You are on page 1of 64

COMPETENCY BASED LEARNING MATERIAL

Sector:
CONSTRUCTION
Qualification:
CARPENTRY NC II
Unit of Competency:
PREPARE STAKE-OUT BUILDING LINES

Module Title:

PREPARING STAKE-OUT BUILDING LINES

Technical Education and Skills Development Authority

Welcome to the Module Preparing stake-out building lines. This module


contains training materials and activities for you to complete.
The unit of competency “Stake-out building lines.” contains the knowledge and
skills and attitudes required for Carpentry. It is one of the specialized modules at
National Certificate level I (NC II).
You are required to go through a series of learning activities in order to complete
each learning outcomes of the module. In each learning outcome there are
Information Sheets to help you understand better the required activities. Follow these
activities on your own and answer the self –check at the end of each learning
outcome. You may remove a blank answer sheet at the end of each module (or get
from your facilitator/ trainer) to write your answers for each self-check. If you have
questions, don’t hesitate to ask your facilitator for assistance.

Instruction sheets:

 Information Sheet – This will provide you with information (Concepts,


principles and other relevant information) needed in performing certain
activities.

 Operation Sheet – This will guide you in performing single task, operation
process in a job.

 Job Sheet – This is designed to guide you how to do the job that will contribute
to the attainment of the learning outcome.

 Assignment Sheet – The assignment sheet is a guide used to enhance (follow


up) what you have learned in the information sheet or job sheet.

 Worksheet – are the different forms that you need to fill up certain activities
that you performed.
LIST OF COMPETENCIES

NO UNIT OF COMPETENCIES MODULE TITLE CODE


1
Stake-out Building Lines Staking-out Building Lines

2 Fabricate Formworks Fabricating Formworks

3 Install Formworks Components Installing Formworks


Components

4 Strip Formworks Components Strip Formworks Components

5 Install Framing Components Installing Framing


Components
MODULE CONTENT

UNIT OF COMPETENCY: Stake-out Building Lines

MODULE TITLE: Staking-out Building Lines

MODULE DESCRIPTOR: This module covers the knowledge, skills and attitudes in
preparing materials for stake-out building lines, setting batter boards, fixing building
lines.

NOMINAL DURATION: 24 Hours

QUALIFICATION LEVEL: NC II

LEARNING OUTCOMES:
At the end of this module you MUST be able to:
LO1. Prepare materials for stake-out building lines
LO2. Stake-out and set batter boards
LO3. Fix building lines

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 4 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
LEARNING OUTCOME SUMMARY

Qualification : CARPENTRY NC-II


Unit of Competency : Stake-out Building Lines

Module Title : Staking-out Building Lines

Learning Outcome # 1 : Prepare materials, tools and equipment for Staking out
Building Lines

Contents:
 Tools, materials and equipment for staking-out building lines
 Materials estimates
 Economic use of materials
 Basic geometrical construction
 Linear Measurement
 Board foot computation

Assessment Criteria:
 Plans and details are correctly interpreted and identified according to job
requirements
 Materials, tools and equipment are identified consistent with job requirements
 Materials and tools are properly stored and freed from defects.
 Appropriate PPE are selected according to job requirements.

Resources:
Students/Trainees must be provided with the following:
Tools Equipment Materials
Personal Protective Plan and working
Claw Hammer
Equipment drawings
Pencil/marking Automatic level
Lumber
pen
Pull-push rule Nails
Water hose level
Nylon String
Plumb Bob

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 5 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Steel Square
Try-square
Hand Saw
Chalk Line
Bolo
Sledge Hammer

Evaluation Methods:
 Self Check
 Demonstration

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 6 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Learning Experience

LEARNING OUTCOME # 1:
Prepare materials, tools and equipment for Staking out Building Lines

Learning Activities Special Instructions

Read Information Sheet If you have some problem on the content


No. 1.1-1 Tools, of the information sheet don’t hesitate to
materials and approach your facilitator.
equipment for Staking If you feel that you are now
out Building Lines knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.

