X - Decision 27288-D01-2022 - Rattlesnake Ridge Wind Power Plant Time Extension - 000010
X - Decision 27288-D01-2022 - Rattlesnake Ridge Wind Power Plant Time Extension - 000010
Time extension
3. BHE stated that construction of the power plant commenced in 2020. Twenty-three of the
26 turbines have been assembled and 19 turbines are operational as of March 30, 2022. BHE
requested a new construction completion date of May 15, 2022. It stated that the time extension
request is due to turbine delivery delays because of supply chain disruptions.
4. BHE stated that all wildlife surveys remain current and will remain current until the
construction completion date.
5. BHE stated that it continues to engage with landowners for the duration of project
construction activities and has not received any landowner complaints related to construction
timing.
6. BHE stated that the Alberta Electric System Operator has been updated with the revised
construction completion date and has no concerns.
1
Power Plant Approval 26967-D02-2021, Proceeding 26967, Application 26967-A001, December 2, 2021.
Alberta Utilities Commission
April 21, 2022 Page 2 of 2
7. BHE has provided information respecting the need, nature and the duration of the
requested time extension. Based upon the information provided, BHE has demonstrated that the
requested time extension is of a minor nature.
8. The Commission approves a time extension to June 30, 2022, to complete construction of
the power plant.
10. The Commission may, no later than 60 days of the date of this decision and without
notice, correct typographical, spelling and calculation errors and other similar types of errors and
post the corrected decision on its website.
Wayne MacKenzie
Executive Director, Facilities Division
On behalf of the Alberta Utilities Commission