1)Definition of Carbon steel according to NACE MR 0175.

 Alloy of carbon and iron containing up to 2% & manganese up 1.65


 Alloy of carbon and iron containing up to 3% & manganese up 1.65

carbon steel
alloy of carbon and iron containing up to carbon and up to manganese and residual quantities of other
elements, except those intentionally added in specific quantities for deoxidation (usually silicon and/or
aluminum)
Carbon steels used in the petroleum industry usually contain less than 0,8% carbon.

2)For HIC testing how much H2S gas purity required.

 99.9
 99.5
 99.2
 99.4

3)Definition of the lethal fluids. As per ASME SEC 8 DIV 1

 vessel is to contain fluids of such a nature that a very small amount mixed or unmixed with air is
dangerous to life when inhaled,

 Vessel fill with the high-pressure fluid if it breaks it will affect the human life.

4)Question is based on below topic NACE MR 0175 PART 3


CRAs (corrosion-resistant alloys) and other alloys selected using this part of NACE
MR0175/ISO 15156 are resistant to cracking in defined H2S-containing environments in oil and gas
production but not necessarily immune to cracking under all service conditions. It is the equipment
user's responsibility to select the CRAs and other alloys suitable for the intended service

 True and False

5)Tack welds used to secure alignment shall either be removed completely when they have served their
purpose, before completing weld.

 True /False

6)If the vessel is design according to ASME DIV 1 may be stamp ? U? Designated stamp may not
required to apply

 True /False
7) Welder qualification expiration baseed on

 If the welder did not perform weld process more than 6 month
 If the welder is sick and not done welding more than 6 month
 When there is a specific reason to question the welder's ability to make welds that meet the
specification

All of above

8)Lethal service as per SAMSS


 Concentration of H2S more than 20%
 Concentration of H2s less than 20%
 Concentration of H2s less than 30%

9) tolerance of nozzle Height from base line to top nozzle face

10)What is manual welding

 .welding with equipment that has controls that can be adjusted by the welding operator, or
adjusted direction, in response to changes in the welding conditions.

 welding wherein the entire welding operation is performed and controlled by hand.

11)Machin welding & automatic welding is essential variable for welding operator

Ture/False

12) Inspection code covers the in-service inspection, repair, alteration, and rerating activities for
pressure vessels

 API 510
 API 653
 API 620
 API 650

13) a pneumatic test may be used in lieu of the standard hydrostatic test

 As per the instruction of manufacturer


 As per the instruction of manufacturer inspector
 As per the instruction of client inspector
 Vessel are so designed and/or supported that they cannot safely be filled with water; vessel
not readily dried, that are to be used in services where traces of the testing liquid cannot be
tolerated and the parts of which have, where possible, been previously tested by hydrostatic
pressure to the pressure required in UG-99.

14) Pressure retaining component shall not be closer than from adjacent edge of any other weld

 25
 50
 100
 75

15)Macro testion specimen for perpormance quaifcation

 The cut end of one of the end plate sections, approximately 1 in. (25 mm) long, in Figure QW-
462.4(b) or the cut end of one of the pipe quarter sections in Figure QW-462.4(c), as applicable,
shall be smoothed and etched with a suitable etchant (see QW-470) to give a clear definition of
the weld metal and heat-affected zone. In order to pass the test
 The cut end of one of the end plate sections, approximately 2 in. (50 mm) long, in Figure QW-
462.4(b) or the cut end of one of the pipe quarter sections in Figure QW-462.4(c), as applicable,
shall be smoothed and etched with a suitable etchant (see QW-470) to give a clear definition of
the weld metal and heat-affected zone. In order to pass the test
 The cut end of one of the end plate sections, approximately 4 in. (100 mm) long, in Figure QW-
462.4(b) or the cut end of one of the pipe quarter sections in Figure QW-462.4(c), as applicable,
shall be smoothed and etched with a suitable etchant (see QW-470) to give a clear definition of
the weld metal and heat-affected zone. In order to pass the test
 The cut end of one of the end plate sections, approximately 3 in. (75 mm) long, in Figure QW-
462.4(b) or the cut end of one of the pipe quarter sections in Figure QW-462.4(c), as applicable,
shall be smoothed and etched with a suitable etchant (see QW-470) to give a clear definition of
the weld metal and heat-affected zone. In order to pass the test

16)HIC testing perform according to which standard

 NACE TM0284
 NACE TM0248
 NACE TM0208

17) What is the bottom head insulation nut distance

 200
 300
 400
 350
18)Vessel manufacturer shall prepare as built drawings, which indicate thickness of the vessel shell
section, heads, and nozzles. An adequate number of readings shall be taken to represent the actual
thickness of the components by using which method

 UT
 RT
 ET
 MT

19)As per UW 3 joint category definition and type of joint category .


 The term “Category” as used herein defines the location of a joint in a vessel, but not the
type of joint. Category A,B,C,D

 The term “Category” as used herein defines the location of a joint in a vessel, but not the
type of joint. Category WA,WB,WCW,D
 The term “Category” as used herein defines the location of a joint in a vessel, but not the
type of joint. Type joint 1,2,3,4

20) Shell to nozzle weld joint category

 A,
 B
 C
 D

21) If vessel made by two different P no material then heating temp base on

 Thickness of thin member


 Higher Heating temperature of base
 Lower heating temp of base metal
 Or not required

22) If the vessel made by 1.25% Cr exceeding material PWHT required

 True /False

23)What is the reference standard for SSC

 NACE MR0175 & ISO 15156

24)Hydro test pressure for ASME Sec VIII Div.1


 1.3 MAWP with minimum stress ration ratio
 1.25 MAWP minimum stress ration
 1.1 MAWP minimum stress ration
 1.3MAWP

25) RT requirement for Joint Efficiency .70 of Category B

 Full
 Spot
 None
 None of the above

26)What is the minimum project of less than 6” NPS Nozzle?


 6 inches
 8 inches
 2 inches
 None of the above
27) Minimum joint efficiency for RT

 100%
 85%
 50%