Professional Documents
Culture Documents
MANAGEMENT
Ramun Prasad†*
(Lecture No. - 41,42 & 43)
a
Recapitulate
ay
Learning Outcomes
After this session students will be able to:
1
Unit-07: Project Management Ramun Prasad
a
tion, so that the organization’s objectives and goals can be achieved within budget, on sched-
ule and at the desired performance/technology level, while adhering to the ever changing
environmental input factors, like legal, social, political, economical and technological.
ay
Project management can be defined as the planning, organizing, directing and controlling
of company resources for a relatively short-term objective that has been established to com-
plete specific goals and objectives.
A project is a temporary and one time endeavor undertaken to create a unique product or
service.
1. Organize and implement diverse and scattered activities to achieve time, cost and
performance goals.
2
Unit-07: Project Management Ramun Prasad
3. Organize for execution of the plan. He should show his commitment to this plan.
4. He should inculcate enthusiasm, team spirit, confidence and reputations for excel-
lence.
a
9. He should be an entrepreneur.
ay
Following are the important tools and techniques for effective project management.
3
Unit-07: Project Management Ramun Prasad
a
1.7 Phases/Stages of Project Management
ay
.G
.P
Source: https://researchadmin.asu.edu/themes/rtdoked/images/pmo-process.png
G
4
Unit-07: Project Management Ramun Prasad
• PERT, actually, developed as a research and development planning tool where activity
timings could not be estimated with enough certainty.
a
• PERT can be employed at those places where a project can not be easily defined in
terms of time or resources required.
ay
• PERT is mainly concerned with event and thus it is an event-oriented system.
• The basic tools used in PERT technique is the network or flow plan. Network consists
of series of related events and activities.
4. Using three times estimate, the expected time for each activity is calculated.
.P
7. Expected time, earliest starting time, and latest finishing times are marked on the
network diagram.
8. Slack is calculated.
G
11. Lastly, the probability that the project will finish at due date is calculated.
All activity arrows must begin and end with event nodes. It is shown in the following figure:
5
Unit-07: Project Management Ramun Prasad
a
ay
.G
Source:https://www.researchgate.net
• Unlike PERT, CPM developed in civilian business and engineering industry where
activity timings were relatively well known.
• CPM is applicable to both large and small projects, taking from space programmes to
wedding or horse shows. It is widely recognized and is the most versatile and potent
management planning technique.
• CPM is a technique, used for planning and controlling the most logical and economic
G
sequence of operations for accomplishing a project. The project is analyzed into dif-
ferent activities whose relationship, as in PERT, are shown on the network diagram.
The network is then utilized for optimising the use of resources, progress and control.
The CPM employs the following steps for accomplishing a project planning:
6
Unit-07: Project Management Ramun Prasad
9. Tabulate various times and marks Earliest Start Time (EST) and Latest Finished Time
(LFT) on the arrow diagram.
a
11. Identify the critical activities and mark the critical path on the arrow diagram.
ay
13. If it is intended to reduce the total project duration, crash the critical activities of the
network.
Source: http://www.pmknowledgecenter.com/
7
Unit-07: Project Management Ramun Prasad
a
2. Both techniques have different concept of working like CPM uses deterministic con-
cept for its work whereas probabilistic concept is used by PERT.
ay
3. Networking approach also varies in both techniques like CPM uses networking that
based upon activity oriented; on contrary PERT uses networking that based on event.
4. In PERT technique, an estimation of time for different activities is not perfect and
accurate whereas in CPM activities duration are estimated with the quality of accuracy.
.G
5. Both of the techniques used for same purpose but the nature of their working is dif-
ferent and some can do their work efficiently with CPM and some can do same with
PERT.
6. The most important thing to solute is to minimize time so that they can get good result
for their cost factor. In PERT, time is said to be a controlling factor.
7. CPM has one-time estimate while PERT has three time estimates.
.P
8. Unpredicted activities are managed with the help of Program Evaluation and Review
Technique (PERT), whereas CPM is used for dealing those projects that have some
alarmed activities. These two techniques said to be a key element for the management
of any project.
