumpuan x = 20.00 bh
4
Panjang Tulangan Tumpuan x = 2.00 m
Panjang Total tulangan Tumpuan x = 40.00 m
Jumlah Tulangan Tumpuan y = 16.00 bh
Panjang Tulangan Tumpuan y = 2.50 m
Panjang Total tulangan Tumpuan y = 40.00 m
Panjang Total tulangan Pelat = 160.00 m
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 1,579.52 kg
Berat Total Tulangan Panel 4 = 1579.52 kg
Panel 5
Jumlah Panel = 4.00 bh
Lx = 1.80 m
Ly = 4.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 18.00 bh
Panjang Tulangan Lapangan x = 0.90 m
Panjang Total tulangan Lapangan x = 16.20 m
Jumlah Tulangan Lapangan y = 8.00 bh
Luas 635.50
Volume 95.33
Total Beton Pelat Lantai 2 95.33 m
Sengkang Ø10-150
Panjang Tulangan = 0.93 m
Banyak Sengkang = 40.00 bh
Jumlah Kolom = 35.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 803.33 kg
Pelat Tangga
Panjang = 1.50 m
Lebar = 1.12 m
Tebal = 0.15 m
Jumlah = 2.00 bh
Jumlah Tulangan Bagi = 11.20 bh Tulangan Bagi Ø10-155
Jumlah Tulangan Utama = 13.64 bh Tulangan Utama D16-110
- Berat Ø10 = 0.62 kg/m
Berat Ø16 = 1.58 kg/m
Total 1 Lapis = 80.19 kg
Total 2 Lapis = 160.38 kg
Berat Tulangan Pelat Tangga = 160.38 kg
Bordes
Panjang = 2.25 m
Lebar = 2.34 m
Jumlah bordes = 3.00 bh
615
Tebal = 0.10 m
Jumlah Tulangan Utama = 14.62 bh Tulangan Utama D16-215
Jumlah Tulangan Bagi = 20.45 bh Tulangan Bagi Ø16-110
Total Berat = 82.61 kg
Berat Tulangan Bordes = 82.61 kg
Balok Bordes
Panjang = 4.40 m
Lebar Balok = 0.30 m
Tebal Balok = 0.12 m
Berat D16 = 1.58 kg/m
Jumlah Tulangan = 2.00 bh Tulangan 2D10
Total Berat = 13.90 kg
Berat Tulangan Balok Bordes = 13.90 kg
Bekisting Tangga
Anak Tangga
Lebar = 1.12 m
Optrede = 0.17 m
Jumlah = 20.00 bh
Luas = 3.81 m2 3.81 m2
Pelat Tangga
Cetakan Bawah
Lebar = 2.25 m
Panjang = 2.34 m
Jumlah = 2.00 bh
Luas = 10.53 m2 10.53 m2
Cetakan Samping
Panjang = 2.15 m
Tinggi = 0.17 m
Jumlah = 2.00 bh
Luas = 1.46 m2 1.46 m2
Bordes
Panjang = 2.25 m
Lebar = 2.34 m
Tinggi = 0.20 m
Luas = 5.27 m2 5.27 m2
Balok Bordes
Panjang = 4.40 m
Tebal = 0.10 m
Lebar = 0.30 m
Luas = 2.20 m2 2.20 m2
Beton Tangga
Anak Tangga
Lebar = 1.12 m
Optrede = 0.17 m
- Antrade = 0.30 m
Jumlah = 20.00 bh
Volume = (Lebar x Optrede x Antrede) 1.14 m3
Pelat Tangga
Lebar = 1.12 m
Tinggi = 0.20 m
Panjang = 2.15 m
Jumlah = 2.00 bh
Volume = ng x Tinggi x Lebar x Jumlah 0.96 m3
Bordes
Panjang = 2.25 m
Lebar = 2.34 m
Tinggi = 0.20 m
Jumlah = 3.00 bh
Volume = ng x Lebar x Tinggi x Jumlah 3.16 m3
Balok Bordes
Panjang = 4.40 m
Tebal = 0.15 m
Lebar = 0.30 m 0.66 m3
Volume = Panjang x Lebar x Tinggi
LANTAI 3
4.8 Pekerjaan Balok Lantai 3
Pekerjaan Pembesian Balok Induk
Balok Memanjang
Ukuran 30/60 Panjang 5.5 M
TUMPUAN
Panjang Balok = 5.50 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 458.92 kg
LAPANGAN
Panjang Balok = 5.50 m
Banyak Tulangan = 3.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 688.38 kg
Total = 1,147.30 kg
Balok Memanjang
Ukuran 30/60 Panjang 5 M
TUMPUAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 28.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 834.40 kg
LAPANGAN
Panjang Balok = 5.00 m
Banyak Tulangan = 3.00 bh
Jumlah Balok = 28.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 1,251.60 kg
Total = 2,086.00 kg
LAPANGAN
Panjang Balok = 8.00 m
Banyak Tulangan = 5.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 1,668.80 kg
Total = 2,336.32 kg
Sengkang Ø10-250 8 M
Panjang Tulangan = 1.48 m
Banyak Sengkang = 34.00 bh
Jumlah Balok = 14.00 bh
Berat D10 = 0.62 kg/m
Berat sengkang = 434.66 kg
Berat Total Tulangan = 2770.98
Balok Melintang Ukuran 30/60 Panjang 2.25 M
TUMPUAN
Panjang Balok = 2.25 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 187.74 kg
LAPANGAN
Panjang Balok = 2.25 m
Banyak Tulangan = 5.00 bh
Jumlah Balok = 14.00 bh
Berat D22 = 2.98 kg/m
Berat Total = 469.35 kg
Total = 657.09 kg
TUMPUAN
Panjang Balok = 5.50 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 4.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 69.52 kg
LAPANGAN
Panjang Balok = 5.50 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 4.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 69.52 kg
Total = 139.04 kg
Balok Memanjang
Ukuran 250/350 Panjang 5 M
TUMPUAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 8.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 126.40 kg
LAPANGAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 8.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 126.40 kg
Total = 252.80 kg
Sengkang Ø10-150 5 M
Panjang Tulangan = 1.03 m
Banyak Sengkang = 5.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 25.42 kg
Berat Total Tulangan = 278.22 kg
Berat Total Pembesian Balok Anak Lantai 2 427.43 kg
Panjang = 5.50 m
Jumlah balok = 4.00 bh
Lebar = 0.25 m Tebal papan bekisting 4 cm
Tinggi = 0.25 m dikurangi tebal plat 10 cm
Luas =,25 m)+ 2 x (5,5 m x 0,25 m))
= 16.50 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/60 PANJANG 8 M
Panjang = 8.00 m
Jumlah balok = 14.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.50 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 16.80 m²
Total Beton Balok Induk = 16.80 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/55 PANJANG 5,5 M
Panjang = 5.50 m
Jumlah balok = 28.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.50 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 23.10 m²
Total Beton Balok Induk = 23.10 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/60 PANJANG 5 M
Panjang = 5.00 m
