No Uraian pekerjaan Volume Satuan Harga satuan Harga

I PEK. PERSIAPAN
1 Sakelar tunggal 22 IDR 15,000 IDR 330,000
2 MCB 2 IDR 20,000 IDR 40,000
3 Stop kontak 8 IDR 15,000 IDR 120,000
4 KWH meter 1,300 VA IDR 1,486,000 IDR 1,486,000
5 Sekering 1 IDR 24,000 IDR 24,000
6 Kabel NYA 2 1,5mm x 50m IDR 89,000 IDR 178,000
7 Lampu 41 12 watt IDR 70,000 IDR 2,870,000
9 Fitting 41 IDR 7,000 IDR 287,000
10 Pipa conduit 11 20mm x 3m IDR 15,000 IDR 165,000
TOTAL IDR 1,741,000 IDR 5,500,000
BOBOT DURASI Hari ke-
1 2 3 4 5 6 7
6.00% 5 1.20% 1.20% 1.20% 1.20% 1.20%
0.73% 1 0.73%
2.18% 1 2.18%
27.02% 5 5.40% 5.40% 5.40% 5.40% 5.40%
0.44% 1 0.44%
3.24% 4 0.81% 0.81% 0.81% 0.81%
52.18% 7 7.45% 7.45% 7.45% 7.45% 7.45% 7.45% 7.45%
5.22% 1 5.22%
3.00% 2 1.50% 1.50%
100.00% 10.19% 13.15% 16.80% 14.87% 14.06% 12.86% 18.08%
KUMULATIF 10.19% 23.34% 40.14% 55.01% 69.07% 81.92% 100.00%
AKTUAL 4% 10% 21% 30% 21% 13% 1%
KUM. AKTUAL 4% 14% 35% 65% 86% 99% 100%