 Answer Self-Check No. Compare your answer to the answer key


1.1-1 1.1-1. If you got 100% correct answer in
this self-check, you can now move to the
next information sheet. If not review the
information sheet and go over the self-
check again.
 Read Information Sheet If you have some problem on the content
No. 1.1-2 on Materials of the information sheet don’t hesitate to
estimates approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
 Answer Self-Check Compare your answer to the answer key
No1.1-2 1.1-2. If you got 100% correct answer in
this self-check, you can now move to the
Operation Sheet. If not review the
information sheet and go over the self-
check again.
 Read information sheet If you have some problem on the content
no.1.1-3 on Economic of the information sheet don’t hesitate to
use of materials approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 7 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
 Answer Self-Check No. Compare your answer to the answer key
1.1-3 1.1-3. If you got 100% correct answer in
this self-check, you can now move to the
Operation Sheet. If not review the
information sheet and go over the self-
check again.
 Read information sheet If you have some problem on the content
No. 1.1-4 on Linear of the information sheet don’t hesitate to
measurement approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
 Answer Self-Check Compare your answer to the answer key
No.1.1-4 1.1-4. If you got 100% correct answer in
this self-check, you can now move to the
Operation Sheet. If not review the
information sheet and go over the self-
check again.
 Read information sheet If you have some problem on the content
No 1.1-5 Board foot of the information sheet don’t hesitate to
computation approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
 Answer Self-Check Compare your answer to the answer key
No.1.1-5 1.1-5. If you got 100% correct answer in
this self-check, you can now move to the
Operation Sheet. If not review the
information sheet and go over the self-
check again.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 8 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
INFORMATION SHEET 1.1-2

Learning Objectives: After reading this information sheet, you must be able to:
 Identify the tools and materials and their uses in staking- out building lines

Tools and Materials Used for Staking-out Building Lines

Introduction

It is very important to know the name and proper use of each of the various tools
we need in our work. In addition, their proper care and maintenance will give you the
following advantages: efficiency of the work, quality speed, accomplishment and
accuracy.

The following are the most commonly used staking out tools and materials:

Carpentry Tools

Hammer –it is used for driving & pulling out nails

Sledge Hammer- is used to sink corner stakes or


batter boards and posts.

Push-pull rule – Use in measuring distances and


dimensions.

Plumb-bob is used to locate the corners of the


building dimensions.

Hand saw - is used to cut batter boards and posts.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 9 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Framing square - is used to check the squareness
of lines.

Carpenter's level/Bar Level is used to level a


surface and to sight level lines. It may be used
directly on the surface or with a straight edge.

Crow bar - it is used to pull out large nail and


stripping wood works.

Transparent hose level - is use to get the


horizontal level of any structure.

Pencil- it is use in marking dimensions on


measurements

String line is used to distinguish the dimensions of


the building layout.

Chalk line is used to deposit chalk on the surface


in order to make a straight guideline.

Bolo is used to sharpen batter-board posts and


stakes.

A. Materials

1. Lumber- it is a sawn timber and used as stake and batterboard

Sizes of softwood or building construction lumber are standardized for convenience in


ordering and handling.

Lumber is sawn in standard (nominal) sizes:


Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 10 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
 Length: 8, 10, 12, 14, 16, 18, and 20 feet.
 Width: 2, 4, 6, 8, 10, and 12 inches.
 Thickness: 1, 2, and 4 inches.

2. Plywood is a thin cross laminated sheet of wood usually 4 feet by 8 feet and varies in
thickness from 1/8 to 1 inch.Plywood are also used to square building lines.

3. Nails are made of metal used for fastening wood and to secure string line to batter
boards.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 11 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
SELF-CHECK 1.1-2
A. MATCHING TYPE
I. Direction: Match the tools on column A with their classification on column B. Write
only the letter of the correct answer on your answer sheet.
Column A Column B

1. It is used to drive stake on the ground A.

2. It is used to drive & pull out nails


B.
3. It is used to level a surface and to sight
level lines. It may be used directly on the
surface or with a straight edge. C.

4. It is used to measure distances and dimensions. D.

1. Use to check the verticality of structure

E.

F.