3 Concept of Break-Even-Analysis
G
The Break-Even-Analysis (BEA) is used to determine the level of operation at which a firm
makes no profit and incurs no loss. At this stage, its profit level is zero. This analysis will
enable an entrepreneur to ascertain this minimum production level so that he can meet all lia-
bilities without incurring a loss. Break-Even-Analysis (BEA) uses Fixed cost (FC), Variable
Cost (VC), Total Cost (TC) and Total Revenue (TR) curves to demonstrate the Break-Even-
Point.
Fixed Cost (FC): Fixed costs are those costs which do not vary with the level of output in
the short term. For Example: Rent, Office salaries, Advertising, Insurance, Depreciation,
etc.
Variable Cost (VC): A variable cost is that cost which varies with the level of production. It
directly related to the quantity of output. If output doubles, then the variable cost would dou-
ble. If output halved, the variable costs would halve. If output were zero, then no variable
8
Unit-07: Project Management Ramun Prasad
costs would be incurred. For Example: Direct labour Cost, Raw materials and components,
Packaging costs, Royalties, etc.
Total Cost (TC) = Fixed Costs + Variable Costs
a
ay
Source: https://images.app.goo.gl/m3HVoXfEdSmfMNvN8
Total Revenue (TR): Total Revenue in economics refers to the total receipts from sales
of a given quantity of goods or services. It is the total income of a business and is calculated
.G
by multiplying the quantity of goods sold by the price of the goods.
A break-even analysis is that point at where revenues equal expenses. It can be demonstrated
with help of following graph:
.P
G
9
Unit-07: Project Management Ramun Prasad
As given in the the above diagram, the break- even point is reached where TR equals TC
(TR=TC = BEP). Prior to this stage, the TC is above TR and the firm is making losses. It
starts earning profits after the break- even point.
Margin of Safety: In break-even analysis, the term margin of safety indicates the amount
of sales that are above the break-even point. In other words, Margin of safety shows how far
sales can fall before losses made.
a
2. It helps in production decision making.
3. BEA is an important tool for product pricing. Once BEP is known, the ex-factory
ay
price can be determined very easily. It also helps to decide whether or not to allow
any discount on bulk purchases, and if so, how much discount could be allowed.
4. Helps to make ‘Price or Buy’ decision: In case there is an increased demand for the
product, BEA helps in making correct decision whether to produce more to meet the
demand or buy the product from another unit and meet the demand.
.G
Sometimes buying the product from another unit may be cheaper than producing more
in the firm.
fixed and variable costs, which may not be possible every time.
2. For the multiple- product or joint- product operations, it is difficult to apply the break-
even analysis.
3. The computation of break- even point is based on the historical information. If this
information is not relevant, the analysis can not be applied usefully.
G
4 Conclusion
During this session, we have discussed about the introduction to Project Management, CPM
& PERT Techniques and the concept of Break-Even-Analysis and learned that : -
10
Unit-07: Project Management Ramun Prasad
• PERT & CPM are two of the most widely used techniques in project management. The
objectives of project management can be described in terms of a successful completion
of project on time within the budgeted cost and adhering to technical specifications
which satisfy the end users.
These techniques have been created out of the need of Western Industrial and Military
establishments to plan, schedule and control the complex projects. But now- a- days
it is extended to each and every areas of project management.
• The Break-Even-Analysis (BEA) is that analysis which used Fixed cost Variable Cost
to determine the level of operation at which a firm makes no profit and incurs no
loss. Further, BEA also helps an entrepreneur to take investment decision, production
a
decision, and product pricing decision.
ay
1. Explain the term ‘Project Management’.
12. What is Fixed Cost and Variable cost? Explain with the help of graph.
G
6 Glossary
Project: A project is an individual or collaborative enterprise that is carefully planned to
achieve a particular aim.
Activity: A clearly definable portion of a project that requires for its completion, the con-
sumption of resources and time in particular. (i.e. Activity is the actual performance of task.)
Critical Activity: An activity becomes critical, if delay in its estimated time duration delays
the whole project to that extent.
11
Unit-07: Project Management Ramun Prasad
Critical Path: The longest path through the network, consisting of critical activities. The
length of the critical path is the shortest time allowable for project completion.
Successor Event: It is the event or events that immediately follows another event.
Predecessor Event: It is the event which comes immediately before another event.
Earliest Expected Time: The earliest time that an event can occur is on the latest com-
a
pletion of an activity.
Slack: It is the difference between Latest Allowable Time (TL ) and Earliest Expected Time
ay
(TE ) i.e. slack = TL - TE .