Jumlah balok = 10.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.45 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 6.75 m²
Total Beton Balok Induk = 6.75 m²
Beton Balok
Beton Balok Induk
Balok Induk 30/60 PANJANG 5 M
Panjang = 2.25 m
Jumlah balok = 14.00 bh
Lebar = 0.30 m Tebal papan bekisting 4 cm
Tinggi = 0.50 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 4.73 m²
Total Beton Balok Induk = 4.73 m²
PANJANG 5 M
Panjang = 5.00 m
Jumlah balok = 8.00 bh
Lebar = 0.28 m Tebal papan bekisting 4 cm
Tinggi = 0.25 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 2.75 m² 2.75 m²
1
Jumlah Tulangan Lapangan y = 15.00 bh
Panjang Tulangan Lapangan y = 2.75 m
Panjang Total tulangan Lapangan y = 41.25 m
Jumlah Tulangan Tumpuan x = 15.00 bh
Panjang Tulangan Tumpuan x = 1.13 m
Panjang Total tulangan Tumpuan x = 16.88 m
Jumlah Tulangan Tumpuan y = 15.00 bh
Panjang Tulangan Tumpuan y = 2.75 m
Panjang Total tulangan Tumpuan y = 41.25 m
Panjang Total tulangan Pelat = 141.00 m
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 347.99 kg
Berat Total Tulangan Panel 1 = 347.99 kg
- Panel 2
Jumlah Panel = 8.00 bh
Lx = 2.25 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 1.13 m
Panel 3
Jumlah Panel = 6.00 bh
Lx = 4.00 m
- Ly = 5.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.23 m Tulangan Ø10-225 mm
Jarak Lapangan y = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan x = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan y = 0.23 m Tulangan Ø10-225 mm
Jumlah Tulangan Lapangan x = 25.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 50.00 m
Jumlah Tulangan Lapangan y = 18.00 bh
Panel 4
Jumlah Panel = 16.00 bh
Lx = 4.00 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 40.00 m
Jumlah Tulangan Lapangan y = 16.00 bh
Panjang Tulangan Lapangan y = 2.50 m
Panel 5
Jumlah Panel = 4.00 bh
Lx = 1.80 m
Ly = 4.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 18.00 bh
Panjang Tulangan Lapangan x = 0.90 m
Panjang Total tulangan Lapangan x = 16.20 m
Jumlah Tulangan Lapangan y = 8.00 bh
Sengkang Ø10-150
Panjang Tulangan = 0.93 m
300
Beton Kolom
Beton Kolom 40/40 Panjang = 0.40 m
Lebar = 0.40 m
Tinggi = 3.80 m
Jumlah = 35.00 bh
Volume = ( Panjang x Lebar x Tinggi )
Volume = 21.28 m3
Lantai Atap
621
LAPANGAN
Panjang Balok = 5.50 m
Banyak Tulangan = 4.00 bh
Jumlah Balok = 14.00 bh
Berat D19 = 2.22 kg/m
Berat Total = 683.76 kg
Total = 1,196.58 kg
LAPANGAN
Panjang Balok = 5.00 m
Banyak Tulangan = 4.00 bh
Jumlah Balok = 28.00 bh
Berat D19 = 2.22 kg/m
Berat Total = 1,243.20 kg
Total = 2,175.60 kg
Sengkang Ø10-250 5 M
Panjang Tulangan = 0.98 m
Banyak Sengkang = 31.00 bh
Jumlah Balok = 28.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 524.84 kg
Berat Total Tulangan = 2700.4 m2
Balok Melintang
Ukuran 30/55 Panjang 8 M
TUMPUAN
Panjang Balok = 8.00 m
Banyak Tulangan = 4.00 bh
Jumlah Balok = 14.00 bh
Berat D19 = 2.22 kg/m
Berat Total = 994.56 kg
LAPANGAN
Panjang Balok = 8.00 m
Banyak Tulangan = 6.00 bh
Jumlah Balok = 14.00 bh
Berat D19 = 2.22 kg/m
Berat Total = 1,491.84 kg
Total = 2,486.40 kg
Sengkang Ø10-250 8 M
Panjang Tulangan = 0.98 m
Banyak Sengkang = 49.00 bh
Jumlah Balok = 14.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 414.80 kg
Berat Total Tulangan = 2901.20
Balok Melintang
Ukuran 30/55 Panjang 2.25 M
TUMPUAN
Panjang Balok = 2.25 m
Banyak Tulangan = 4.00 bh
Jumlah Balok = 14.00 bh
Berat D19 = 2.98 kg/m
Berat Total = 375.48 kg
LAPANGAN
Panjang Balok = 2.25 m
Banyak Tulangan = 6.00 bh
Jumlah Balok = 14.00 bh
Berat D19 = 2.22 kg/m
Berat Total = 419.58 kg
Total = 795.06 kg
LAPANGAN
Panjang Balok = 5.50 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 4.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 69.52 kg
Total = 139.04 kg
622
Balok Memanjang
623
LAPANGAN
Panjang Balok = 5.00 m
Banyak Tulangan = 2.00 bh
Jumlah Balok = 8.00 bh
Berat D16 = 1.58 kg/m
Berat Total = 126.40 kg
Total = 252.80 kg
Sengkang Ø10-150 5 M
Panjang Tulangan = 1.03 m
Banyak Sengkang = 5.00 bh
Berat Ø10 = 0.62 kg/m
Berat sengkang = 25.42 kg
Berat Total Tulangan = 278.22 kg
Berat Total Pembesian Balok Anak Lantai Atap 427.43 kg
PANJANG 5 M
Panjang = 5.00 m
Jumlah balok = 8.00 bh
Lebar = 0.25 m Tebal papan bekisting 4 cm
Tinggi = 0.25 m dikurangi tebal plat 10 cm
Luas = ( Panjang x Lebar x Tinggi )
= 2.50 m²
Total Beton Balok Anak = 3.87 m²
625
Panel 2
Jumlah Panel = 8.00 bh
Lx = 2.25 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 1.13 m
Panjang Total tulangan Lapangan x = 22.50 m
Jumlah Tulangan Lapangan y = 9.00 bh
2 Panjang Tulangan Lapangan y
Panjang Total tulangan Lapangan y
=
=
2.50
22.50
m
m
Jumlah Tulangan Tumpuan x = 20.00 bh
Panjang Tulangan Tumpuan x = 1.13 m
Panjang Total tulangan Tumpuan x = 22.50 m
Jumlah Tulangan Tumpuan y = 9.00 bh
Panjang Tulangan Tumpuan y = 2.50 m
Panjang Total tulangan Tumpuan y = 22.50 m
Panjang Total tulangan Pelat = 90.00 m
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 444.24 kg
Berat Total Tulangan Panel 2 = 444.24 kg
Panel 3
Jumlah Panel = 6.00 bh
Lx = 4.00 m
Ly = 5.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.23 m Tulangan Ø10-225 mm
Jarak Lapangan y = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan x = 0.23 m Tulangan Ø10-225 mm
Jarak Tumpuan y = 0.23 m Tulangan Ø10-225 mm
Jumlah Tulangan Lapangan x = 25.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 50.00 m
Jumlah Tulangan Lapangan y = 18.00 bh
Panel 4
Jumlah Panel = 16.00 bh
Lx = 4.00 m
Ly = 5.00 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 20.00 bh
Panjang Tulangan Lapangan x = 2.00 m