B. Identification:
Directions: Identify what construction material is asked
1. ________ it is a sawn timber and used as stake and batterboards.
2. ________ is a thin cross laminated sheet of wood usually 4 feet by 8
feet and varies in thickness from 1/8 to 1 inch and are also used to
square building lines
3. ________ are made of metal used for fastening wood and to secure string line to
batter boards.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 12 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
ANSWER KEY
SELF CHECK # 2.1.1
MATCHING TYPE
1. A
2. G
3. C
4. F
5. B
IDENTIFICATION
1. Lumber
2. Plywood
3. Nail

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 13 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Information Sheet 1.1-2 Material Estimate

Learning Objectives: After reading the information sheet, you should be able to
Estimate materials for staking out building lines .

Introduction

A materials estimate list puts materials takeoff list information into a shorter form; adds
allowance for waste and breakage; and estimates quantities of materials needed (Table
below). The lumber required is listed by board feet (BF).

Sample of Materials Estimate List

In determining the materials for stakes and batterboards, one has to consider the
following;

1. The sizes of the stake to be used.


2. Elevation of the ground
3. Size of the Building to be lay-out
4. Kind of wood lumber to be used
5. Size and Number of columns

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 14 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Number of comuns- 9
Height of column – 8’

From the Floor plan above, The materials for staking out and setting batterboards
were estimated.

Item Size Description/unit Total Quantity

No.

1. 2”x2” x36” Stakes 36

2. 2”x2”x20’ Batterboard 24

3. 2”x2”x8’ Formworks 36

4. 1/4”x4’x8’ Plywood 9

5. 2”x2”x6’ Vertical Brace 36

6. 2”x 2” x 8’ Diagonal 18

7. 2”x2”x4’ Horizontal Braces 40

8. 2”x2”x16” Horizontal Braces 72

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 15 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
9. roll Nylon string 1

10 Meters Level Hose 12

11. kg CWN 3” 25

12. kg CWN 2” 8

13 kg CWN 1” 2

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 16 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Self Check 1.1-2

Material Estimate

Direction
Given a house plan with 3m x 3m with its Lenght and width and 8m high, estimate the
number of materials in staking and setting batterboard.

Item Size Description/unit Total Quantity


No.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 17 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
ANSWER KEY
Self Check 1.2-2

Item Size Description/unit Total Quantity


No.
1. 18
2”x2” x36” Stakes
2. 16
2”x2”x16’ Batterboard
3. 16
2”x2”x8’ Vertical brace
4. 4
1/4”x4’x8’ Plywood
5. 8
2”x2”x6’ Diagonal Brace
6. 32
2”x 2” x 8’ Diagonal
7. 16
2”x2”x4’ Horizontal Braces
8. 32
2”x2”x16” Horizontal Braces
9. 1
roll Nylon string
10. 1
Meters Level Hose
11. 6
kg CWN 3”
12. 1
kg CWN 2”
13. 1
kg CWN 1”
14. kg Cwn 4” 8

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 18 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Information Sheet 1.1-3

ECONOMIC USE OF MATERIALS

Tips for avoiding waste of construction materials.

1. Study carefully the plan and detailed drawing.


2. From the given detailed drawing, study its different parts, including their sizes.
3. When cutting lumbers, always refer to the schedule of cutting
4. Always determine the methods of measurement used in the plan for Marking
5. Always remember the principles for cutting “measure twice and cut once”
6. In cutting lumber and plywood, always use effective tools.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 19 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Self Check 1.1-3 True or False

Direction: Write True if the statement is correct and False if the statement is not
correct.

