Professional Documents
Culture Documents
SAFETY WARNING
Only qualified personnel should install and service the equipment. The installation, starting up, and servicing of
heating, ventilating, and air-conditioning equipment can be hazardous and requires specific knowledge and training.
Improperly installed, adjusted or altered equipment by an unqualified person could result in death or serious injury.
When working on the equipment, observe all precautions in the literature and on the tags, stickers, and labels that are
attached to the equipment.
WARNING
Follow EHS Policies!
Failure to follow instructions below could result in
death or serious injury.
• All Trane personnel must follow the company’s
Environmental, Health and Safety (EHS) policies
when performing work such as hot work, electrical,
fall protection, lockout/tagout, refrigerant handling,
etc. Where local regulations are more stringent than
these policies, those regulations supersede these
policies.
• Non-Trane personnel should always follow local
regulations.
Copyright
This document and the information in it are the property of
Trane, and may not be used or reproduced in whole or in
part without written permission. Trane reserves the right
to revise this publication at any time, and to make changes
to its content without obligation to notify any person of
such revision or change.
Trademarks
All trademarks referenced in this document are the
trademarks of their respective owners.
AC-PRB001B-EN 3
Table of Contents
Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
General Information . . . . . . . . . . . . . . . . . . . 5
Case 1
Two Chillers Side by Side . . . . . . . . . . . . . . . 6
Case 2
Two Chillers End to End . . . . . . . . . . . . . . . . 6
Case 3
Three or More Chillers Side by Side . . . . . . 6
Recommended Installation
of Multiple Chillers . . . . . . . . . . . . . . . . . . . . . 6
Special Installations . . . . . . . . . . . . . . . . . . . . 6
Case 4
Restricted Airflow on One Side . . . . . . . . . . 7
Case 5
Decorative Walls on All Sides . . . . . . . . . . . 9
Case 6
Pits or Solid Walls Surrounding Unit . . . . 10
Recommended Installation
Walls/Obstructions . . . . . . . . . . . . . . . . . . . . 11
Performance Decrease From External Static
Pressure . . . . . . . . . . . . . . . . . . . . . . . . . . 12
4 AC-PRB001B-EN
Scope
This engineering bulletin covers application of the air- performance degradation if minimum service clearance is
cooled Ascend™ ACR and Sintesis™ chillers in close provided.
spacing and restricted airflow situations.
Figure 2. Air redistribution with a wall restricting the
air flow
General Information
Air-cooled chillers are frequently applied in situations
where close spacing of multiple chillers is required. They Airflow
are also applied in situations that result in restricted
airflow due to walls and other obstructions. The air-cooled
Ascend™ or Sintesis™ chiller offers an advantage over
competitive equipment in many of these situations.
Performance is minimally affected in many restricted Open
Area
airflow situations due to its unique condensing coil
geometry. Also, through its advanced Adaptive Control™ Airflow
microprocessor logic, the chiller will attempt to stay on-
line whereas competitors’ chillers may shut down.
Adaptive Control microprocessor logic describes the
ability of the control system to understand the operating Wall or Air freely enters and
environment of the chiller and adapt to it by first distributes to inner coils
Other
optimizing its performance and second, attempting to stay
Obstruction
on-line through abnormal conditions. For example, high
ambient temperatures combined with a restricted airflow The remainder of this engineering bulletin describes
situation will generally not cause unit shutdown. various commonly encountered close spacing and
Competitor’s chillers would typically shut down on high restricted airflow installations. The performance changes
pressure cutout in these conditions. are in terms of % Capacity (Tons) reduction and %
The chiller has 3 coil configurations that minimize Compressor Power (kW) increase at full load. Adjust the
performance effects in close spacing and restricted airflow performance given in the catalog or selection program
situations. using performance adjustment factors taken from the
graphs. For example, assume that a chiller selection is
Figure 1. Air flow made that gives a catalog capacity of 180 tons at 195 kW
(compressor power). Because of the actual installed
conditions, one of the cases given in this engineering
bulletin applies. A 1% capacity reduction and a 2% power
increase is taken from the graphs for that case. The
adjusted performance would be:
Adjusted Capacity= (1 - .01) x 180 tons= 178.2 tons
Adjusted Compressor Power = (1 + .02) x 195 kW = 198.9
kW
Increases in power required may limit the maximum
Airflow ambient the unit is capable of.
