Professional Documents
Culture Documents
P2-Periodical Exam
DIRECTION: Read each question carefully. For problem solving questions, show your
complete solution or the calculator method if any. For concepts/principles, choose the correct
answer. For solutions make sure that your final answer is rounded off in three-decimal places.
Write your answers and solutions in your test booklet and in your answer sheet shade the letter
that corresponds to your answer. Erasure in your answer sheet is STRICTLY NOT
ALLOWED.
9. Determine the ratio of the equivalent coefficient of permeability to the equivalent vertical
coefficient of permeability for flow through the sides of the canal.
a. 3.056
b. 2.556
c. 2.056
d. 1.556
10. Determine the equivalent hydraulic conductivity below the bottom of the canal.
a.
b.
c.
d.
11. Determine the flow rate at the bottom of the canal if the area of the canal is 1000 square
meters.
a.
b.
c.
d.
Situation 2 (12-14): For a field compaction test conducted in construction area of a hospital
gives the following field results:
CIE 047: Geotechnical Engineering I
P2-Periodical Exam
b.
c.
d.
17. Determine the Relative Compaction of the sample.
a. 86.726%
b. 88.247%
c. 90.245%
d. 92.147%
Situation 4 (18-20): For the given soil sample the following data were obtained, if the soil
sample datum is below 1.20 m from the soil samples. Consider the volume collected is 1,000
cubic meters every 220 seconds, the distance between points A and B = 1100 cm, between A and
C=1925 cm. Consider a soil specimen area of 100 square meters.
SOIL CONSTANTS POINT A POINT B POINT C
Velocity 2.35 m/s 3.24 m/s 4.18 m/s
Soil Pressure 63.50 KN/M^2 57.25 KN/M^2 46.70 KN/M^2
Elevation 3.50 m 4.20 m 5.50 m
Situation 6 (23-24): A proposed embankment fill requires 10,000 cubic meters of compacted
soil. The void ratio of the compacted fill is 0.65. Four borrow pits are available in the table
described below:
A 0.87 325.00
B 0.75 210.50
C 1.20 175.50
D 1.15 185.00
23. Determine which among four borrow pits will require the most amount of borrow.
a. Borrow Pit A
b. Borrow Pit B
c. Borrow Pit C
d. Borrow Pit D
24. Determine which borrow pit will cost the least among the four borrow pits.
a. Borrow Pit A
b. Borrow Pit B
c. Borrow Pit C
d. Borrow Pit D
Situation 7 (25-27): The moist unit weights and degrees of saturation of a soil are given in the
following table:
S (%)
105.73 50
112.67 75
d. 12.30%
Situation 9 (31-33): A liquid limit test conducted on a soil sample in the cup device gave the
following results:
Number of 10 19 23 27 40
Blows, N
Situation 10 (37-39): A 300 mm diameter well penetrates 27 meters below the static water table.
After 24 hours of pumping at a constant rate of 69 liters per second, the water table in two
observation wells located 35 m and 95 m from the well showed drawdowns of 1.1 meter and 0.5
meter, respectively.
Situation 11 (40-42): A confined aquifer as shown in the figure below has a source of recharge
located at the top. The hydraulic conductivity of the aquifer is 40 m/day with porosity of 25%.
The piezometric (head) surface in the two observation wells 1325 m apart are elevation 65 m and
60 m, respectively from common datum. The aquifer has an average thickness of 25 m and an
average width of 4 km.
CIE 047: Geotechnical Engineering I
P2-Periodical Exam
40. Determine the nearest value to the rate of flow through the aquifer, in cubic meters per
day
a. 13210
b. 16980
c. 11320
d. 15090
41. Determine the nearest value to the seepage velocity, in m/day
a. 0.528
b. 0.453
c. 0.679
d. 0.604
42. Determine the nearest value to the time of travel from the head of aquifer to a point 4km
downstream, in days
a. 7570
b. 8830
c. 6625
d. 5890
Situation 12 (43-45): The coefficient of permeability below a dam is 4 m/day. The water on the
upstream side is 30 meters higher than on the downstream side. To estimate the seepage below
the dam a flow net was graphically drawn such that the number of potential drops Nd = 10 and
the number of flow channels Nf = 4. The base of the dam is found 1 m below the ground.
Between the heel and the toe of the dam, a distance of 30 meters.
43. Evaluate the seepage flow per meter width of dam, in liters/min
a. 18.6
b. 33.3
c. 20.6
d. 32.5
44. Determine the uplift pressure at the heel of the dam, in kPa
a. 114
b. 265
c. 198
d. 181
45. Determine the uplift force, in kN per meter, per meter length of dam
a. 4415
b. 5615
c. 3974
d. 442
46. A quantity of seepage in each flow channel of a flow net is
a. Dependent of size of field
b. Dependent of potential drop
c. The same
d. Dependent on the number of flow channels
47. Drop in head between adjacent equipotential line is
a. Dependent of up-stream head
b. Dependent of down-stream head
c. Dependent of number of equipotential lines
d. The same
48. Identify the incorrect flow net property.
a. Flow lines and equipotential lines intersect or meet orthogonally.
CIE 047: Geotechnical Engineering I
P2-Periodical Exam
=====================================================================
“Kung BIBO ka ngayon, dapat mas BIBO ka bukas.”
Prepared by:
Engr. John Paul R. Tumangan
Engr. Neal Joseph V. Maniego