Professional Documents
Culture Documents
143
Assodata Members-continued.
ALBERT
Inst. C.E.
EDWARD ARTRUB WILSON.
1
WILSON, B.&., ( h n d . ) stud. HOWARD
C.E.
PETER
WONTNER-SXITH, Stud. h S t .
REmus WRAY.
JOHN FRANCE WILSON. l
Aesociates.
C H A R LCOURTENAY
SYDNEY ~ CASTLE. I CEARLESEOBERT HEXINGWAY.
HISTORY TRAMWAYS.
OF LONDOX
with the conduit should be the lines south of the Thames from
Westminster Bridge to Tooting, and from Blackfriars Bridge to
Hennington ; afterwards they added to these the line from Water-
loo Bridgeto St. George’s Circus. This means, i n other words,
thetramwaylinesrunning from thethreeThamesbridges at
Westminster, Waterloo, and Blackfriars, to a southern terminus at
Tooting, having a route length of over 8 miles and consisting of
about 162 miles of single track (Fig. 1, Plate 2).
During the passing of the Bills through Parliament,most of the
borough authorities,whicharethe road authorities, expressed
themselves emphatically against overhead traction in any form ;
thus providing the Council withanotherstrong reason, had i t
been required, for proceeding with the more expensive system of
conduit construction. TheBills were finally passed in August,
1900,and provision was inserted that, before actual construction
began,plansmustbesubmittedtothe road authorities of the
various boroughs concerned, for approval, and to the Board of Trade.
A clause was also inserted that nowhere should overhead construc-
tion be employed without the consent of the road authorities of the
district. The consent of the Board of Trade and of the borough
authorities of Lambeth, Southwark and Wandsworth, within which
the Tooting lines lie, was finally obtained in the spring of 1901 ;
and, as by that time the other formalities prescribed by the Act
had also been attended to, the working-drawings andspecifications
for the final scheme were proceeded with, and thevarious contracts
were let.
In this Paperon the South London tramways, such features of
theworkasstation-plantand equipment, car-depots, rolling
stock (apparatus for collecting current excepted), etc., which are
more or less the same for overhead and conduit systems of electric
traction, will not be touched upon otherwise than by a passing
reference;buttheAuthor proposes tosubmitdetails of three
branches of the work, namely :-
(1) Construction of Permanent Way,
( 2 ) Electrical Distribution on the Line,
and (3) Collection of Current ;
ROAD-WORK
AND PERXANENT-WAY
CONSTRUCTION.
The general arrangementof road-work construction is shown i n
Figs. 2-6, Plate 2. A conduit or tube,whioh runstheentire
length of the lines, isformed in each track, exactly centralbetween
the running rails. The bottom and sides of the conduitproper
are composed entirely of 540-1 concrete and cast iron, and the top
consists partly of the same materials and partly of two 2-shaped
rolled slot-rails” (Fig. 7). These slot-rails form togetherthe
opening, or slot, by means of which communication canbe
established between the car-motors and the conductor-bars.
From Figs. 2-4, Plate 2 , it will be seen that at intervals of
These widths are necesaary to ensure easy running for the car-wheels, and
do not depend on plough-clearance. Hadthe latter been the only considera-
tion, the sizes might have been leas.
L 2
148 XILLAR ON THE ELECTREAL RECONSTRUCTION OF [Minutes of
Fig. 1.5.
PLAN
S C A L Ei!’z INCH ~ 1 FOOT
INCIICS 6 b F007
I _ -
CAST-IRONCOVER
FOR INSULATOR-CHAMBER.
Figs. 24-27, and those used for a junction are very similar In
Proceedings.] SOUTH LONDON TRAMWAYS. 159
character. In addition t o supportingthe slot-rails, the yokes
have ex
160 MILLAR ON THE ELEOTRICAERECONSTRUCTION OF [Miautes of
ElJ. 22.
CROSSING.
STANDARD
Figs. 24.
ELEVATION
SCALE I I N C H = 2 FEET
2 FrET
INCHES,
U,
? I
- I
:SPECIAL
YOKESFOR CROSSOTEHS.
YOKESFOR CROSSOVERS.
