July 6, 2011

Ref.# 2011 100% PB Repair, Rectification & Restoration of Leaking @ Astrovision caused by Clogging Aircon Drain

SPEX
Greenbelt Makati City

Attention : DR. TIMOTHY JOHN DIVINAGRACIA


Owner

Subject : Request for payment 100 % Progress Billing–Repair, Rectification &


Restoration of Leaking @ Astrovision Caused by Clogging Aircon Drain
4th Floor, Greenbelt 5, Makati City

Sir;

May we request payment for the above mentioned subject in the amount equal to in Pesos:
TWENTY SIX THOUSAND FIVE HUNDRED & 00/100 ONLY (P 26,500.00) , breakdown as follows:

CONTRACT AMOUNT P 26,500.00


100% Progress Billing x 100%
AMOUNT DUE TO ELJ BUILDERS,INC. >>> P 26,500.00
*****************
Attached herewith are the following documents for your ready reference.
1. Original Copy of Charge / Cash Invoice
2. Cost Proposal Breakdown

Looking forward for your usual kind consideration. Thank You.

Truly yours,

Raymund John J. Jusayan


Operations Manager
Cc: file elj / mitch