Professional Documents
Culture Documents
Agenda
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
5
Commercial Management in Construction Projects
6
Commercial Management in Construction Projects
Project
Employer/ Manager/ Contractor
Developer Engineer/
Consultants
Suppliers Specialists
Sub-Contractor
9
Commercial Management in Construction Projects
With Consultant
Estimating, Cost Planning, Budget Preparation, Risk Management, Value Management, Value Engineering,
Benchmarking, Life Cycle Costing, Procurement, Tender Evaluation, Change Control, Assessment of Variations /
Claims, Preparing Financial Statements, Cash Flow Forecasts, Cost Control, Reconciliations, Interim Valuations, Final
Account, etc.
With Client
Managing Budgets, Change Control, Preparation and Management of Tender / Procurement Process, Identification
and Management of Commercial Risks, Contract Administration, Cash Flow Forecasts, Payment Certification, Final
Account, etc.
COMMERCIAL MANAGEMENT IN CONTRACTOR’S ORGANISATION
12
Commercial Management in Construction Projects
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
15
Commercial Management in Construction Projects
Commercial Management in Construction Projects
www.aimsintlqs.com info@Aimsintlqs.com
COST CONTROL Cost in the
amount of
money spent for
obtaining goods
or services.
• Pre-Contract Cost Control is required to ensure that Contract Sum is within Client’s approved
Budget.
Contract Reference
Package name and reference
Budget associated with each contract / package
Contract Price
Instructed variations (agreed / not agreed)
Anticipated variations (forecast)
Claims / EOT
www.aimsintlqs.com info@Aimsintlqs.com
Project Financial Control and Reporting
What does a financial report look like?
Post-Contract Cost Control
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
www.aimsintlqs.com info@Aimsintlqs.com
EVA (Earned Value Analysis)
• Earned Value measures project progress in objective manner combing scope, cost and time.
• It compares planned progress and cost during a particular duration to that with actual progress and
cost incurred in the same duration.
• It gives a good indication of the project progress as compared to the planned enabling proper forecast
of eventual cost and time.
EV = Budget at Completion X Actual Progress
CV (Cost Variance) = EV (Earned Value) – AC (Actual Cost)
E.g. If a projects time for completion is 6 months and budget is AED 100,000/- and after 3 months its 50 % complete with
actual cost AED 60,000/- then EV is AED 50,000/- and CV is AED –(10,000/-).
CV SV CPI SPI
Schedule
Cost Performance
Cost Variance Schedule Variance Performance
Index
Index
EV – PV EV / PV
EV – AC EV / AC
Where: Where:
Where: Where:
EV = Earned Value EV = Earned Value
EV = Earned Value EV = Earned Value
PV = Planned PV = Planned
AC = Actual Cost AC = Actual Cost
Value Value
• EV – AC
CV (Cost Variance)
• Under Budget
Positive
• On Budget
Zero
EARNED VALUE FORMULAS
SV - Schedule • EV – PV
Variance
• Project Performance on
Zero
schedule
EARNED VALUE FORMULAS
• On Budget
Value= 1
EARNED VALUE FORMULAS
• Project Performance on
Value= 1
schedule
Commercial Management in Construction Projects
44
Commercial Management in Construction Projects
BROAD
PERSEPECTIVE
MARKET LATERAL
ANALYST THINKING
Special
abilities of
BEST
COMMUNI
Commercial ANALYSE
RISKS
-CATOR Manager
SELECTION OF
GOOD RIGHT
NEGOTIATOR PROCUREMENT
STRATEGIES
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
Alternative forms of construction procurement and payment mechanisms: Payment mechanism: The way
(mechanism) in which the contractor or subcontractor is paid for the work they undertake. These include the
following mechanisms:
•Target sum contracts: where a target sum (subject to contractual variations) is tendered
lump sum
and agreed for a contracting organisation to deliver a project. The target will usually be
built up in a similar way to the calculation of a fixed price in a lump sum contract. The final
target (including contractual variations) will then be compared with the actual costs
bill of
incurred by the contracting organisation. The difference (both overspend and savings,
quantities,
guaranteed usually known as ‘pain and gain’) will be split between the client and contracting
with or
maximum organisation, using calculations and proportions agreed in the contract.
without
price.
remeasureme
nt •Guaranteed maximum price (GMP) contracts: these are sometimes very similar to target
sum contracts, but with a contractual guaranteed maximum price agreed in the contract.
However, GMP can also exist as a variant to a lump sum arrangement, with limited
opportunities for the lump sum to be increased for change. The contractor will not be
entitled to any additional money should the GMP be exceeded, unless this is due to a
contractual variation, the opportunities for which will often be much lower than for any of
cost the alternatives above.
reimbursemen target sum
t
•Cost reimbursable contracts: where the contracting organisation is paid the actual costs
incurred in delivering the contract, plus an agreed (usually tendered) profit fee.
www.aimsintlqs.com info@Aimsintlqs.com
Commercial management of contracts
Commercial Candidates should have knowledge of all the main components as they represent the most common procedures used in the Knowing
management of industry.
contracts Level 1
Commercial Candidates should have experienced as many of the above components as possible, in relation to the contract(s) they have Doing
management of been involved with. Where they have not experienced a component they should have a strong theoretical knowledge of
contracts Level 2 the practical procedures involved.
For example:
A candidate might have carried out cost value reconciliation for part of their project but not all of it.
They will need to investigate how the remainder of the project is dealt with so that they have a thorough understanding of
this component.
They might only have experienced financial management of the supply chain, but they should still be aware of how cost
value reconciliation is carried out and its use in preparing monthly accounts at either project or business level.
Commercial Ideally candidates should have given advice on suitable commercial management procedures. They should be able to Advising
management of compare and contrast different techniques and their relevance to a given project.
contracts Level 3 If they have not had an opportunity to do this they should be able to demonstrate a depth of understanding of the
components listed above, sufficient to be able to give advice on a specific project.
5. Conclusion
www.aimsintlqs.com info@Aimsintlqs.com
Commercial Management in Construction Projects
51
Commercial Management in Construction Projects
52
Commercial Management in Construction Projects
53
Commercial Management in Construction Projects
Commercial Management in Construction Projects
Q
&
A
www.aimsintlqs.com © All Rights Reserved info@aimsintlqs.com