SPECIAL
when the leveris released the weightand points returnto their ori-
ginal positions. Holes are provided in lever T, for regulating the
leverage of the weight S. This form of construction, with weight
attached, is suitable for trailing points which are also intended
M 2
164 OF
MILLAR ON THE ELECTREAL Z~ECON~TRUCTION [Nindtee df
Figs.30.
litC" I M
Scdc
0
3 Inches
I 1
- I Fo~t
J * B ,NC"i3
CABLECOXXECTORT'O CONDCCTOR-BAR.
OF CURRENT.
COLLECTION
The arrangement for collecting current from the insulated con-
ductor-bars placed in the conduit, and for conveying it to the car-
motors mounted on thetrucks, is shown in Figs. 32 and 32a,
Figs.31.
DOUBLE J U N C T I O N
CONNECTIONS
COXDCCTOR-BAE AT SPECIAL
WORE.
Plate 3. The part suspended from the truck into the conduit is
called the ‘‘ plough,’’ and its support the ‘‘ plough carrier.” One
complete collectingapparatus is $tted to e&chcarl and trapdoors
Proceedings.] SOUTH LONDON TRAMWAYS. 169
inthe car-floor provide means of access toanypart of the
apparatus.
The details of the plough are shown in Figs. 33, Plate 3. I t
will be seen that the two soft cast-.iron shoes, one on each side of
the plough-shank,make contact with the conductor-bars. These
oontact-shoes are secured to the wooden framework at the bottom
of the plough by hinged steel links and abymild-steel flat spring.
When the plough is not in use, and the springs are normal, the
distance between the rubbing surfaces of the shoes is 7 inches, the
linksbeingarrangedtopreventanyfurther expansion. Whcn
the plough is in place between the conductor-bars, the springs are
compressed, andthedistance between therubbing surfaces is
reduced to 6 inches. A force of 8 to 10 lbs. is sufficient for
this, and ensures enough pressure on the conductor-bar to establish
good contact.
Short flexible fuses connect the shoes to the copper strip or lead
running down the chase inside the plough-shank. These fuses are
made of' closely stranded copper wire, and each will blow a t about
200 amperes. The fuses have a split-tube spring bayonet contact
for fitting into the terminal at the bottom of the copper leads, and
a t t h e contact-shoes.' Both the top and bottom terminals of the
copper leads are made of brass, sweated on to the leads. These
leads are covered with rubber andtaped, and the whole is carefully
vulcanized. From the top terminal a cable of 0.064 square inch
section is taken to the car-motors.
The bottom of the ploughconsists of three pieces of maple wood,
held together by steel screws, and it will be seen from the illustra-
tion that each screw penetrates through two of the boards only.
The heads of the screws are recessed into the wood, the recesses
being filled up flush with a special insulating material.2 Before
the woodwork is put together i t is immersed in a bath of this insu-
lating composition, at a temperature of 150° F., for 24 hours. The
shank of theplough consists of two mild-steelplates, tightly
screwed together, and thechases for the copper strips are carefully
milled out. The thickness of the plate, after the chase has been
milled, permits 2%inch tobe worn off before renewal becomes
necessary. The head of the plough consists of two gun-metal cast-
ings bolted to the shanks. The ends of the castings are designed
At the bottom of the leads, thc springbayonet contact has proved sufficient
to maintain the fuse inplace, but at the contact-shoes, in order to overcome the
loosening effects of vibration, it has been necessary to supplement thia holding
device by adding the springshown in Figs. 33.
Composed chicfly of beeswax, pw~ffin, vaseline and rosin,
170 YILLAR ON THE ELECTRICAL RECONSTRUCTION OF [Minutes Of
so as to form a cross-head which bears on the bottom flange of the
Z-shaped carrier. The claw-shaped steel castingbolted to the head
of the ploughenables the motor-man, by the aid of a special lifting-
apparatus, to raise the plough clear of the track when required,
for example, where the car runson to an overhead system.
Every plough is tested, at the makerts works, with a 2,000-
volt alternating current between boththeplough contact-shoes
and the steel plates of the plough ; and a condition of acceptance
is that it must stand this pressure for 3 hourwithoutinjury.