1. _________ Carefully Studying the plan and detailed drawing will contribute to
the economic use of materials
2. _________ From the given detailed drawing, study its different parts, including
their sizes.
3. _________ Always refer to the schedule of cutting when measuring lumbers.
4. _________ Always determine the methods of measurement used in the plan for
Marking
5. _________ Always remember the principles for cutting “measure once and cut
twice”

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 20 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Answer Key
Self Check 1.1-3
1. True
2. True
3. False
4. False
5. False

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 21 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
INFORMATION SHEET 1.1-4
LINEAR MEASUREMENT
Learning objective: After reading the information sheet, you must be able to
 Identify the two system of measurement
 Convert English to metric measurement and vice versa

System Of Measurement
A system of measurement is a set of units which can be used to specify anything
which can be measured.These are common units of measurement used in making layout
and installation of electrical materials.
Linear measures
1. English system:
The English system of measurement grew out of the creative way that people
measured from themselves. For example, people measured shorter distance on the
ground with their feet. They measured long distances by their palms which is equal to
a yard.
 Inch
 Yard
 Miles

2. Metric system is a decimalized system of measurement. It exists in several
variations with different choices of base units. Metric units are widely used around
the world for personal, commercial and scientific purpose.
 Millimeter - mm M dm cm mm
 Centimeter - cm
 Decimeter - dm
 Meter - M

1.0 0.1 0.01 0.001

Example: A. To convert 2 meters to dm, count 1 decimal places going to the right and
add it as zero, so the answer is 20 decimeter.
B. To convert 2 meters to cm, count 2 decimal places going to the right and
add it as zero, so the answer is 200 centimeter.
C. To convert 2 meters to mm, count 3 decimal places going to the right and
add it as zero, so the answer is 2000 centimeter

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 22 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
English units and each equivalent
 12 inches =1foot(ft)
 1 foot = 3yard (yd)
 1 yard = 36 inches

Metric units and each equivalent
 10 millimeter (mm) = 1centimeter (cm)
 10 centimeter = 1decimeter(dm)
 100 centimeter = 1meter

English to metric equivalent


 1 inch = 2.54 cm
 1 foot = 30.48 cm
 1 yard = 91.44 cm
 1 ft = 3.28 m

The centimeter graduation

5mm

0.5mm 1mm 10mm or 1cm

The graduations show that every mark is .5mm


How to read the cm graduation:
 First graduation is .5 mm
 Second graduation is 1mm
 Third graduation is 1.5mm
 Fourth graduation is 2mm

If the graduation reaches 10mm, it is equivalent to 1cm.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 23 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
The inch graduation

0 1/8 1/4 3/8 1/2 5/8 3/4 7/8 1


inch

1/16 3/16 5/16 7/16 9/16 11/16 13/16


15/16

How to read the inch graduation:


 First graduation is 1/16
 Second graduation is 1/8
 Third graduation is 3/16

 Fourth graduation is 1/4, then follow the given scale above.

The inch graduation in a steel rule:

Converting the unit of measurement from English to metric and vice versa
Example:
1. 24 inches = ________ cm
Cancel the common unit and apply cross
Since multiplication.
24 inches = 2.54 cm
1 inch

24 x 2.54 cm Perform the indicated operation.


1
Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 24 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Therefore: 24 inches = 60.96 cm

2. 5 feet = ________ inches


Since
5 feet = 12 inches
1 feet

5 x 12 inches
1
Therefore: 5 feet = 60 inches

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 25 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
SELF-CHECK 1.1-4
LINEAR MEASUREMENT
A. Direction: Write the equivalent value of the given unit.
_______ 1. 1cm is ______ mm
_______ 2. 1 yard is _____ inches
_______ 3. 1dm is ______ cm
_______ 4. 15mm is _____ cm
_______ 5. 1foot is ______ inches

B. Direction: Write the correct unit abbreviation of the following:


_______ 6. centimeter
_______ 7. Meter
_______ 8. Decimeter
_______ 9. Yard
_______ 10. Feet

C. Direction: Convert the following:


1. 3 m = __________ cm
2. 70 cm = ___________ mm
3. 15 cm = _________ inches
4. 5 meters = __________ft
5. 48 inches = _________ m

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 26 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
SELF-CHECK 1.1-4 ANSWER SHEET
A.
1. 10mm
2. 36 inches
3. 10 cm
4. 15 cm
5. 12 inches
B.
1. cm
2. m
3. dm
4. yd
5. ft
C.
1. 300 cm
2. 700 mm
3. 6 inches
4. 16.40 ft
4.2 m

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 27 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
INFORMATION SHEET 1.1-5
Compute Board Feet of a Lumber

Learning Objective:
After reading this information sheet, you must be able to:
 Follow the formula in computing board feet of lumber and log
 Compute board feet of lumber and log

Although the system International (SI) has already superseded the english System of
measure, the board foot as the unit measure of lumber popularly and widely used is still
presented for reference in prepararion for the transition from english to Metric approach.
A board foot is actually one square foot of wood one inch thick. The formula being used
in computing board foot is:

Board Foot = t x w L
12

Where t = thickness in inches


w = width in inches
L = Length in feet

This formula is being used for sawed wood of commercial dimensions.

