Professional Documents
Culture Documents
1.0 Introduction
2.0 Scope
3.0 Definitions and types of Boilers
3.1 Definition
3.2 Types of Boilers
4.0 Inspection Role
5.0 Inspection Tools
6.0 Inspection of Boiler During Fabrication
7.0 Check list for Inspection of Boilers
Prior to Erection and Commissioning
7.1 Check list
7.2 Other Specific Requirements
7.2.1 Stream Drum
7.2.2 Economiser, Super Heater and Air Heater
7.3 Precommissioning Activities
8.0 Likely Location of Metal Wastage
8.1 Stream Drum
8.2 Combustion Chamber
8.3 Economiser
8.4 Super heater
8.5 Air-Preheater
8.6 Windbox and Air Duct
8.7 Blowdown Piping/soot Blower Piping
8.8 Expansion Bellows
8.8.1 Co Boiler Duct
8.8.2 Air duct Bellows
8.9 Boiler Feed Pipe Corrosion
9.0 Frequency of Inspection
9.1 On-Stream Inspection
9.2 Shutdown Inspection
10.0 Inspection Procedures
10.1 On-Stream(Water Tube Boilers)
10.1.1 Flame Condition
10.1.2 Excess Air
10.1.3 Condition of Refractory
10.1.4 Leaks
10.1.5 Hot Spots
10.1.6 Ladders, Stairways and Platforms
10.1.7 Boiler Feed
10.2 On-Stream (Fire Tube Boilers)
10.3 Inspection During Shutdown
10.3.1 External Inspection (Water Tube Boilers)
10.3.2 Internal Inspection
10.4 Internal Inspection (Fire Tube Boilers)
11.0 Waste Heat Boilers
12.0 Co-Boilers
13.0 Inspection During Repairs and Replacement
13.1 Repair/Replacement of Economiser
SECTION PAGE NO.
13.2 Drums
14.0 Record and documentation
15.0 References
Annexure I
(Weekly routine Boiler Inspection Report)
Annexure II
(Useful tests for the control of water for Boilers)
INSPECTION OF BOILERS
iii) That the drum is free to expand in all Air and gas tightness tests can be
the required directions. carried out by running the forced draft fan
and maintaining a pressure of 50 mm in
iv) That the water level gauge and water the ducting under test. Leaky portion shall
level instruments connections have be rectified and test shall be repeated to
been installed as per approved ensure satisfactory leak tightness of the
drawings. system.
iv) Thickness wherever possible. A viii) The upper half portion of drum(in
sample of tube if accessible should be steam space)shall be inspected
taken from economiser coils after 10 carefully for sign of oil or similar
years and subsequently after 5 years deposits and cause shall be
and split into two halves for assessing investigated.
the extent of internal pitting/
deterioration. ix) Drum internals, such as internal feed
pipes, steam separators, dry pipes,
External cleanliness of economiser blowdown pipes, deflector plates,
tubes shall be checked. steam scrubber and its clamps shall
be inspected for tightness, soundness
Economiser hopper shall be inspected and structural stability. Vigorous
for erosion and corrosion. turbulence of steam and water present
in drum can vibrate such parts and
welds may crack.
c) Drums, Drum connections and its
internals: x) The sodium hexametaphosphate pipe
and its distributor piping shall be
i) All the internal parts like steam inspected for scaling, pitting or
scrubber, cyclone, separators etc. chockage of holes with sludge.
shall be removed and boiler drum shall
be visually inspected before and after xi) Fibroscope should be used while
cleaning. inspecting the internal condition of
tube connected to drum for
ii) Nature of scale and type of pitting erosion/corrosion and deposits, if any.
beneath the scale or any deterioration
shall be noted. xii) Thickness survey of the drum shell
and its heads shall be carried out with
iii) All the nozzles, like safety valves, help of ultrasonic thickness
emergency blowdown, gauge glass measurement instrument.
connections and especially the lower
connections shall be inspected for xiii) Thickness should be taken adjacent to
accumulation of sludge or foreign all the longitudinal and circumferential
material. Edge thinning or any weld joints.
deterioration of the drum shell to
nozzle welding shall be inspected xiv) Any welding inside the drum having
carefully. visible defects shall be removed by
grinding and shall be carefully
iv) All the weld seams and the areas inspected for cracks and defects.