The completed plough is also immersed in the insulatingcompound
before mentioned, but at a slightly lower temperature, for some
hours, and on its being withdrawn, the waxy solution is allowed to
dry thoroughly. The carrier (Figs. 32) has two side frames which
are bolted to the side frames of the maximum-traction truck at the
pedestal of the small wheels, and form an extension to it. Between
these extension members are two Z-shaped cross-bars, 5 inches by
3 inches by 23 inches by 4 inch, from which the plough is hung.
Theploughrests on the bottomflange of the Z bars, and an
angle-iron bolted to the web of the bars prevents the plough from
rising (Fig. 32a). The ends of the bars are left open, so that in
an emergency, such as taking the wrong road, the plough, after
travelling right across the carrier,can drop outof the guides at the
ends without anyserious damage. By this means the most fruitful
source of damage to ploughs and interruption to traffic is avoided.
I n order to allow a plough to slide easilyo n these bars, the bottom
bearing of the plough-head is rounded. I n the centre of one of the
Z cross-bars a space of 8 inches of the bottom flange is cut away,
and a substitute for it is provided by a hinged flap (Figs. 32a).
This flap is secured to proper level by the bolt shown in Fig. 32.
The object of this arrangement is to provide a ready means for
removing or inserting a plough while the car is on the line. All
that is necessary to accomplish this is to release thehinged
bearing by withdrawing the bolt by means of the handle A. The
hinged flap then drops, and the plough canbe removed or inserted
as desired. The rubber cables from the ploughs to themotors have
suitableplug connections for permitting a plough tobe dis-
connected when it drops off, or is removed from the carrier.
DESCRIFTION OPERATIONS.
OF ROAD-WORK
imposed by this Section form a serious obstacle, and add greatly to the expense
of tramway schemes. The restrictions make trenching a difficult and
hazardous business forcontractors, to whom no guarantee can be given that
operations can extend beyond 100 yards; and they are apt to be used by local
authorities as a vexatious lever to secure concessions from the County Council
or similar body.
172 YILLAR ON THE
ELECTRICAL
RECONSTRUCTION OF [Minutes Of
of the work, except where their removal at that time would have
occasioned serious interference with the horse-car service. I n all,
about two hundred obstructionswere met with, rangingfrom small
service-pipes to &foot iron mains, and still larger brick sewers.
They inclxded gas-, water-,electric,telephone- andtelegraph-
mains, sewers, sewer-manholes and ventilators.
At the Tooting end, where the re-construction operations started,
three 30-inch water-mains run practically underneath the tramway
all the way from the terminus to Devonshire Road, a distance of
over 12 mile. As these pipes for a considerable length were
1 foot 6 inches to 2 feet 6 inches below the surface, it required some
manmuvring of the line to avoid diverting them. Before fixing
the position of the new line here, the position and depth of the
pipes found in thenumerous trial openings were carefully recorded
on a large-scale plan prepared from an actual survey. The lines
were then schemed out in thepositions where they were most likely
to avoid the water-pipes. I t wasnot, however, found possible
everywhere both to secure a good alignment of track and to avoid
the pipes ; and a scheme for raising the roadway a t several places
was submitted to the Wandsworth borough authorities and was
agreed to by them. This method of dealing with pipes was sub-
sequently followed a t a number of other places, and considerable
expense and delay to the works were thus avoided.
Wherc obstructions have been encountered running for a short
distance along the conduit-track at a depth of 2 feet to 2 feet G
inches, the difficulty has been overcome by using cantilever yokes
(Figs. 34, Plate 3). Elsewhere, obstructions met at the same range
of depth, but crossing the track at right anglesor nearly so, have
been avoided by altering the spacing of the yokes, so as to bring
the obstruction into the panel between them. I n such places an
inverted trough, for protecting the part of the pipe entering the
concreteconstruction,was fixed when required. The upper part
of the cantilever yoke is the same as the standard yoke so far as
the bearing surface of the slot-rail and the anchoring lugs for the
tie-barsare concerned. This allowed thestandardarrangement
of erecting the track- and slot-rails to be adhered to. One draw-
back to the use of the cantilever yokes is the delay that occurs in
fixing them i n position, the final erection and adjustment having
to wait until the track-rails are place
in ; and another disadvantage
is that less cont,rol of the slot-opening is obtained. Nevertheless,
they have been the means of effecting a considerable saving of
expenditure in pipe-diversions, and no bad eeects have resulted
from their use,
i7'3
Although pipes and other mains havebeen allowed to penetrate
the 6-inch concrete sill of the conduit, no sufficient reason arose
for allowing them inside the conduit; and in thepoint-mechanism
pits the linkwork has been designed so that no part crosses the
line of conduit above the sill-level. Bythisarrangement no
restrictions will be imposed on the operating department when
periodically cleaning out the conduit. For the scraper there will
be everywhere an available heightof 8 inches from the sill of the
conduit to the underside of the conductor-bars.
