Ref. #2011 100% PB-Construction of Summit Superbikes Corporation-Iloilo Branch
Ref. #2011 100% PB-Construction of Summit Superbikes Corporation-Iloilo Branch
SUBJECT : Request for Payment – 100% Progress Billing - Construction of Summit Superbikes
Corporation-Ilo-ilo Branch
Iloilo City, Philippines
Madame;
May we request payment for the above mentioned subject in the amount equal to in Pesos: ONE HUNDRED
EIGHTY ONE THOUSAND ONE HUNDRED FORTY SEVEN AND 50/100 ONLY (P 181,147.50), breakdown as
follows:
CONTRACT AMOUNT: P 830,000.00
100 % Progress Billing x 100 %
P 830,000.00
Less:
30 % Down Payment P 249,000.00
75.75% Progress Billing P 316,852.50
10 % Retention P 83,000.00 P 648,852.50
AMOUNT DUE TO ELJ BUILDERS, INC. >>>>> P 181,147.50