Panjang Total tulangan Lapangan x = 40.00 m
Jumlah Tulangan Lapangan y = 16.00 bh
Panjang Tulangan Lapangan y = 2.50 m
Panjang Total tulangan Lapangan y = 40.00 m
Jumlah Tulangan Tumpuan x = 20.00 bh
Panjang Tulangan Tumpuan x = 2.00 m
Panjang Total tulangan Tumpuan x = 40.00 m
Jumlah Tulangan Tumpuan y = 16.00 bh
Panjang Tulangan Tumpuan y = 2.50 m
4
Berat Tulangan Ø10 = 0.62 kg/m
Berat Total Tulangan = 1,579.52 kg
Berat Total Tulangan Panel 4 = 1579.52 kg
Panel 5
Jumlah Panel = 4.00 bh
Lx = 1.80 m
Ly = 4.50 m
Diameter Tulangan = 0.01 m
Jarak Lapangan x = 0.25 m Tulangan Ø10-250 mm
Jarak Lapangan y = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan x = 0.25 m Tulangan Ø10-250 mm
Jarak Tumpuan y = 0.25 m Tulangan Ø10-250 mm
Jumlah Tulangan Lapangan x = 18.00 bh
Panjang Tulangan Lapangan x = 0.90 m
Panjang Total tulangan Lapangan x = 16.20 m
Beton Plat
Tebal Pelat 0.15 m
Luas 635.50
Volume 95.33
Total Beton Pelat Lantai 2 95.33 kg
V PEKERJAAN ARSITEKTUR
5.1 PEKERJAAN DINDING
- LANTAI 1
Pasangan dinding bata Panjang = 495.50 m
Tinggi 3.75 m
Luasan 1,858.13 m2 1858.13 m2
- LANTAI 2
Pasangan dinding bata Panjang = 495.50 m
Tinggi 3.60 m
Luasan 1,783.80 m2 1783.80 m2
- LANTAI 3
Pasangan dinding bata Panjang = 495.50 m
Tinggi 3.60 m
Luasan 1,783.80 m2 1783.80 m2
2 Lantai 2
- Pekerjaan Pintu P1 Jumlah Pintu = 10.00 bh
Lebar = 0.90 m
Tinggi = 2.00 m
Luas = 18.00 m2 18.00 m2
- Pekerjaan Pintu P2 Jumlah Pintu = 3.00 bh
Lebar = 0.80 m
Tinggi = 2.00 m
Luas = 4.80 m2 4.80 m2
- Pintu KM/WC/P3 Jumlah Pintu = 5.00 bh 5.00 bh
3 Lantai 3
- Pekerjaan Pintu P1 Jumlah Pintu = 2.00 bh
Lebar = 0.90 m
Tinggi = 2.00 m
Luas = 3.60 m2 3.60 m2
- Pekerjaan Pintu P2 Jumlah Pintu = 2.00 bh
Lebar = 0.80 m
Tinggi = 2.00 m
Luas = 3.20 m2 3.20 m2
- Pintu KM/WC/P3 Jumlah Pintu = 4.00 bh 4.00 bh
Tebal = 0.02 m
Volume = 36.83 m3
2 Lantai 2
Plafond gypsum 9 mm = 607.11 m2
3 Lantai 3
Plafond gypsum 9 mm = 610.03 m2
1 LANTAI 2
Pekerjaan Cat Tembok Panjang = 495.50 m
Tinggi = 3.70 m
Luas total = 3,666.70 m2 3666.70 m2
1 LANTAI 3
Pekerjaan Cat Tembok Panjang = 495.50 m
Tinggi = 3.70 m
Luas total = 3,666.70 m2 3666.70 m2
Lantai 2
- Pasangan Kloset Duduk + Acc = 22.00 bh
- Pasangan Washtafel + Acc = 22.00 bh
- Pasangan Jetwasher = 22.00 bh
- Pasangan Floor Drain Stainless Steel = 22.00 bh
- Pasangan Kran Air = 22.00 bh
- Pasangan Kitchen Zink = 1.00 bh
- Pasangan Pipa PVC 1/2" = 4,782.00 m
- Pasangan Pipa PVC 3/4" = 3,278.00 m
- Pasangan Pipa PVC 1 1/2" = 853.00 m
- Pasangan Pipa PVC 2" = 3,246.00 m
- Pasangan Pipa PVC 4" = 2,353.00 m
- Pompa air = 2.00 bh
- Shower = 22.00 bh
- Water profing lantai KM/Wc = 69.16 m²
Lantai 3
- Pasangan Kloset Duduk + Acc = 19.00 bh
- Pasangan Washtafel + Acc = 19.00 bh
- Pasangan Jetwasher = 19.00 bh
- Pasangan Floor Drain Stainless Steel = 19.00 bh
- Pasangan Kran Air = 19.00 bh
- Pasangan Pipa PVC 1/2" = 4,328.00 m
- Pasangan Pipa PVC 3/4" = 1,532.00 m
- Pasangan Pipa PVC 1 1/2" = 765.00 m
- Pasangan Pipa PVC 2" = 2,841.00 m
- Pasangan Pipa PVC 4" = 1,945.00 m
- Pompa air = 2.00 bh
- Shower = 19.00 bh
- Water profing lantai KM/Wc = 75.16 m²
2 Lantai 2
Instalasi titik lampu = 177.00 bh 177.00 bh
Instalasi Stop Kontak = 154.00 bh 154.00 bh
Instalasi Stop Exchaust Fan = 8.00 bh 8.00 bh
Instalasi Stop Kontak AC = 48.00 bh 48.00 bh
Lampu TL RM 2 x 18 = 192.00 bh 192.00 bh
Lampu TL 1 x 36 = 96.00 bh 96.00 bh
Down light PLC 18 W = 118.00 bh 118.00 bh
Down light PLC 8 W = 59.00 bh 59.00 bh
Exchaust Fan = 8.00 bh 8.00 bh
Saklar Tunggal = 28.00 bh 28.00 bh
Saklar Ganda = 66.00 bh 66.00 bh
Stop Kontak = 132.00 bh 132.00 bh
Stop Kontak AC = 48.00 bh 48.00 bh
Box Panel 2 = 2.00 bh 2.00 bh
3 Lantai 3
Instalasi titik lampu = 171.00 bh 171.00 bh
Instalasi Stop Kontak = 143.00 bh 143.00 bh
Instalasi Stop Exchaust Fan = 4.00 bh 4.00 bh
Instalasi Stop Kontak AC = 41.00 bh 41.00 bh
Lampu TL RM 2 x 18 = 172.00 bh 172.00 bh
Lampu TL 1 x 36 = 86.00 bh 86.00 bh
Down light PLC 18 W = 123.00 bh 123.00 bh
Down light PLC 8 W = 43.00 bh 43.00 bh
Exchaust Fan = 4.00 bh 4.00 bh
Saklar Tunggal = 27.00 bh 27.00 bh
Saklar Ganda = 34.00 bh 34.00 bh
Stop Kontak = 114.00 bh 114.00 bh
Stop Kontak AC = 41.00 bh 41.00 bh
Box Panel 2 = 2.00 bh 2.00 bh
PEKERJAAN : K3
TAHUN 2021
LOKASI Pembangunan Gedung Rawat Inap RSUD PALI
I PEKERJAAN K3
1 Penyiapan RK3K terdiri atas :
1 Pembuatan Manual, Prosedur, intruksi kerja dan 1 1 Set Rp. 2,000,000.00 Rp. 2,000,000.00
2 Pembuatan kartu identitas Pekerja (KIP) 75 1 Org Rp. 7,000.00 Rp. 525,000.00
Sosialisasi dan
2 promosi K3 terdiri atas :
1 Perilaku Berbasis Keselamatan (Budaya K3) 75 1 Org Rp. 7,500.00 Rp. 562,500.00
2 P3K 3 1 Org Rp. 1,750,000.00 Rp. 5,250,000.00
3 Simulasi K3 75 1 Org Rp. 7,500.00 Rp. 562,500.00
4 Spanduk (banner) 4 1 Lb Rp. 150,000.00 Rp. 600,000.00
5 Poster; 8 1 Lb Rp. 50,000.00 Rp. 400,000.00
6 Papan Informasi K3. 5 1 Bh Rp. 500,000.00 Rp. 2,500,000.00
3 Alat Pelindung Diri terdiri atas:
1 Topi Pelindung (Safety Helmet) 75 1 Bh Rp. 75,000.00 Rp. 5,625,000.00 staf & tamu
2 Pelindung Mata (Goggles, Spectacles); 40 1 Psg Rp. 25,000.00 Rp. 1,000,000.00
3 Tameng Muka (Face Shield); 20 1 Bh Rp. 75,000.00 Rp. 1,500,000.00
4 Pelindung Pernafasan Dan Mulut (Masker); 150 1 Bh Rp. 5,000.00 Rp. 750,000.00
5 Sarung Tangan (Safety Gloves); 75 1 Psg Rp. 5,000.00 Rp. 375,000.00
6 Sepatu Keselamatan (Safety Shoes); untuk Staf 10 1 Psg Rp. 650,000.00 Rp. 6,500,000.00
7 Sepatu Keselamatan (Rubber Safety Shoes_and toe cap) 45 1 Psg Rp. 145,000.00 Rp. 6,525,000.00
