Professional Documents
Culture Documents
Dr. Zee
The critical path is the longest sequence of activities in a project that must be completed
on time to ensure the project's overall timeline is met. It is determined by analyzing the
interdependencies of all the project activities and identifying which ones are sequential and
which can occur in parallel. By performing calculations, we can determine the early start and
finish times, as well as the late start and finish times for each activity, based on their
dependencies and durations. This information can be used to identify the critical path and
calculate the total duration of the project. If any activity on the critical path is delayed, the entire
While an inspection or visual inspection may help identify some of the project's
activities, it is difficult to determine the critical path by inspection alone. This is because a visual
inspection only provides information about the current state of the project and may not provide a
complete picture of the project's interdependencies. Moreover, visual inspection may not identify
hidden dependencies that can affect the critical path. Thus, it may not reveal the specific path
that is critical to completing the project on time. In order to make the clarification to these points,
we may take a review to the following list of daily activities routine, which is depicted in Table
1:
Table 1
F Brush teeth D 3
G Commute to work E, F 30
This is a simple list of activities that one might perform in the morning before commuting
to work. The activities are arranged in a sequence with the duration of each activity given in
minutes. The first activity is to (A) wake up, which takes 5 minutes, followed by (B) getting out
of bed which takes 2 minutes and is preceded by waking up. The next activity is to (C) take a
shower, which takes 15 minutes and is preceded by getting out of bed. Then comes the activity
of (D) getting dressed, which takes 10 minutes and is preceded by taking a shower. (E) Eating
breakfast is the next activity and takes 20 minutes and is preceded by getting dressed. (F)
Brushing teeth takes 3 minutes and is done after getting dressed. Finally, (G) the commute to
work takes 30 minutes and is preceded by eating breakfast and brushing teeth.
There may be hidden dependencies between activities that can affect the critical path but
are not immediately obvious through inspection. For example, in the daily routine activities
example, while "brush teeth" and "get dressed" may seem like independent activities, they are
actually dependent on each other as they both precede "commute to work". Without
understanding this hidden dependency, it would be difficult to accurately identify the critical
path for completing the routine in the shortest time possible. So, if we were only relying on
inspection to identify the critical path, we might overlook this hidden dependency and end up
with an inaccurate critical path. This could lead to delays or missed deadlines for the project.
critical path through techniques like the forward and backward pass, can provide a more accurate
picture of the interdependencies between the activities and help to identify the critical path. For
4
example, in the daily activity routine, creating a network diagram and performing calculations
can help to identify the critical path as (A) Wake up → (B) Get out of bed → (C) Shower → (D)
Get dressed → (E) Eat breakfast → (G) Commute to work. As the result, the total duration for
the critical path in the daily activity routine is 82 minutes. This is the sum of the duration of each
Total duration = 5 minutes (Wake up) + 2 minutes (Get out of bed) + 15 minutes
work) = 82 minutes
This duration is a must required to be completed on time in order to ensure the project
Overall, while an inspection may provide some useful information about a project's
progress, it is not sufficient to accurately determine the critical path. Calculations that take into
account the dependencies and durations of all activities in the project are necessary for an