Soil Consolidation

Marmaray – City Train Station


Istanbul - Republic of Turkey

Project owner
City of Istanbul

Product
Colbonddrain CX 1000

Function
Soil Consolidation

Contractor
ALTERNATİF ZEMİN MEKANİĞİ

Project date
2014

Volume
500 000 lm

Marmaray suburban rail is an essential project for Solution


Istanbul, connecting Europe with Asia under the • Installing Colbonddrain CX 1000 vertical drain in a 1.2 m
Boshphorus and running in the heart of the city. It is raster with an average depth of 15 m to speed up soil
crucial to connect the city’s metro network over two consolidation
continents; in the future it will also connect the
After soil measurements and investigation had been
suburbs of Istanbul with the heart of the city. performed, the calculated 1.2 m installation raster and
average 15 m installation depth delivered the calculated
Challenge 0.9 m settlement in a 6 months time frame instead of
It is a real civil engineering challenge to shore up and years.
stabilize weaker soils in a short time frame to allow early
construction on them. Using Prefabricated Vertical Drains Benefits of the solution
(PVD’s) is a cost efficient solution to reach this goal and to Applying PVD’s as a solution not just allowed the
stabilize soft soils even in 30-40 m depths. contractor to dramatically reduce construction time, but
Applying PVD’s a path is formed for excess pore-water also delivered significant cost savings compared to other
created by the overburden. Water is drained off to the possible civil engineering solutions for stabilizing soft soils
surface resulting in a stable subgrade on which in such depths, like piling or even replacing the complete
construction can take place. soil.

www.enkasolutions.com
Colbonddrain CX1000 - at work

Installation machine installing Time benefit with Prefabricated Vertical Drain Forms path for excess pore-water created by the
Colbonddrain CX1000 overburden

Colbonddrain with its patented core and unique production Result


method of thermally bonding the filter at the entire surface Expensive and time consuming traditional methods with
makes a thoroughly tough and durable geocomposite with intensive truck and machinery demand could be replaced
excellent drainage capacities. by installing Colbonddrain CX1000. A stable sub-grade
Colbonddrain’s high tensile strength allows faster has been created for the railway superstructure in a short
construction and the thermally bonded filter provides a time, which will serve the millions of travellers in the
tear off free and thus safer installation. upcoming decades.

Installation benefits
Colbonddrain is easy to handle with a roll length of 280 m
and is suitable for use in all soil types.
Its unique production method and its high tensile strength
allows usage with all installation rig types.

Products used

Colbonddrain CX1000
Prefabricated Vertical Drain (PVD) geocomposite
for soil consolidation

China +86 519 6858 5555 Hungary +36 23 610 870 Disclaimer
The information set forth in this brochure reflects our best knowledge at the time of publication. We have a policy of continuous
France +33 1 74 90 00 13 Netherlands +31 85 744 1300 development and therefore our products, information and specifications may be subject to change. We therefore advise you to
Germany +49 6022 812020 USA +1 800 365 7391 contact us to make sure the information you receive is accurate and actual. We do not accept any liability arising from the
application of these products, the results thereof or the information given in this document. © 2018 Low & Bonar

www.enkasolutions.com | info@enkasolutions.com

You might also like