MEP LABOR PRODUCTION RATES

8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
PLUMBING & DRAINAGE Plumber Helper

1 Water Supply Pipes (PEX) LM


2 Water Supply Pipes (PRP) LM
3 Valves & Accessories of varying diameter No
4 Water Booster Pumpset No 2 1 1

5 Water Transfer Pumpset No


6 Water Treatment with Accessories No
7 Storage Tank No
8 Water Heater No 3 1 1

9 Water Meter No
10 Waste Water Drainage Pipes & Fittings below grade LM
11 Waste Water Drainage Pipes & Fittings above grade LM
12 Sump Pumpset No
13 Drains & Grating No
14 W/C - Asian No 2 1 1

15 W/C - Western No 3 1 1

16 Shower set No
17 Urinal No
18 MOP sink No
19 Bidet No 3 1 1

HVAC WORKS AC Technician Helper

1 Chilled water Piping LM 25 1 1

2 Chilled water Pipes Insulation with Canvase Cloth LM 20 1 1

3 Duct Work with Insulation m2 10 1 1

4 Fresh Air Handling Units (FAHU) Installation No 1 1 1

5 Fan Coil Units (FCU) Installation No 2 1 1

6 Exhaust Fan Installaion No 2 1 1

7 Dampers & Control No


8 Grills & Diffusers Installation No 8 1 1

9 Closed Control Units No


10 Chemical Dosing No
11 Chilled Water Pump No
12 BMS No

Marvin Fernandez-CE Page 1 of 2


ELECTRICAL WORKS Electrician Helper

1 Duct Laying LM 50 1 1

2 P.V.C Conduits Layings LM 200 1 1

3 G.I Conduits Layings LM 50 1 1

4 Cable Pulling ( 10 to 50 Sq mm ) LM 100 1 1

5 Cable Pulling ( 50 to 90 Sq mm ) LM 50 1 1

6 Cable Pulling ( 100 to 200 Sq mm ) LM 30 3 5

7 Cable Pulling ( 200 Sq mm and Above ) LM 30 3 5

8 Cable Trays (100mm-300mm ) i/c Support System LM 50 1 1

9 Cable Trays (300mm-600mm) i/c Support System LM 40 1 1

10 Cable Trays (600mm-900mm) i/c Support System LM 30 1 1

11 Wiring LM 300 1 1

12 Termination No 50 1 1

13 DB Installation No 2 1 1

14 MDB/SMDB Installation No 1 4 2

15 LV Panels Installation No
16 Motor Control Centres No
17 Sockets Installation No 80 1 1

18 Switches Installation No 80 1 1

19 Light Fixtures Installation No 50 1 1

20 Earthing System No
21 Generator set No
22 Main Cable Laying LM
22 CCTV System No
23 Telephone Equipment Installation No 5 1 1

FIRE FIGHTING & FIRE ALARM SYSTEM Fire Fighters Helper

1 Piping Network LM
2 Fire Hose Cabinets No
3 Fire Extinguishers and Cabinets No
4 Sprinklers No
5 Valves & Accessories No
6 Fire Protection Pumpset No
7 Fire gas Suppression System No
8 Fire Alarm Control Panel No
9 Smoke & Heat Detectors No
10 Monitor Module No
11 Control Module No
12 Voice Evacuation System No

Marvin Fernandez-CE Page 2 of 2