Airflow
In complicated installations, some uncertainty may exist
relative to performance and control. Remember, Trane’s
unique Adaptive Control™ microprocessor logic will make
as much chilled water as possible, given the actual
installation, and avoid nuisance high pressure cutouts.
Consult with Product Support for any unusual applications
not covered by this bulletin.
AC-PRB001B-EN 5
Scope
Case 1 Case 3
Two Chillers Side by Side Three or More Chillers Side by
The most common case is that of two chillers located side Side
by side as shown in Figure 3. Minimum recommended
service clearance between units (D) is 7’. Note: For optimum performance, this configuration is not
recommended. See following section.
Figure 3. Two chiller side by side See Figure 5. Minimum recommended service clearance
between units (D) is 7’. The performance effect of Chillers
A and C (outside units) is given in Case 1. When distance
D is 7’, the performance effect on Chiller B (center unit) due
to close spacing is 3% capacity reduction and 5% power
D
increase.The performance degradation of the center unit
is due to recirculated air, which is unavoidable. Unlike the
outside units, both sides of the center unit will see
recirculated air.
.
Case 2
Two Chillers End to End Recommended Installation
Two chillers may be installed end to end in various ways as
of Multiple Chillers
shown in Figure 4. Consideration of the performance effects shown in Cases
1 through 3 lead to the conclusion that locating multiple
Figure 4. Two chillers installed end to end
chillers side by side does not yield optimum performance.
Rather, the installation shown in Figure 6 produces
optimum performance of closely-spaced multiple chillers.
Control
Control
Panel
Panel
Panel
8’
Panel
min
6 AC-PRB001B-EN
Scope
Wall or D
Building
Structure
0.9
0.8
0.7
d=6 ft
% Capacity Reduction
0.6 d=4 ft
d=2 ft
0.5
0.4
0.3
0.2
0.1
0
0 5 10 15 20 25 30
AC-PRB001B-EN 7
Scope
2.5
d=6 ft
d=4 ft
1.5
% Power Increase
d=2 ft
0.5
0
0 5 10 15 20 25 30
8 AC-PRB001B-EN
Scope
6
d - Distance from Wall to Unit - feet
0
0 5 10 15 20 25 30 35 40 45 50
AC-PRB001B-EN 9
Scope
D D
D
H
14
12
Distance to Pit Walls
% Capacity Reduction
4 feet
10
6 feet
8 feet
8
0
0 2 4 6 8 10 12 14
Depth of Pit/Wall (feet)
10 AC-PRB001B-EN
Scope
14
Distance to Pit Walls
4 feet
12 6 feet
8 feet
10
% Power Increase
0
0 2 4 6 8 10 12 14
Depth of Pit/Wall (feet)
8’ min
Recommended installation
AC-PRB001B-EN 11
Scope
1.8
1.6
300 Ton
1.4
% Capacity Reduction
1.2
0.8
0.6
0.4
0.2
0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35
-H2
External static pressure, in-H2O
12 AC-PRB001B-EN
Scope
300 Ton
4
% Power Increase
0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35
300 Ton
5
% EER Decrease
0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35
AC-PRB001B-EN 13
Trane - by Trane Technologies (NYSE: TT), a global climate innovator - creates comfortable, energy
efficient indoor environments for commercial and residential applications. For more information,
please visit trane.com or tranetechnologies.com.
Trane has a policy of continuous product and product data improvement and reserves the right to change design and specifications without
notice. We are committed to using environmentally conscious print practices.