8 Penunjang Seluruh Tubuh (Full Body Harness); 15 1 Bh Rp. 750,000.00 Rp. 11,250,000.000
9 Rompi Keselamatan (Safety Vest); 50 1 Bh Rp. 65,000.00 Rp. 3,250,000.00
10 Celemek (Apron/Coveralls); 20 1 Bh Rp. 40,000.00 Rp. 800,000.00
4 Asuransi Dan Perijinan terdiri atas :
Surat Ijin Pengesahan Panitia Pembina Keselamatan Dan Kesehatan
1 1 1 Ls Rp. 500,000.00 Rp. 500,000.00
Kerja (P2K3);
5 Rambu- Rambu terdiri atas :
1 Rambu Petunjuk; 4 1 Bh Rp. 75,000.00 Rp. 300,000.00 sesuai kebutuhan
2 Rambu Peringatan; 4 1 Bh Rp. 75,000.00 Rp. 300,000.00 sesuai kebutuhan
3 Rambu Kewajiban; 4 1 Bh Rp. 75,000.00 Rp. 300,000.00 sesuai kebutuhan
4 Rambu Informasi; 10 1 Bh Rp. 75,000.00 Rp. 750,000.00 sesuai kebutuhan
6 Lain- Lain Terkait Pengendalian Risiko K3
1 Alat Pemadam Api Ringan (APAR); 10Kg 3 1 Bh Rp. 550,000.00 Rp. 1,650,000.00
2 Bendera K3; 1 1 Bh Rp. 50,000.00 Rp. 50,000.00
3 Pelaporan dan Penyelidikan Insiden. 1 1 Ls Rp. 500,000.00 Rp. 500,000.00
Kuantitas
No Uraian Pekerjaan Satuan Harga satuan (Rp) Jumlah harga (Rp)
Pekerjaan
I PEKERJAAN PERSIAPAN
1.1 Pekerjaan Pembersihan 799.00 m² 27,312.50 21,822,687.50
1.2 Pemasangan Bouwplank 111.00 m² 95,133.75 10,559,846.25
1.3 Pemagaran Proyek 119.00 m 521,197.25 62,022,472.75
1.4 Pembuatan Kantor Sementara 35.00 m² 2,010,372.50 70,363,037.50
1.5 Pembuatan Gudang Alat dan Bahan 35.00 m² 1,515,872.50 53,055,537.50
1.6 Mobilisasi Alat Pancang 1.00 Ls 40,000,000.00 40,000,000.00
Total Harga Pekerjaan Persiapan 257,823,581.50
LANTAI 2
4.4 Pekerjaan Balok
- Pekerjaan Pembesian Balok 8,047.62 Kg 26,093.50 209,990,591.26
- Pekerjaan Bekisting Balok 515.15 m² 454,474 234,122,409.89
- Pekerjaan Beton Balok ( f'c 30 Mpa) 54.13 m³ 1,899,337.02 102,801,616.13
4.5 Pekerjaan Pelat
- Pekerjaan Pembesian Pelat Lantai 3,277.26 Kg 26,093.50 85,515,110.75
- Pekerjaan Bekisting Pelat 515.15 m² 514,849 265,224,591.14
- Pekerjaan Beton Pelat Lantai (f'c 30 Mpa) 95.33 m³ 1,899,337.02 181,054,301.29
4.6 Pekerjaan Kolom
- Pekerjaan Pembesian Kolom 3,538.37 Kg 26,093.50 92,328,561.97
- Pekerjaan Bekisting Kolom 212.80 m² 445,849 94,876,720.40
- Pekerjaan Beton Kolom (f'c 30 Mpa) 21.28 m³ 1,899,337.02 40,417,891.75
4.7 Pekerjaan Tangga
- Pekerjaan Pembesian Tangga 398.78 Kg 26,093.50 10,405,549.82
- Pekerjaan Bekisting Tangga 23.27 m² 431,417 10,036,910.69
- Pekerjaan Beton Tangga (f'c 30 Mpa) 5.92 m³ 1,899,337.02 11,252,812.10
LANTAI 3
4.8 Pekerjaan Balok
- Pekerjaan Pembesian Balok 8,047.62 Kg 26,093.50 209,990,591.26
- Pekerjaan Bekisting Balok 515.15 m² 454,474 234,122,409.89
- Pekerjaan Beton Balok ( f'c 30 Mpa) 54.13 m³ 1,899,337.02 102,801,616.13
4.9 Pekerjaan Pelat
- Pekerjaan Pembesian Pelat Lantai 3,277.26 Kg 26,093.50 85,515,110.75
- Pekerjaan Bekisting Pelat 515.15 m² 514,849 265,224,591.14
- Pekerjaan Beton Pelat Lantai (f'c 30 Mpa) 95.33 m³ 1,899,337.02 181,054,301.29
4.10 Pekerjaan Kolom
- Pekerjaan Pembesian Kolom 3,538.37 Kg 26,093.50 92,328,561.97
- Pekerjaan Bekisting Kolom 212.80 m² 445,849 94,876,720.40
- Pekerjaan Beton Kolom (f'c 30 Mpa) 21.28 m³ 1,899,337.02 40,417,891.75
631
LANTAI ATAP
4.11 Pekerjaan Ring Balok
- Pekerjaan Pembesian Ring Balok 8,596.35 Kg 26,093.50 224,308,767.92
- Pekerjaan Bekisting Balok 479.10 m² 454,474 217,738,613
- Pekerjaan Beton Balok ( f'c 30 Mpa) 52.54 m³ 1,899,337.02 99,795,915.30
4.12 Pekerjaan Pelat Dak
- Pekerjaan Pembesian Pelat Lantai 3,277.26 Kg 26,093.50 85,515,110.75
- Pekerjaan Bekisting Pelat Lantai 479.10 m³ 514,849.25 246,664,275.68
- Pekerjaan Beton Pelat Lantai (f'c 30 Mpa) 95.33 m³ 1,899,337.02 181,054,301.29
V PEKERJAAN ARSITEKTUR
5.1 PEKERJAAN DINDING
- LANTAI 1
Pekerjaan Pasangan Dinding Bata Ad. 1:4 1,858.13 m² 342,757.50 636,886,279.69
- LANTAI 2
Pekerjaan Pasangan Dinding Bata Ad. 1:4 1,783.80 m² 342,757.50 611,410,828.50
- LANTAI 3
Pekerjaan Pasangan Dinding Bata Ad. 1:4 1,783.80 m² 342,757.50 611,410,828.50
Total Harga Pekerjaan Dinding 1,859,707,936.69
- LANTAI 1
Pekerjaan Acian 3,716.25 m² 64,026.25 237,937,551.56
- LANTAI 2
Pekerjaan Acian 3,567.60 m² 64,026.25 228,420,049.50
- LANTAI 3
Pekerjaan Acian 3,567.60 m² 64,026.25 228,420,049.50
Total Harga Pekerjaan Acian Dinding 694,777,650.56
5.3 PEKERJAAN KUSEN & PINTU
- LANTAI DASAR
Pekerjaan Pintu P1 18.00 m² 1,097,335.75 19,752,043.50
Pekerjaan Pintu P2 4.80 m² 1,097,335.75 5,267,211.60
Pintu KM/WC/P3 6.00 m² 4,146,689.55 24,880,137.30
Total Jumlah Harga 49,899,392.40
- LANTAI 2
Pekerjaan Pintu P1 18.00 m² 1,097,335.75 19,752,043.50
Pekerjaan Pintu P2 4.80 m² 1,097,335.75 5,267,211.60
Pintu KM/WC/P3 5.00 m² 4,146,689.55 20,733,447.75
Total Jumlah Harga 45,752,702.85
- LANTAI 3
Pekerjaan Pintu P1 3.60 m² 1,097,335.75 3,950,408.70
Pekerjaan Pintu P2 3.20 m² 1,097,335.75 3,511,474.40
Pintu KM/WC/P3 4.00 m² 4,146,689.55 16,586,758.20
Total Jumlah Harga 24,048,641.30
Total Harga Pekerjaan Kusen Pintu & Jendela 119,700,736.55
LANTAI 2
1 Kunci Tanam Stainless Steel 18.00 Bh 803,706.25 14,466,712.50
2 Engsel Pintu 36.00 Bh 91,545.75 3,295,647.00
Total Jumlah Harga 17,762,359.50
LANTAI 3
1 Kunci Tanam Stainless Steel 8.00 Bh 803,706.25 6,429,650.00
2 Engsel Pintu 16.00 Bh 91,545.75 1,464,732.00
Total Jumlah Harga 7,894,382.00
Total Harga Pekerjaan Kunci 44,405,898.75
LANTAI 2
1 Pekerjaan Pasangan Keramik 40 x 40 544.76 m² 325,476.45 177,304,923.52
2 Pekerjaan Pasangan Keramik 20 x 20 69.16 m' 332,051.00 22,964,647.16
Total Jumlah Harga 200,269,570.68
632
LANTAI 3
1 Pekerjaan Pasangan Keramik 40 x 40 538.76 m² 325,476.45 175,352,064.82