The lines and levels having been fixed provisionally, and all
the larger ascertained pipe-obstructions having been removed, the
work of laying the temporary track,necessaryforaccommodation
the
of theveryfrequent horse-car service during reconstruction,
proceeded. The daycar-service, lasting from 7 A.Y. to 1A.M., varies
considerably on different sections of the route. I n some parts a car
runs each way every minute,and in other parts the interval is only
4 minute.AtSt. George's Circus, wheremanylines converge,
five hundred cars per hour were run over one piece of temporary
track. Between the hours of 1 A.M. and 7 A.M. a small service was
maintained over the greater part of the line. The course usually
followed was to attack one line ata time, and to use the other line,
supplemented with long loops of temporary track laid alongside on
the surface of the street, for the car-service. Most of the loops or
double-lineportions were about 500 feet in length : the single-
line portions rarely extended to 400 feet. The car-service on the
temporary lines was regulated by signal-posts, with semaphore3
painted red and white by day, and red and clear lights at night.
The section of rail adopted for the temporary lines was of the
flat-bottomed typewith bevelled sides. On straightpartsat
intervals of 24 feet, and on curved parts at intervals of 12 feet,
flat steel tie-bars were spiked to the roadway, and kept the track
t o gauge. When laid in position, the rails were barely 2 inches
above the surface ; and, i n order to enable the ordinary vehicular
traffic to pass over them more easily, wedge-shaped wood and bark
werelaid along the sides of the rails! at short intervals. This form
of temporary line is easily laid, andoffers little obstruction totraffic;
and the infrequencyof accidents testifies t o its suitability.
The old permanentwayhad been laidat different periods
extending back t o 1869, and it varied somewhat i n character.
The condition of the old concrete bed also varied considerably.
The depth of the concrete bed ranged from 5 inches to 18 inches.
The old paving was chiefly of stone,grouted with cement. The
best of the old sets were redressed and used in the new work.
174. m ON ~mE L E ~ A ~ C ARECONSTRUCEION
L OF rninutea of
The first operation in breaking up the old permanent way was
to lift thepavinginthemargin of thetrackundergoing
reconstruction,cutouttheconcreteunderneath,anddigsmall
pookets a t intervals of 3 feet. Into these pockets Barrett
jacks, commonly calledpump ” jacks,wereplacedwiththeir
for sweeping a thin layer of cement mortar along the insideof the
tube. Theinsulator pit-frameswere then laid i n position on a
prepared bed of cement mortar, and the top of the frame, fixed in
position to the same camber as the paving, was allowed to project
inch above the plane of the rail. The paving in thecovers was
laid slightly higher, so that its surface might correspond with the
general paving, kept Q inch above the slot- and track-rails. After
the frames had been set, a layer of cement mortar was spread round
all the frame-edges and along the slot-rail flange, so as to seal u p
effectually any small hole where the concrete had fallen away.
The conductor-bar gang thencommenced their work. No curved
bars were allowed into the tube until they had first been checked by
laying them on the top of the slot-rail immediatelyover the place
where they were to be fixed. The bond-holes at the ends of the
conductor-bars, which were originally drilled at the rolling-mills to
a bare $-inch diameter, were then rimered out to a full 2 inch, and
the cylindricalsolid terminals of the bonds were inserted i n one end
of each conductor-bar. There the terminalswere expanded into the
holes by the hydraulicbond-compressors shown i n Figs. 35, capable
of exerting a pressure of 15 tons. Several conductor-bars weresawn
through theholes with the bonds in place, and the resultswere re-
markably good. The conductor-bars, having been thus prepared,
were introduced into the tube at openings every 200 yards, where
pieces of slot-rail 7 feet G inches long, i.e., spanning two bays, had
been left out, and were carried on hooks attached to small trolleys
running on the slot-rail (Figs. 35). The conveying arrangement
isvery simple. Eachtrolley-carriage consists of tworollers
the axles of which support two cross-bars. Between these, a holed
flat bar is suspended at any height, by inserting a pin through
it and the cross-bars. This bar hangs between the slot-rails, and
is hooked at its lower end, to carry the conductor-bars.
