You are on page 1of 3

Weekly Report for CIDATA FWA Project

Week12
Date: 2023/11/20-2023/11/24

The Progress of Week12


 eNB installation:9 sites installation is finished,7 sites is online

now.

 BOSS business user cases test: done.

 EPC2 installation: physical installation is done.

EPC server configuration:

 2nd rack installation: rack installation is done, waiting for the

power cable.

Switch configuration:

 The switch in each site and router transmission site: waiting for

the PO.

RAN OAM: monitor room is ok.

BOSS test:

 Use Case: bundle test is pass.

 Selfcare app: waiting for the app store account and app website

domain info from CIDATA.


IPLOOK NETWORKS (HONG KONG) CO., LIMITED
RM 1003,10/F TOWER 1 LIPPO CTR 89 QUEENSWAY ADMIRALTY HONG KONG ,
 Waiting for the commercial bundle from CIDATA.

SIM card:

 SIM card info and APN: received.

 Waiting for the logo information feedback.

CPE:

 Waiting for the CPE design feedback.

Training:

 RAN OMC training: finish.

 EPC OMC training: Ongoing.

 BOSS training: training video has shared.

eNB Delivery:

 Start the delivery next week.

The Plan of Next Week13:

 Rack2 installation in MainOne database.

 Next 8 sites installation.

 BOSS test and training.

 EPC OMC training.

IPLOOK NETWORKS (HONG KONG) CO., LIMITED


RM 1003,10/F TOWER 1 LIPPO CTR 89 QUEENSWAY ADMIRALTY HONG KONG ,
 New 12 sets eNB delivery.

IPLOOK NETWORKS (HONG KONG) CO., LIMITED


RM 1003,10/F TOWER 1 LIPPO CTR 89 QUEENSWAY ADMIRALTY HONG KONG ,