2 Pekerjaan Pasangan Keramik 20 x 20 75.16 m' 332,051.00 24,956,953.16
Total Jumlah Harga 200,309,017.98
- LANTAI 2
Pemasangan 1 M2 Langit - Langit gypsum board + rangka besi hollow 607.11 m2 67,188.75 40,791,029.20
Total Jumlah Harga 40,791,029.20
- LANTAI 3
Pemasangan 1 M2 Langit - Langit gypsum board + rangka besi hollow 610.03 m2 67,188.75 40,986,817.22
Total Jumlah Harga 40,986,817.22
Total Harga Pekerjaan Plafond 122,568,875.62
LANTAI 2
1 Pekerjaan Pengecatan Dinding 3,666.70 m² 53,974.10 197,906,832.47
2 Pekerjaan Pengecatan Plafond 607.11 m² 32,147.10 19,516,858.03
Total Jumlah Harga 217,423,690.50
LANTAI 3
1 Pekerjaan Pengecatan Dinding 3,666.70 m² 53,974.10 197,906,832.47
2 Pekerjaan Pengecatan Plafond 610.03 m² 32,147.10 19,610,534.68
Total Jumlah Harga 217,517,367.15
VI PEKERJAAN MEP
6.1 PEKERJAAN SANITASI
LANTAI 1
1 Pasangan Kloset Duduk + Acc 5 bh 7,146,560.00 35,732,800.00
2 Pasangan Kloset Jongkok + Acc 7 bh 822,652.50 5,758,567.50
3 Pasangan Urinoir + Acc 5 bh 4,149,775.00 20,748,875.00
4 Pasangan Washtafel + Acc 10 bh 1,687,165.00 16,871,650.00
5 Pasangan Jetwasher 5 bh 412,940.00 2,064,700.00
6 Pasangan Penyekatan Urinoir 4 bh 1,829,630.00 7,318,520.00
7 Pasangan Floor Drain Stainless Steel 13 bh 427,426.25 5,556,541.25
8 Pasangan Kran Air 2 bh 146,078.75 292,157.50
9 Pasangan Kitchen Zink 1 bh 782,028.75 782,028.75
10 Pasangan Pipa PVC 1/2" 1,792 m 21,646.59 38,790,696.00
11 Pasangan Pipa PVC 3/4" 1,543 m 28,870.75 44,547,567.25
12 Pasangan Pipa PVC 1 1/2" 742 m 45,587.44 33,825,878.63
13 Pasangan Pipa PVC 2" 1,741 m 56,994.00 99,226,554.00
14 Pasangan Pipa PVC 4" 1,421 m 114,661.47 162,933,947.09
15 Septictank 3 unit 4,784,677.00 14,354,031.00
16 Pompa air 1 bh 1,755,000.00 1,755,000.00
17 Water proofing lantai KM/Wc 72 m² 62,469.15 4,497,778.80
Total Jumlah Harga 495,057,292.77
LANTAI 2
1 Pasangan Kloset Duduk + Acc 22 bh 7,146,560.00 157,224,320.00
2 Pasangan Washtafel + Acc 22 bh 1,687,165.00 37,117,630.00
3 Pasangan Jetwasher 22 bh 412,940.00 9,084,680.00
4 Pasangan Floor Drain Stainless Steel 22 bh 427,426.25 9,403,377.50
5 Pasangan Kran Air 22 bh 146,078.75 3,213,732.50
6 Pasangan Kitchen Zink 1 bh 782,028.75 782,028.75
7 Pasangan Pipa PVC 1/2" 4,782 m 21,646.59 103,514,011.31
8 Pasangan Pipa PVC 3/4" 3,278 m 28,870.75 94,638,318.50
9 Pasangan Pipa PVC 1 1/2" 853 m 45,587.44 38,886,084.19
10 Pasangan Pipa PVC 2" 3,246 m 56,994.00 185,002,524.00
11 Pasangan Pipa PVC 4" 2,353 m 114,661.47 269,798,435.97
12 Pompa air 2 bh 1,755,000.00 3,510,000.00
13 Shower 22 bh 85,000.00 1,870,000.00
14 Water profing lantai KM/Wc 69 m² 62,469.15 4,320,366.41
Total Jumlah Harga 918,365,509.13
633
LANTAI 3
1 Pasangan Kloset Duduk + Acc 19 bh 7,146,560.00 135,784,640.00
2 Pasangan Washtafel + Acc 19 bh 1,687,165.00 32,056,135.00
3 Pasangan Jetwasher 19 bh 412,940.00 7,845,860.00
4 Pasangan Floor Drain Stainless Steel 19 bh 427,426.25 8,121,098.75
5 Pasangan Kran Air 19 bh 146,078.75 2,775,496.25
6 Pasangan Pipa PVC 1/2" 4,328 m 21,646.59 93,686,457.75
7 Pasangan Pipa PVC 3/4" 1,532 m 28,870.75 44,229,989.00
8 Pasangan Pipa PVC 1 1/2" 765 m 45,587.44 34,874,389.69
9 Pasangan Pipa PVC 2" 2,841 m 56,994.00 161,919,954.00
10 Pasangan Pipa PVC 4" 1,945 m 114,661.47 223,016,556.72
11 Pompa air 2 bh 1,755,000.00 3,510,000.00
13 Shower 19 bh 85,000.00 1,615,000.00
12 Water profing lantai KM/Wc 75 m² 62,469.15 4,695,181.31
Total Jumlah Harga 754,130,758.47
LANTAI 2
1 Instalasi Titk Lampu 177 titik 385,227.00 68,185,179.00
2 Instalasi Stop Kontak 154 titik 592,227.00 91,202,958.00
3 Instalasi Exchaust Fan 8 titik 598,258.75 4,786,070.00
4 Instalasi Stop Kontak AC 48 titik 688,094.00 33,028,512.00
5 Lampu TL RM 2 x 18 192 Bh 956,000.00 183,552,000.00
6 Lampu TL 1 x 36 96 Bh 455,250.00 43,704,000.00
7 Down light PLC 18 W 118 Bh 455,250.00 53,719,500.00
8 Down light PLC 8 W 59 Bh 385,750.00 22,759,250.00
9 Exchaust Fan 8 Bh 330,200.00 2,641,600.00
10 Saklar Tunggal 28 Bh 4,000.00 112,000.00
11 Saklar Ganda 66 Bh 112,000.00 7,392,000.00
12 Stop Kontak 132 Bh 17,000.00 2,244,000.00
13 Stop Kontank AC 48 Bh 225,350.00 10,816,800.00
14 Box Panel 1 2 Bh 32,200,300.00 64,400,600.00
Total Jumlah Harga 588,544,469.00
LANTAI 3
1 Instalasi Titk Lampu 171 titik 385,227.00 65,873,817.00
2 Instalasi Stop Kontak 143 titik 592,227.00 84,688,461.00
3 Instalasi Exchaust Fan 4 titik 598,258.75 2,393,035.00
4 Instalasi Stop Kontak AC 41 titik 688,094.00 28,211,854.00
5 Lampu TL RM 2 x 18 172 Bh 956,000.00 164,432,000.00
6 Lampu TL 1 x 36 86 Bh 455,250.00 39,151,500.00
7 Down light PLC 18 W 123 Bh 455,250.00 55,995,750.00
8 Down light PLC 8 W 43 Bh 385,750.00 16,587,250.00
9 Exchaust Fan 4 Bh 330,200.00 1,320,800.00
10 Saklar Tunggal 27 Bh 4,000.00 108,000.00
11 Saklar Ganda 34 Bh 112,000.00 3,808,000.00
12 Stop Kontak 114 Bh 17,000.00 1,938,000.00
13 Stop Kontak AC 41 Bh 225,350.00 9,239,350.00
14 Box Panel 1 2 Bh 32,200,300.00 64,400,600.00
` Total Jumlah Harga 538,148,417.00
LANTAI 2
4.4 Pekerjaan Balok
Pekerjaan Pembesian Balok 0.070 oh 8,047.62 Kg 250.00 oh 14.29 Kg 3,571.43 Kg/hr 2.25 ~ 3 hari
Pekerjaan Bekisting Balok 0.660 oh 515.15 m² 150.00 oh 1.52 m² 227.27 m²/hr 2.27 ~ 3 hari
Pekerjaan Beton Balok 2.100 oh 54.13 m³ 50.00 oh 0.48 m³ 23.81 m³/hr 2.27 ~ 3 hari
Pekerjaan Pembongkaran Bekisting Balok 0.250 oh #NAME? m³ 50.00 oh 4.00 m³ 200.00 m³/hr #NAME? ~ #NAME? hari
LANTAI 3
4.8 Pekerjaan Balok
Pekerjaan Pembesian Balok 0.070 oh 8,047.62 Kg 250.00 oh 14.29 Kg 3,571.43 Kg/hr 2.25 ~ 3 hari
