April 21, 2022 Decision 27288-D01-2022

BHE Canada Rattlesnake G.P. Inc.


Suite 3020, Bow Valley Square III
255 Fifth Avenue S.W.
Calgary, Alta. T2P 3G6

Attention: Darin Watson


Vice President, Engineering, Construction and Operations

Rattlesnake Ridge Wind Power Plant Time Extension


Proceeding 27288
Application 27288-A001

Time extension

1. BHE Canada Rattlesnake G.P. Inc. (BHE), by Application 27288-A001, registered


with the Alberta Utilities Commission on April 1, 2022, requested approval of a time extension
in order to complete construction of a 130-megawatt wind power plant, designated as the
Rattlesnake Ridge Wind Power Plant, located in the Whitla area.

2. The proposed work is related to facilities previously approved by the Commission in


Approval 26967-D02-2021, 1 where January 31, 2022, was stipulated as the completion date for
the project.

3. BHE stated that construction of the power plant commenced in 2020. Twenty-three of the
26 turbines have been assembled and 19 turbines are operational as of March 30, 2022. BHE
requested a new construction completion date of May 15, 2022. It stated that the time extension
request is due to turbine delivery delays because of supply chain disruptions.

4. BHE stated that all wildlife surveys remain current and will remain current until the
construction completion date.

5. BHE stated that it continues to engage with landowners for the duration of project
construction activities and has not received any landowner complaints related to construction
timing.

6. BHE stated that the Alberta Electric System Operator has been updated with the revised
construction completion date and has no concerns.

1
Power Plant Approval 26967-D02-2021, Proceeding 26967, Application 26967-A001, December 2, 2021.
Alberta Utilities Commission
April 21, 2022 Page 2 of 2

7. BHE has provided information respecting the need, nature and the duration of the
requested time extension. Based upon the information provided, BHE has demonstrated that the
requested time extension is of a minor nature.

8. The Commission approves a time extension to June 30, 2022, to complete construction of
the power plant.

9. Approval 27288-D02-2022 is attached.

10. The Commission may, no later than 60 days of the date of this decision and without
notice, correct typographical, spelling and calculation errors and other similar types of errors and
post the corrected decision on its website.

Alberta Utilities Commission

(original signed by)

Wayne MacKenzie
Executive Director, Facilities Division
On behalf of the Alberta Utilities Commission