Margin of Safety: This is shown on the chart by the distance between B.E.P. and Out-
put being produced. It shows that if this distance is short then a small decrease in output or
sales will reduce the profit greatly. If distance is long it means the business could still be
making profit after a great reduction in output.
.G
Sales at Full Capacity - Sales of B.E.P.
Margin of Safety = × 100
Sales at Full Capacity
Fixed Cost
Break-Even-Point =
Selling Price - Variable Cost Per Unit
References
.P
[1] Banga T.R. & Sharma S.C. (2015), Industrial Organization & Engineering Economics,
Khanna Publishers, New Delhi. (Chapter-28, 29 & 69)
[2] Khanna O. P. (1999) Industrial Engineering. & Management, Dhanpal Rai & Sons New
Delhi. (Chapter-10)
G
[4] G. Pratibha (2015) Production & Operation Management, Kataria & Sons, New Delhi.
(Chapter-18)
[6] Singh R. (2010), Principles of Engineering Economics & Management, Kataria & Sons,
New Delhi. (Chapter-19)
[7] (http://www.ignouhelp.in/ignou-study-material/)
[8] (https://www.manage.gov.in/studymaterial/PM.pdf)
12
Unit-07: Project Management Ramun Prasad
APPENDIX
I. Graphical representation of different types of costs:
a
ay
.G
.P
G
Source: https://images.app.goo.gl/aGJxtsAfZdJmt6t87
13
Unit-07: Project Management Ramun Prasad
a
ay
In this diagram, an increase in price has brought about a shift in the TR curve and has
preponed the break even point. The converse is true in case of a fall in the price of the
commodity.
.G
Self-Assessment Questionnaires (SAQ)
If a firm X in the example solved above finds a rise in price to Rs. 12 what will be its break-
even sales and if the price falls to Rs. 6, what will the break- even sales be?
2. Changes in fixed cost:
An increase in the fixed cost increases the break- even point while a fall in the fixed cost will
reduce the break- even point.
.P
G
14
Unit-07: Project Management Ramun Prasad
In this diagram, an increase in fixed cost has brought about a shift in the TC curve and has
increased the break even point. The converse is true in case of a fall in the fixed cost.
Self-Assessment Questionnaires (SAQ)
If a firm X in the example solved above finds a rise in the fixed cost to Rs. 7000 what will be
its break- even sales and if the fixed cost falls to Rs. 3000, what will the break- even sales
be?
3. Changes in variable cost per unit
An increase in the variable cost per unit increases the break- even point while a fall in the
variable cost will reduce the break- even point.
a
ay
.G
.P
G
In this diagram, an increase in variable cost has brought about a shift in the TC curve and
has increased the break even point. The converse is true in case of a fall in the variable cost.
Self-Assessment Questionnaires (SAQ)
If a firm X in the example solved above finds a rise in the variable cost per unit to Rs. 8
what will be its break- even sales and if the variable cost per unit falls to Rs. 3, what will
the break- even sales be?
15
Unit-07: Project Management Ramun Prasad
1. It determines the expected duration of activities and consequently of the the project
duration.
2. It helps the management in handling the uncertainties involved in the project and thus
reduces the risk element in the object.
4. It process for the right action, at the right point and the right times in the organization.
Disadvantages of PERT
a
1. The time estimates to perform activities constitutes a major limitation of this tech-
nique. If the estimates are not satisfactory then the network will be highly unrealistic.
ay
2. The probability distribution of total time is assured to be normal, which in real life
situation may not be true.
3. The simple PERT technique does not consider the resources required at various stages
of the project. If a certain resource may be used to perform more than one activity
and at the same time, it can be used for only one activity at a time, then the network
.G
diagram will become infeasible.
4. Use of this technique for active control of a project requires frequent updating and
revision of PERT calculations and this proves quite a costly affair.
Advantages of CPM
4. It identifies the most critical elements in the project. Thus, the management is kept
alert and prepared to pay due attention to the critical activities of the project.
G
Disadvantages of CPM
2. It operates on the assumption that there is a precise known time that each activity in
the project will take. It may not be true in reality.
3. It can not be used as a controlling device since any change introduced will change the
entire structure of the network. Thus, CPM can not be used as a dynamic controlling
device.
16