Pekerjaan Bekisting Balok 0.660 oh 515.15 m² 150.00 oh 1.52 m² 227.27 m²/hr 2.27 ~ 3 hari
Pekerjaan Beton Balok 2.100 oh 54.13 m³ 50.00 oh 0.48 m³ 23.81 m³/hr 2.27 ~ 3 hari
Pekerjaan Pembongkaran Bekisting Balok 0.250 oh 515.15 m³ 50.00 oh 4.00 m³ 200.00 m³/hr 2.58 ~ 3 hari
Pekerjaan Pembongkaran Bekisting Kolom 0.250 oh #NAME? m³ 20.00 oh 4.00 m³ 80.00 m³/hr #NAME? ~ #NAME? hari
LANTAI ATAP
4.11 Pekerjaan Balok
Pekerjaan Pembesian Balok 0.070 oh 8,596.35 Kg 250.00 oh 14.29 Kg 3,571.43 Kg/hr 2.41 ~ 3 hari
Pekerjaan Bekisting Balok 0.660 oh 479.10 m² 150.00 oh 1.52 m² 227.27 m²/hr 2.11 ~ 3 hari
Pekerjaan Beton Balok 2.100 oh 52.54 m³ 50.00 oh 0.48 m³ 23.81 m³/hr 2.21 ~ 3 hari
Pekerjaan Pembongkaran Bekisting Balok 0.250 oh 479.10 m³ 50.00 oh 4.00 m³ 200.00 m³/hr 2.40 ~ 3 hari
V PEKERJAAN ARSITEKTUR
5.1 PEKERJAAN DINDING
- LANTAI 1
Pekerjaan Pasangan Dinding Bata Ad. 1:4 0.600 oh 1,858.13 m² 112.00 oh 1.67 m² 186.67 m²/hr 9.95 ~ 10 hari
- LANTAI 2
Pekerjaan Pasangan Dinding Bata Ad. 1:4 0.600 oh 1,783.80 m² 112.00 oh 1.67 m² 186.67 m²/hr 9.56 ~ 10 hari
- LANTAI 3
Pekerjaan Pasangan Dinding Bata Ad. 1:4 0.600 oh 1,783.80 m² 112.00 oh 1.67 m² 186.67 m²/hr 9.56 ~ 10 hari
- LANTAI 2
Pekerjaan Pintu P1 0.085 oh 18.00 m² 2.00 oh 11.76 m² 23.53 m²/hr 0.77 ~
Pekerjaan Pintu P2 0.085 oh 4.80 m² 2.00 oh 11.76 m² 23.53 m²/hr 0.20 ~ 2 hari
Pintu KM/WC/P3 0.050 oh 5.00 bh 1.00 oh 20.00 bh 20.00 bh/hr 0.25 ~
- LANTAI 3
Pekerjaan Pintu P1 0.085 oh 3.60 m² 2.00 oh 11.76 m² 23.53 m²/hr 0.15 ~
Pekerjaan Pintu P2 0.085 oh 3.20 m² 2.00 oh 11.76 m² 23.53 m²/hr 0.14 ~ 1 hari
Pintu KM/WC/P3 0.050 oh 4.00 bh 1.00 oh 20.00 bh 20.00 bh/hr 0.20 ~
- LANTAI 1
Kunci Tanam Stainless Steel 0.010 oh 19.00 Bh 2.00 oh 100.00 Bh 200.00 Bh/hr 0.10 ~ 1 hari
Engsel Pintu 0.015 oh 38.00 Bh 4.00 oh 66.67 Bh 266.67 Bh/hr 0.14 ~
- LANTAI 2
Kunci Tanam Stainless Steel 0.010 oh 18.00 Bh 2.00 oh 100.00 Bh 200.00 Bh/hr 0.09 ~ 1 hari
Engsel Pintu 0.015 oh 36.00 Bh 4.00 oh 66.67 Bh 266.67 Bh/hr 0.13 ~
- LANTAI 3
Kunci Tanam Stainless Steel 0.010 oh 8.00 Bh 2.00 oh 100.00 Bh 200.00 Bh/hr 0.04 ~ 1 hari
Engsel Pintu 0.015 oh 16.00 Bh 4.00 oh 66.67 Bh 266.67 Bh/hr 0.06 ~
- LANTAI 2
Pemasangan 1 M2 Langit - Langit gypsum board + rangka besi0.100
hollow oh 607.11 m2 23.00 oh 10.00 m2 230.00 m²/hr 2.64 ~ 3 hari
- LANTAI 3
Pemasangan 1 M2 Langit - Langit gypsum board + rangka besi0.100
hollow oh 610.03 m2 23.00 oh 10.00 m2 230.00 m²/hr 2.65 ~ 3 hari
VI PEKERJAAN MEP
6.1 PEKERJAAN SANITASI
6.1.1 LANTAI 1
623
6.1.2 LANTAI 2
Pasangan Kloset Duduk + Acc 3.300 oh 22 Bh 17 oh 0.30 Bh 5.15 Bh/hr 4.27 ~
Pasangan Washtafel + Acc 1.200 oh 22 Bh 23 oh 0.83 Bh 19.17 Bh/hr 1.15 ~
Pasangan Jetwasher 0.010 oh 22 Bh 23 oh 100.00 Bh 2,300.00 Bh/hr 0.01 ~
Pasangan Floor Drain Stainless Steel 0.010 oh 22 Bh 23 oh 100.00 Bh 2,300.00 Bh/hr 0.01 ~
Pasangan Kran Air Standar 0.010 oh 22 Bh 5 oh 100.00 Bh 500.00 Bh/hr 0.04 ~
Pasangan Kitchen Zink 0.030 oh 1 Bh 5 oh 33.33 Bh 166.67 Bh/hr 0.01 ~ 122 hari
Pasangan Pipa PVC 1/2" 0.036 oh 4,782 m' 5 oh 27.78 m' 138.89 m'/hr 34.43 ~
Pasangan Pipa PVC 3/4" 0.036 oh 3,278 m' 5 oh 27.78 m' 138.89 m'/hr 23.60 ~
Pasangan Pipa PVC 1 1/2" 0.054 oh 853 m' 5 oh 18.52 m' 92.59 m'/hr 9.21 ~
Pasangan Pipa PVC 2" 0.054 oh 3,246 m' 10 oh 18.52 m' 185.19 m'/hr 17.53 ~
Pasangan Pipa PVC 4" 0.081 oh 2,353 m' 8 oh 12.35 m' 98.77 m'/hr 23.82 ~
pompa air 0.010 oh 2 Bh 2 oh 100.00 Bh 200.00 Bh/hr 0.01 ~
Shower 1.000 oh 22 Bh 3 oh 1.00 Bh 3.00 Bh/hr 7.33 ~
water profing lantai KM/Wc 0.028 oh 69 m2 30 oh 35.71 m2 1,071.43 m²/hr 0.06 ~
6.1.3 LANTAI 3
Pasangan Kloset Duduk + Acc 3.300 oh 19 Bh 17 oh 0.30 Bh 5.15 Bh/hr 3.69 ~
Pasangan Washtafel + Acc 1.200 oh 19 Bh 23 oh 0.83 Bh 19.17 Bh/hr 0.99 ~
Pasangan Jetwasher 0.010 oh 19 Bh 23 oh 100.00 Bh 2,300.00 Bh/hr 0.01 ~
Pasangan Floor Drain Stainless Steel 0.010 oh 19 Bh 23 oh 100.00 Bh 2,300.00 Bh/hr 0.01 ~
Pasangan Kran Air Standar 0.010 oh 19 Bh 5 oh 100.00 Bh 500.00 Bh/hr 0.04 ~ 89 hari
Pasangan Pipa PVC 1/2" 0.036 oh 4,328 m' 6 oh 27.78 m' 166.67 m'/hr 25.97 ~
Pasangan Pipa PVC 3/4" 0.036 oh 1,532 m' 6 oh 27.78 m' 166.67 m'/hr 9.19 ~
Pasangan Pipa PVC 1 1/2" 0.054 oh 765 m' 6 oh 18.52 m' 111.11 m'/hr 6.89 ~
Pasangan Pipa PVC 2" 0.054 oh 2,841 m' 10 oh 18.52 m' 185.19 m'/hr 15.34 ~
Pasangan Pipa PVC 4" 0.081 oh 1,945 m' 8 oh 12.35 m' 98.77 m'/hr 19.69 ~
pompa air 0.010 oh 2 Bh 2 oh 100.00 Bh 200.00 Bh/hr 0.01 ~
Shower 1.000 oh 19 Bh 3 oh 1.00 Bh 3.00 Bh/hr 6.33 ~
water profing lantai KM/Wc 0.028 oh 75 m2 30 oh 35.71 m2 1,071.43 m²/hr 0.07 ~
6.2.2 LANTAI 2
Instalasi Titk Lampu 0.135 oh 177.00 titik 15 oh 7.41 titik 111.11 titik/hr 1.59 ~
Instalasi Stop Kontak 0.135 oh 154.00 titik 30 oh 7.41 titik 222.22 titik/hr 0.69 ~
Instalasi Exchaust Fan 0.100 oh 8.00 titik 10 oh 10.00 titik 100.00 titik/hr 0.08 ~
Instalasi Stop Kontak AC 0.135 oh 48.00 titik 10 oh 7.41 titik 74.07 titik/hr 0.65 ~
Lampu TL RM 2 x 18 1.000 oh 192.00 Bh 22 oh 1.00 Bh 22.00 Bh/hr 8.73 ~
Lampu TL 1 x 36 1.000 oh 96.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 3.20 ~
Down light PLC 18 W 1.000 oh 118.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 3.93 ~ 33 hari
Down light PLC 8 W 1.000 oh 59.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 1.97 ~
Exchaust Fan 1.000 oh 8.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 0.27 ~
Saklar Tunggal 1.000 oh 28.00 Bh 10 oh 1.00 Bh 10.00 Bh/hr 2.80 ~
Saklar Ganda 1.000 oh 66.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 2.20 ~
