Q 1 - Substitution enables to automatically change master data fields of Project Definitions, WBS
Elements, Network Headers and Activities?

A - True

B - False

Q 2 - Using Control key in SAP PS system, you can determine the business transactions to be
performed when you perform an activity?

A - True

B - False

Q 3 - In SAP PS system, a control key is identified by?

A - Two digit alphanumeric ID

B - Three digit alphanumeric ID

C - Four digit alphanumeric ID

D - None of the above

Q 4 - In SAP PS system, structure of NTW is similar to which of the following order type?
A - Network Order

B - Planned Order

C - Production Order

D - Maintenance Order

Q 5 - Access control list function should be activated in project profile or network profile?

A - True

B - False

Q 6 - Authorization can be assigned for following PS objects?

A - Project

B - Work Breakdown structure

C - Network

D - A and B

E - A, B and C

Q 7 - In SAP PS system, a write authorization allows you to?

A - Display PS Project & Change PS Project

B - Create PS Project

C - Delete PS Project

D - All of the above

Q 8 - Consider a user A is assigned to user group 1 that has read authorization for a PS object and
user has change authorization for PS object. The user gets?

A - Read Authorization

B - Change Authorization

C - Both of the above

Q 9 - Which of the following is used to define the pricing strategy in the system for costing and
how overhead is to be determined?

A - Finance Accounting and Controlling

B - Cost function

C - Costing variants
D - Costing Type

Q 10 - Which of the following is used to calculate current budget in SAP Project System?

A - Original Budget

B - Supplements (added)

C - Transfers (addition/subtraction)

D - Returns (Subtraction)

E - All of the above

Q 11 - Budget is defined as approved cost for a project and it is same as the cost plan?

A - True

B - False

Q 12 - Which of the following is an engine which is used to fill demand and supply gap of
material?

A - Plant Maintenance

B - Storage

C - MRP run

D - WBS

Q 13 - In SAP PS, which of the following project version is used to store different cost plans for a
project?

A - Project Versions

B - Plan Versions

C - Selection Versions

D - Simulation Versions

ANSWER SHEET

Question Number Answer Key

1 A

2 A
3 C

4 D

5 A

6 E

7 A

8 B

9 C

10 E

11 B

12 C

13 B