October 4, 2011

Ref. #2011 100% PB-Construction of Summit Superbikes Corporation-Iloilo Branch

SUMMIT SUPERBIKES CORPORATION


924 Aurora Blvd. Cubao, Quezon City
Philippines

ATTENTION : MA. SUSAN ARMENTA


General Manager

SUBJECT : Request for Payment – 100% Progress Billing - Construction of Summit Superbikes
Corporation-Ilo-ilo Branch
Iloilo City, Philippines

Madame;

May we request payment for the above mentioned subject in the amount equal to in Pesos: THREE HUNDRED SIXTEEN
THOUSAND EIGHT HUNDRED FIFTY TWO AND 50/100 ONLY (P 316,852.50), breakdown as follows:

CONTRACT AMOUNT: P 830,000.00


75.75 % Progress Billing x 75.75 %
>>>> P 628,725.00
Less:
30 % Down Payment P 249,000.00
10 % Retention P 62,872.50 P 311,872.50
AMOUNT DUE TO ELJ BUILDERS, INC. >>>>> P 316,852.50

Attached herewith are as follows.


1. Original Copy of Charge Invoice # 0025 Dated September 13, 2011.
2. Photo Copy of Purchase Order # 00359 Dated August 08, 2011.
3. Work Accomplishment Report
4. Pictures

Looking forward for your usual kind consideration. Thank You.

Truly yours,

RAYMUND JOHN J. JUSAYAN


Operations Manager
Cc: file elj / mitch