Stop Kontak 1.000 oh 132.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 4.40 ~
Stop Kontak AC 1.000 oh 48.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 1.60 ~
Box Panel 1 1.000 oh 2.00 Bh 5 oh 1.00 Bh 5.00 Bh/hr 0.40 ~
6.2.3 LANTAI 3
Instalasi Titk Lampu 0.135 oh 171.00 titik 15 oh 7.41 titik 111.11 titik/hr 1.54 ~
Instalasi Stop Kontak 0.135 oh 143.00 titik 30 oh 7.41 titik 222.22 titik/hr 0.64 ~
Instalasi Exchaust Fan 0.100 oh 4.00 titik 10 oh 10.00 titik 100.00 titik/hr 0.04 ~
Instalasi Stop Kontak AC 0.135 oh 41.00 titik 10 oh 7.41 titik 74.07 titik/hr 0.55 ~
Lampu TL RM 2 x 18 1.000 oh 172.00 Bh 22 oh 1.00 Bh 22.00 Bh/hr 7.82 ~
Lampu TL 1 x 36 1.000 oh 86.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 2.87 ~
Down light PLC 18 W 1.000 oh 123.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 4.10 ~
Down light PLC 8 W 1.000 oh 43.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 1.43 ~ 31 hari
Exchaust Fan 1.000 oh 4.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 0.13 ~
Saklar Tunggal 1.000 oh 27.00 Bh 10 oh 1.00 Bh 10.00 Bh/hr 2.70 ~
Saklar Ganda 1.000 oh 34.00 Bh 10 oh 1.00 Bh 10.00 Bh/hr 3.40 ~
Stop Kontak 1.000 oh 114.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 3.80 ~
Stop Kontak AC 1.000 oh 41.00 Bh 30 oh 1.00 Bh 30.00 Bh/hr 1.37 ~
Box Panel 1 1.000 oh 2.00 Bh 5 oh 1.00 Bh 5.00 Bh/hr 0.40 ~
4.2.6 Barchart dan Kurva S
4.2 LANTAI 2
4.2.1 Pekerjaan Pembesian Balok 19 Rp 209,990,591 1.177
4.2.2 Pekerjaan Bekisting Balok 21 Rp 234,122,410 1.312
4.2.3 Pekerjaan Beton Balok 13 Rp 102,801,616 0.576
4.2.5 Pekerjaan Pembesian Pelat Lantai 16 Rp 85,515,111 0.479
4.2.6 Pekerjaan Bekisting Pelat 22 Rp 265,224,591 1.487
4.2.7 Pekerjaan Beton Pelat Lantai 13 Rp 181,054,301 1.015
4.2.9 Pekerjaan Pembesian Kolom 16 Rp 92,328,562 0.518
4.2.10 Pekerjaan Bekisting Kolom 14 Rp 94,876,720 0.532
4.2.11 Pekerjaan Beton Kolom 12 Rp 40,417,892 0.227
4.2.13 Pekerjaan Pembesian Tangga 5 Rp 10,405,550 0.058
4.2.14 Pekerjaan Bekisting Tangga 3 Rp 10,036,911 0.056
4.2.15 Pekerjaan Beton Tangga 2 Rp 11,252,812 0.063
4.3 LANTAI 3
4.3.1 Pekerjaan Pembesian Balok 19 Rp 209,990,591 1.177
4.3.2 Pekerjaan Bekisting Balok 21 Rp 234,122,410 1.312
4.3.3 Pekerjaan Beton Balok 13 Rp 102,801,616 0.576
4.3.5 Pekerjaan Pembesian Pelat Lantai 16 Rp 85,515,111 0.479
4.3.6 Pekerjaan Bekisting Pelat 22 Rp 265,224,591 1.487
4.3.7 Pekerjaan Beton Pelat Lantai 13 Rp 181,054,301 1.015
4.3.9 Pekerjaan Pembesian Kolom 16 Rp 92,328,562 0.518
4.3.10 Pekerjaan Bekisting Kolom 14 Rp 94,876,720 0.532
4.3.11 Pekerjaan Beton Kolom 12 Rp 40,417,892 0.227
V PEKERJAAN ARSITEKTUR
5.1 PEKERJAAN DINDING
5.1.1 Lantai 1 22 Rp 636,886,280 3.570
5.1.2 Lantai 2 26 Rp 611,410,829 3.427
5.1.3 Lantai 3 18 Rp 611,410,829 3.427
VI PEKERJAAN MEP
6.1 PEKERJAAN SANITASI
6.1.1 Lantai 1 20 Rp 495,057,293 2.775 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
6.1.2 Lantai 2 36 Rp 918,365,509 5.148
6.1.3 Lantai 3 20 Rp 754,130,758 4.227
6.2 PEKERJAAN LISTRIK
6.2.1 Lantai 1 14 Rp 399,111,399 2.237
6.2.2 Lantai 2 20 Rp 588,544,469 3.299
6.2.3 Lantai 3 17 Rp 538,148,417 3.017
0.08 0.08
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.01 0.01 0.01 0.01 0.01
0.02 0.02 0.02
0.03 0.03
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.02 0.02 0.02
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14 0.14
0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
0.16 0.16 0.16 0.16 0.16 0.16 0.16
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.4 0.4 0.5 0.5 0.5 0.5 0.5 0.5 0.4 0.5 0.5 0.4 0.2 0.2 0.5 0.5 0.5 0.5 0.6 0.6 0.8 0.8 0.8 0.7 0.6 0.9 0.9 0.7 0.7 0.8 0.8 0.8 0.9 0.9 0.8 0.8 0.6 0.7 0.7 0.5 0.5 0.6 0.6 0.6 0.6 0.6 0.5 0.5 0.5 0.5 0.3 0.4 0.5 0.5 0.5 0.5 0.6 0.5 0.5 0.5 0.6 0.6 0.6 0.7 0.7 0.7 0.7 0.7 0.5 0.5 0.4 0.4 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.43 0.59 0.59 0.59 0.59 0.62 0.62 0.62
26.2 26.5 27.0 27.6 28.1 28.6 29.1 29.6 30.0 30.5 31.0 31.3 31.6 31.8 32.3 32.8 33.3 33.8 34.4 34.9 35.7 36.5 37.2 37.9 38.5 39.4 40.3 41.0 41.7 42.6 43.4 44.2 45.1 45.9 46.7 47.6 48.2 48.9 49.6 50.1 50.6 51.2 51.7 52.3 52.9 53.5 54.0 54.5 55.0 55.5 55.8 56.2 56.8 57.3 57.9 58.4 59.0 59.5 60 61 61 62 62 63 63.8 64.4 65.1 65.7 66.3 66.8 67.2 68 68.0 68.5 69.0 69.4 69.9 70.3 70.8 71.2 71.8 72.4 73.0 73.6 74.2 74.8 75.4
BULAN KE 6 BULAN KE 7 BULAN KE 8
3 4 1 2 3 4 1 2 3 4
156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224
100%
50%
0.13 0.13
0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19 0.19
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.11
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.14
0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21
0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0%
0.70 0.56 0.43 0.28 0.28 0.35 0.35 0.35 0.35 0.46 0.46 0.46 0.44 0.48 0.48 0.40 0.40 0.40 0.40 0.59 0.40 0.40 0.40 0.40 0.56 0.56 0.56 0.56 0.74 0.74 0.74 0.75 0.75 0.54 0.54 0.63 0.63 0.44 0.44 0.44 0.47 0.31 0.31 0.40 0.39 0.21 0.21 0.21 0.21 0.12 0.17 0.17 0.17 0.17 0.17 0.07 0.07 0.07 0.07 0.07 0.07 0.09 0.09 0.09 0.09 0.09 0.09 0.02 0.02
76.1 76.7 77.1 77.4 77.7 78.0 78.4 78.7 79.1 79.5 80.0 80.5 80.9 81.4 81.9 82.3 82.7 83.1 83.5 84.1 84.5 84.9 85.3 85.7 86.2 86.8 87.4 87.9 88.7 89.4 90.1 90.9 91.6 92.2 92.7 93.4 94.0 94.4 94.9 95.3 95.8 96.1 96.4 96.8 97.2 97.4 97.6 97.8 98.0 98.2 98.3 98.5 98.7 98.8 99.0 99.1 99.1 99.2 99.3 99.4 99.4 99.5 99.6 99.7 99.8 99.9 99.97 99.98 100.00
DURASI
URAIAN PEKERJAAN BIAYA (Rp) BOBOT (%)
(HARI)