adjacent, shall be inspected for
cracks/deterioration. Corrosion along c) Water Headers/Mud Drums
or immediately adjacent to a seam is
more serious than same magnitude of The water headers are susceptible
corrosion in the solid plate away from to heavy deposits build up. In the event of
seam. considerable deposit build up, the flow
may be restricted thus causing
v) Grooving and cracks along overheating. Inspection shall be carried
longitudinal seams are especially out as specified below.
significant as they are likely to occur
when material is highly stressed. i) Visual inspection of all the water
headers shall be done after removing
vi) Severe corrosion is likely to occur at the header caps.
points where the circulation of water is
poor. Such points shall be inspected. ii) All hand holes and their cover seats
shall be inspected for erosion,
vii) Manhole and hand holes cover plates corrosion and cracks. Steam cutting
and their seating surface shall be marks or any other abnormal condition
which might permit leakage shall be ii) Inspection of furnace roof refractory
inspect. shall be done for any leakage and
deterioration.
iii) Leaky header caps shall be inspected
for trueness and possible deformation. iii) Ignitory horns shall be inspected for
erosion, cracks or any other
iv) Internal surface of headers shall be deterioration.
inspected for scale deposits, pits or
any deterioration. Whenever 2) Burners
practicable fibroscope should be used.
i) Burner tips and defusers shall be
v) External inspection of the header shall inspected for evidence of cracking and
be done after the removal of enlargement of holes.
insulation. Particular attention should
be paid to the points, where tubes ii) Burner throat refractory shall be
enter the header for indications of inspected for cracks, erosion and
leakage from the tube roll. fusion.
vi) The header surface adjacent to the iii) Condition of the air regulating vanes
tube roll and hand holes shall be shall be checked for any deterioration.
inspected for cracks.
iv) The burner gun shall be checked for
vii) Thickness survey of all the headers alignment and any other physical
shall be done. abnormalities.
viii) The hanger supports shall be i) Thickness survey of the headers and
inspected for oxidation, breakages and its connected stubs shall be examined
dislocation. by radiography method for loss of
thickness or inside pitting, corrosion measurement is not possible,
etc. radiography should be done.
ii) Some of the stubs connected to viii) Internal inspection of the bend of
headers, if accessible, should be assessing the internal condition, pitting
examined by radiography method for erosion, thinning etc. can be done by
loss of thickness or inside pitting, taking radiographs.
corrosion etc.
j) Indirect Contact Type
iii) External condition of the headers shall Desuperheaters:
be checked for corrosion and pitting
due to wetting of insulation. Thorough inspection of the coils
and desuperheaters shell shall be done
iv) Weld joints of tubes to headers shall after pulling out the tube bundles.
be inspected for cracks or any other
deterioration. i) Tubes bundles external surface shall
be inspected for corrosion, pittings or
i) Super Heater Coils: any mark of steam impingement on
tubes.
Visual inspection of all the stages
of super heater coils shall be carried out ii) Tube ‘U’ bends shall be inspected for
as mentioned below: cracks due to thermal fatigue caused
by steam and water.
i) Nature of external scale deposited,
type of pitting, corrosion under the iii) All the tubes weld joints shall be
deposit due to high temperature of flue inspected for cracks or any
gas shall be checked. deterioration
ii) Super heater coil near the roof iv) Shell internal surface of the
refractory wall shall be closely desuperheater shall be visually
inspected for any external corrosion inspected for pitting and corrosion
and pitting. before and after cleaning.
iii) The coil shall be checked for evidence v) Shell to flange weld joints shall be
of any external dent or abrasion inspected for cracks or weld corrosion.
marks, bowing and bulging etc.
vi) The weld joints at all the steam inlet
iv) All super heater element hangers and and outlet connections with the shell
spacer shall be inspected for burning shall be inspected for cracking.
and damage.
vii) Thickness survey of the shell along
v) For internal inspection, a sample from with the steam inlet and outlet stub
the super heater coil should be taken connections shall be carried out.
and split into two halves for assessing
the internal condition once in 8 years. viii) The weld joints of water inlet and
outlet connection with their respective
vi) Local attack in super heater tube may headers should be inspected by
result from carry over of droplets of random radiography to check the
boiler water and concentration of welding condition.
strong alkalis on the metal surface
particularly at bottom, bends. These ix) Before inserting the tube bundles, it
bends should be inspected by means should be hydraulically tested at 1.5
of radiography, if accessible. times the working pressure.
iii) The calorifiers shall be tested with m) Air Duct and Wind Box:
steam to detect any leakage of tube.
