Lifting Plan
for GFE Container placement
SKE SRL
Site Prep and Pad for SAF at MK, Mihail Kogălniceanu (MK) FOS,
Romania
LIFT PLAN
1 General
2 Personnel
3 Area Preparation
4 Load parameters
5 LHE consideration
6 Environmental Considerations
7 Site drawings
8 Operational Testing
9 Load testing
Attachment
-(A) Form 16-3 Critical lift plan.pdf
-(B) Site drawing plan.pdf
-(C) Truck crane qualifications & certifications.pdf
-(D) Data sheet -Hydraulic Mobile truck crane 02 ; LIEBHERR LTM 1045-3.1.pdf
1 General
This lift plan is prepared to be used for truck crane operations at below project:
Contract number: W912GB-15-S-0013 TO 0327
Contract name: Site prep & pad for SAF at MK.
Lift plan is prepared accordingly to EM-383-1-1, section 16. Load Handling Equipment’s
(LHE); & paragraphs 16.A ;16. B ;16D;16F;16G;16. I.
Lifting procedures for GFE 40 ft container is a critical lift ,since load weight is
76% ( greater than 75%) of crane capacity.
The operator shall remain adjacent to the equipment and is not engaged in any other
duties;
(ii) The CP determines that it is safe to do so and implements measures necessary to
restrain the boom hoist and telescoping, load, swing and outrigger functions;
(4) The operator shall respond to signals from the person who is directing the lift or an
appointed signal person. When a signal person is not used in the LHE operation, the
operator shall ensure he has full view of the load and the load travel paths at all times the
load is rigged to the equipment;
(5) Each operator is responsible for those operations under his direct control.
Whenever there is a concern as to safety, the operator shall have the authority to stop and
refuse to handle loads until a QP has determined that safety has been assure.
Rigger qualifications:
See attached to this plan annex:
(D) Personnel qualifications, Truck crane certifications & CNCIR inspection reports.pdf
3 Area Preparation
Lift Plan for :
for GFE Container placement
Page :5 of 12
W912GB-15-D-0013 TO 0327
ATFP-Site prep & pad for SAF at MK.
3.2 Blocking
During load handling period a blocked/restricted area will be put in place around truck crane
and load location.
Properly traffic warning posts will be put to restriction unauthorized personnel to entry
during load handling.
4 Load parameters
GFE container must be unload by GOV. personnel near to final placement as shown on
Appendix (B) Site drawing plan.pdf position.
SKE will do final placement on twist lock.
40 ft container dimensions:
5 LHE Considerations
-Type of crane & Model: Hydraulic Mobile truck crane; LIEBHERR LTM 1045-3.1
-Max Truck crane Capacity: 45 tons
-Radius: Max. 30m
Min. 3m
-Boom length: Max. 34m
Min.10.3m
-Crane capacity:(max radius): 16 t
(min radius): 40,6 t
-Slings & hoist ropes: max.180kg
Find attached full Truck crane manufacturer data sheet to appendix (G)
6 Environmental Considerations;
Prior to schedule lifting, will be checked environmental consideration that can affect lifting
procedures.
Previously rain can affect ground conditions.
Proper weather (wind, storms, precipitation and ground condition) must be favorable during
lifting procedures.
16.I.01 LHE shall not be operated when wind speeds at the site attain the maximum wind
velocity based on the surface/load ratio recommendations of the manufacturer.
a. At winds greater than 20 mph (9 m/s), the operator, rigger, and lift supervisor shall
cease all crane operations, evaluate conditions and determine if the lift shall proceed. This
determination shall be based on wind calculations per manufacturer’s recommendations.
b. The determination to proceed or not shall be documented in the LHE/crane
operator’s logbook.
16.I.02 Operations performed during weather conditions that produce icing of the LHE or
reduced visibility shall be performed at reduced functional speeds and with signaling means
appropriate to the situation.
16.I.03 When lightning is observed, all LHE operations shall stop. A determination shall be
made as to proximity to operation being performed. (Use a lightning detector or once
lightning is seen, count the number of seconds until you hear thunder. Divide number of
seconds by 5 to get the distance the lightning is away from you). If lightning is 10 miles
away or less, work must stop until 30 minutes after the last audible thunder or visible flash
of lightning.
7 Site drawings
8 Operational Testing
b. Load Testing shall be performed at 100% to 110% of the ANTICIPATED LOAD for the
specified configuration, not to exceed 100% of the manufacturer's load chart at the
configuration of the test. The actual anticipated load itself may be used as the test load if
approved by the GDA.
b. Load Testing shall be performed at 100 to 110% of the ANTICIPATED LOAD for the
specified configuration, not to exceed 100% of the manufacturer's load chart at the
configuration of the test. The actual anticipated load itself will be used as the test load if
approved through this lifting plan by GDA.
c. Load testing shall be performed:
(1) Before initial use of crane or hoisting equipment in which a load bearing or load
controlling part or component, brake, travel component, or clutch has been altered,
replaced, or repaired, and
(2) Every time a crane or hoisting equipment(s) is reconfigured or re-assembled after
disassembly (to include booms);
(3) When the manufacturer requires load testing.