The conductor-bars having been brought into place at thecorrect
height, the work of fixing them to the special insulator-supports
then proceeded. Thiswas done byfixingthe cast-ironclips,
loosely threaded on the insulator-rod, on to the conductor-bar by
means of the tapered pin. The attachment to the insulated support
was then made by screwing on the bottom nut. The fixing of the
freeends of the bonds was done in the tube by means of the
hydraulic bond-compressors. The presswas insertedintothe
inspection-pits,and suspended from a standspanningthepit
(Figs. 35). Once in positionover a bond, the press was jammed
tightly inplace during the bonding-operation by means of a crank
and screw. Pressure was applied to the water in the cylinder by
Proceedings.] SOUTH LONDON TRAMWAYS. 177
Figs. 35.
COST, ETC.
APPENDIXES.
APPENDIX I.-SOUTH LONDON TRAMWAYS.
COSTOF ELECTRIC
CONIXJITCONSTRUCTIOS.
Total . . . . . i 2411,750
225,106
~~
This item includesZ7.500 for obstructions = S458 per mile of single line.
Temporary station only at houghborough Junction.
APPENDIX 11.-EDINBURGHCORPORATIONTRAMWAYS.
COSTOF CABLECONDUITCONSTRUCTION.
(Thc figures embrace the cost of all thelinesrecently constructed by thc
Corporation with the exception of the Mound and Lauriston routes, which
are worked from a depot built prior to the acquirement of the lines by the
Corporation.)
- i Total cost of
35 &lileR of
1'Mile
coat per
of Single
1 single Line. Line.
~
___
1. Permanent-wayconstruction,including
pavingandspecial work'
road-work,
. . . . . . .
1
'
505,100
J
2. Street
improvements and alterations* . . . 31,150
3. Cables . . . . . . . . . . . . . 7,750 221
--__--
. S192 000 1 544,000
4. Power-station, ear-sheds and plant- 15,542
Buildings . . . . . . . .
Plant . . . . . . . . . . 871800 279,800
. . . . ., . , 62,300
5. Cars (4' 1 per mile single line)
6. Supervision andincidentals .
Total
.
. . .
.
.
. . . . 35,000
. . . . 921,100
__-
1 1,760
1,000
~ 26,316
* This item includes .€16,753for obstructions = S478 per mile of singlc line.
2A considerable part of this sum wa8 ultimrrtely paidby the City as
representing permanent street improvements.
N 2
80uJTW L@lNDQRI T R A M W A V S P L A T F: Z .
ELKCTRICAL RECONSTRUCTION O N THE CONDUtT SYSTEM.
h A
SECTlOW A T YOKE.
PLAN OF SlNGLE T R A C K .
m.
/ E%? 3.
'y
E L E V A T I O N .
I
SLCTION ON A A . U
P L A N . SECTION Oy B E .
SECTION O F S L O T - R A I L
C O N D U I T Y O K E .
A .MILLAR
.
8 0 U T H L43NDORI T X A M W A V 8
ELKCTRICAL RECONSTRUCTION ON THE CONDUIT SYSTEM.
C PLATE :; .
. 4'. U." .
E L E V A T I O N .
ir71
SECTIONAL SIDE ELEVATtON.
11 A
C R 0 5 S S E C T I O N .
I 1
PLAN OF G U S S E T COST.
ENLARGED VIEW AT X .
l=<y.: .K2 I
P L A w .
LONGITUOINAL SECTtON OF STRAIGHT TRACK.
P L O U G CH ~ R R I E R
1 . L J
l l I
SECTION OH A A . SECTIONAL E L L V A T I O N ON A A .