In case of any leakage, the leaky tube i) The surface of the air duct and wind
shall be plugged using plugs of same box whenever accessible shall be
metallurgy. visually inspected for scaling,
corrosion and pitting.
iv) Calorifier should be replaced if more
than 50% tubes have been plugged or ii) Ultrasonic thickness survey should be
earlier depending upon operational carried out to know the remaining
requirements. thickness of the plates.
l) Air Preheaters iii) The air duct and wind box shall be
examined for any buckling or
Air Preheaters are or two types, mechanical damage.
recuperative and regenerative type. Air
preheaters are subjected to corrosion on iv) External surface shall be checked for
flue gas side due to condensation during corrosion which might have taken
idle period and also during operation at the place due to defective insulation.
region where metal skin temperature falls
below dew point. Usually the condition at n) Flue Gas Ducts:
inlet and outlet ends will give a good
indication of the condition in the remaining The metallic flue gas duct plate
parts of preheater. shall be inspected for internal scaling and
corrosion. The scale, if noticed, should be
1) Recuperative Type Air analysed to know the cause of corrosion.
Preheater: Ultrasonic thickness survey shall be done
to determine the thinned portions.
i) The tube ends and tube sheets shall Expansion bellows shall be checked for
be inspected for corrosion or tube end leaks and cracks. External surface shall
thinning. be inspected for corrosion.
ii) The condition of the nozzles shall be iv) If any part of the boiler shows undue
checked for erosion and corrosion. deflection or indication of permanent
deformation during progress of the
iii) Steam and air soot blowers shall be test, the pressure shall be released
inspected gland packing leaks and immediately. For more details, Indian
evidence of warpage would tend to boiler regulations shall be referred.
make the unit bend and jam while in
use. s) Safety Valves:
iv) Evidence for leakage of wall box seal Inspection and testing of safety
and steam shut off valve shall also be valves shall be done as per OISD
checked. Standard -132 on Pressure Relieving
Devices.
v) The blower, supporting hangers and
brackets shall be examined visually for t) Deaerator:
soundness and for excessive thinning
from oxidation. i) Visual inspection for the external
surface of shell column for pitting,
q) Pipe Connections and fittings: corrosion, and cracks shall be done.
The pipe connections around the ii) All weldings shall be checked for
boiler shall be inspected for distortion, corrosion, pittings, and cracks.
metal wastage, supports, settlement of
foundation and pipe roller movements. iii) Column trays and its supports shall be
For details OISD inspection standard-130 inspected for any chokage or
on process piping can be referred. deterioration.
Ref. No _____________
Date__________________
_________________________________________________________________________
S.No. Parameters Design Period To Remarks
limits ________________________
MON TUE WED THU FRI SAT
__________________________________________________________________________
1. Feed Water
(Ex Deareator)
02 content
2. Feed Water pH
3. Deareator Temperature
4. Economiser Water
Temperature
Inlet
Outlet
5. Water Hardness
as CaCO3
6. Total dissolved
Solids at boiler
drum
7. Chemical Dosing
a) Morpholine
b) Sulphite (Na2P03)
c) Phosphate (Na3P04)
d) Hydrazine (NZNNH2)
8. Flue gas temperature
(Ex air heater)
9. Flame Condition
Boiler No.1
Boiler No.2
Boiler No. 3
and so on
10 Other abnormalities
(if any)
__________________________________________________________________________
Legends: G-Good, I-Impingement, C-Carbonised flame Flame, O-Oxidized, Y-Yes.
ANNEXURE-II
_______________________________________________________________________________
CHEMICAL TEST UTILISED FOR PREVENTION OR CONTROL OF
METHOD ______________________________________________________________
CORROSION SCALE EBRITTLE- CARRYOVER
MENT
_______________________________________________________________________________
RAW WATER
A-Acidity or * --- --- ---
Alkalinity --- * --- ---
B-Hardness,
Calcium,
Magneism --- * --- ---
SOFTENED WATER
A-Acidity or
alkalinity * --- --- ---
B-Hardness, Calcium
Magneism --- * --- ---
FEED WATER
A-Acidity or
Alkalinity * * --- ---
B-Hardness, Calcium
Magneism --- * --- ---
BOILER WATER
A-Acidity or
alkalinity * * --- ---
C-Hydroxide * * * *
D-Phosphate --- * * ---
E-Sulphate * --- --- ---
F-Nitrate --- --- * ---
_______________________________________________________________________________