PEKERJAAN PERSIAPAN
1.1 Pekerjaan Pembersihan #REF! Rp 21,822,688 #NAME?
1.2 Pemasangan Bouwplank #REF! Rp 10,559,846 #NAME?
1.3 Pemagaran Proyek #REF! Rp 62,022,473 #NAME?
1.4 Pembuatan Kantor Sementara #REF! Rp 70,363,038 #NAME?
1.5 Pembuatan Gudang Alat dan Bahan #REF! Rp 53,055,538 #NAME?
1.6 Mobilisasi Alat Pancang #REF! Rp 40,000,000 #NAME?
4.2 LANTAI 2
4.2.1 Pekerjaan Pembesian Balok #REF! Rp 209,990,591 #NAME?
4.2.2 Pekerjaan Bekisting Balok #REF! Rp 234,122,410 #NAME?
4.2.3 Pekerjaan Beton Balok #REF! Rp 102,801,616 #NAME?
4.2.4 Pekerjaan Pembongkaran Bekisting Balok #REF! #NAME? #NAME?
4.2.5 Pekerjaan Pembesian Pelat Lantai #REF! Rp 85,515,111 #NAME?
4.2.6 Pekerjaan Bekisting Pelat #REF! Rp 265,224,591 #NAME?
4.2.7 Pekerjaan Beton Pelat Lantai #REF! Rp 181,054,301 #NAME?
4.2.8 Pekerjaan Pembongkaran Bekisting Pelat Lantai #REF! #NAME? #NAME?
4.2.9 Pekerjaan Pembesian Kolom #REF! Rp 92,328,562 #NAME?
4.2.10 Pekerjaan Beton Pelat Lantai 1 #REF! Rp 94,876,720 #NAME?
4.2.11 Pekerjaan Beton Kolom #REF! Rp 40,417,892 #NAME?
4.2.12 Pekerjaan Pembongkaran Bekisting Kolom #REF! #NAME? #NAME?
4.2.13 Pekerjaan Pembesian Tangga #REF! Rp 10,405,550 #NAME?
4.2.14 Pekerjaan Bekisting Tangga #REF! Rp 10,036,911 #NAME?
4.2.15 Pekerjaan Beton Tangga #REF! Rp 11,252,812 #NAME?
4.2.16 Pekerjaan Pembongkaran Bekisting Tangga #REF! #NAME? #NAME?
4.3 LANTAI 3
4.3.1 Pekerjaan Pembesian Balok #REF! Rp 209,990,591 #NAME?
4.3.2 Pekerjaan Bekisting Balok #REF! Rp 234,122,410 #NAME?
4.3.3 Pekerjaan Beton Balok #REF! Rp 102,801,616 #NAME?
4.3.4 Pekerjaan Pembongkaran Bekisting Balok #REF! #NAME? #NAME?
4.3.5 Pekerjaan Pembesian Pelat Lantai #REF! Rp 85,515,111 #NAME?
4.3.6 Pekerjaan Bekisting Pelat #REF! Rp 265,224,591 #NAME?
4.3.7 Pekerjaan Beton Pelat Lantai #REF! Rp 181,054,301 #NAME?
4.3.8 Pekerjaan Pembongkaran Bekisting Pelat Lantai #REF! #NAME? #NAME?
4.3.9 Pekerjaan Pembesian Kolom #REF! Rp 92,328,562 #NAME?
4.3.10 Pekerjaan Pembesian Kolom #REF! Rp 94,876,720 #NAME?
4.3.11 Pekerjaan Beton Kolom #REF! Rp 40,417,892 #NAME?
4.3.12 Pekerjaan Pembongkaran Bekisting Kolom #REF! #NAME? #NAME?
PEKERJAAN ARSITEKTUR
5.1 PEKERJAAN DINDING
5.1.1 LANTAI 1 #REF! Rp 636,886,280 #NAME?
5.1.2 LANTAI 2 #REF! Rp 611,410,829 #NAME?
5.1.3 LANTAI 3 #REF! Rp 611,410,829 #NAME?
PEKERJAAN MEP
6.1 PEKERJAAN SANITASI
6.1.1 LANTAI 1 #REF! Rp 495,057,293 #NAME?
6.1.2 LANTAI 2 #REF! Rp 918,365,509 #NAME?
6.1.3 LANTAI 3 #REF! Rp 754,130,758 #NAME?
6.2 PEKERJAAN LISTRIK
6.2.1 LANTAI 1 #REF! Rp 399,111,399 #NAME?
6.2.2 LANTAI 2 #REF! Rp 588,544,469 #NAME?
6.2.3 LANTAI 3 #REF! Rp 538,148,417 #NAME?
PEKERJAAN LAIN-LAIN
7.1 PEKERJAAN AKHIR
Pekerjaan Pembersihan Akhir #REF! Rp 22,942,500 #NAME?
TOTAL #NAME? #NAME?
DURASI
NO URAIAN PEKERJAAN HARGA
(MINGGU)
I PEKERJAAN PERSIAPAN 1 Rp
II PEKERJAAN TANAH DAN PASIR 4 Rp
III PEKERJAAN STRUKTUR BAWAH 6 Rp
IV PEKERJAAN STRUKTUR ATAS 10 Rp
V PEKERJAAN ARSITEKTUR 7 Rp
VI PEKERJAAN MEP 10 Rp
VII PEKERJAAN LAIN-LAIN 2 Rp
TOTAL Rp
RENCANA KEMAJUAN PEKERJAAN
KUMULATIF RENCANA KEMAJUAN PEKERJAAN
HARGA
257,823,582
135,638,100
3,868,615,813
4,229,132,019
4,882,332,745
3,693,357,846
22,942,500
17,089,842,605
REKAPITULASI BIAYA
RAB PEMBANGUNAN GEDUNG KULIAH FAKULTAS EKONOMI UIN RADEN FATAH
KAMPUS B JAKABARING PALEMBANG SUMATERA SELATAN
DURASI DURASI
NO URAIAN PEKERJAAN HARG
(HARI) (MINGGU)
I PEKERJAAN PERSIAPAN #REF! 4 Rp
II PEKERJAAN TANAH DAN PASIR #REF! 3 Rp
III PEKERJAAN PONDASI #REF! 3 Rp
IV PEKERJAAN BEKISTING #REF! 18 Rp
V PEKERJAAN BAJA DAN TULANGAN #REF! 26 Rp
VI PEKERJAAN BETON #REF! 12 Rp
VII PEKERJAAN PEMBONGKARAN BEKISTING #REF! 9 Rp
VIII PEKERJAAN DINDING #REF! 8 Rp
IX PEKERJAAN PLESTERAN DINDING #REF! 12 Rp
X PEKERJAAN KUSEN, PINTU & JENDELA #REF! 9 Rp
XI PEKERJAAN KUNCI #REF! 2 Rp
XII PEKERJAAN PASANGAN KERAMIK #REF! 9 Rp
XIII PEKERJAAN SANITASI #REF! 5 Rp
XIV PEKERJAAN LISTRIK #REF! 6 Rp
XV PEKERJAAN PLAFOND #REF! 3 Rp
XVI PEKERJAAN PENGECATAN #REF! 6 Rp
XVII PEKERJAAN AKHIR #REF! 3 Rp
TOTAL Rp
UIN RADEN FATAH
ELATAN
HARGA
257,823,582
135,638,100
3,868,615,813
4,229,132,019
3,868,615,813
11,252,812
4,229,132,019
1,859,707,937
1,474,713,140
119,700,737
44,405,899
600,848,159
2,167,553,560
1,525,804,285
122,568,876
660,387,998
22,942,500
25,198,843,250