Example:
Compute the board foot of the following lumber:

5pcs – 2” x 6 x 14’

Bd. ft. = 5 x 2 x 6 x 14
12

= 70

The above formula could not be used in finding the board foot of logs. Instead, the
following formula is applied:

Board ft. = (D-4)2 x L


16
Where D = smaller diameter of the logs in inches
L = Length of log in feet
4 and16 = are slab deduction allowance which are constant in the
formula

Example :

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 28 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Given
D= 24”
L= 18’

Find the total board foot that could be derived from the log for commercial
purposes.

Solution:

Board Ft. = (24 – 4)2 x 18 ft.


16

= (20)2 x 18
16

= 450 bd. ft.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 29 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
SELF-CHECK 1.1-5

Directions: Solve for the number of board feet of the following Pieces of lumber.

1. 15 pcs – 2” X3”X14’

2. 60 pcs – 2”X2”X18’

3. D= 26”
L= 16’

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 30 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Answer Key

Self check 1.1-5

1. 105 bd. ft.


2. bd. Ft.
3. 484 bd. ft.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 31 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
LEARNING OUTCOME SUMMARY

Qualification : CARPENTRY NC-II


Unit of Competency : Stake-out Building Lines
Module Title : Staking-out Building Lines

Learning Outcome #2 : Stake-out and set batter boards

Contents:
 Concepts of setting batter boards
 Staking out building lines
 Procedure in Setting Batter Board
Assessment Criteria:
 Stakes are set out from pre-determined building lines
 Batter board materials are measured, laid out and cut according to specification
 Stakes are set 0.75-1.00 meter away from the pre-determined building lines
 Batter boards are properly secured with tolerance for dimensions at ± 5 mm, and
levelness of ± 3 mm.
 Appropriate PPE is used according to job requirements

Resources:
Students/Trainees must be provided with the following:
Tools Equipment Materials
Personal Protective Plan and working
Claw Hammer
Equipment drawings
Pencil/marking Automatic level
Lumber
pen
Pull-push rule Nails
Water hose level
Nylon String
Plumb Bob
Steel Square
Try-square
Hand Saw
Bolo
Sledge Hammer
Evaluation Methods:
 Self Check
Demonstration

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 32 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Learning Experiences
LEARNING OUTCOME # 2: STAKE-OUT AND SET BATTER BOARD

Learning Activities Special Instructions


 Read Information Sheet If you have some problem on the content
No. 1.2-1 on Concept in of the information sheet don’t hesitate to
Setting Batter Boards approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
 Answer Self-Check No. Compare your answer to the answer key
1.2-1 1.2-1. If you got 100% correct answer in
this self-check, you can now move to the
next information sheet. If not review the
information sheet and go over the self-
check again.
 Read information sheet If you have some problem on the content
1.2-2 on staking out of the information sheet don’t hesitate to
building lines approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
 Perform Job sheet Compare your work to the performance
1.2.2 on Staking out checklist and let your trainer check it. If
building lines you got 100% correct answer in this
activity, you can now move to the next
information sheet. If not review the
information sheet and go over the
activity again.
 Read Information Sheet If you have some problem on the content
No. 1.2-3 on Procedure of the information sheet don’t hesitate to
in Setting Batter Board approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now task
sheet provided in the module.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 33 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
 Perform Job sheet 1.2- Compare your work to the performance
3 on Setting checklist and let your trainer check it. If
batterboard you got 100% correct answer in this
activity, you can now move to the next
information sheet. If not review the
information sheet and go over the
activity again.

INFORMATION SHEET 1.2-1


Concept of Setting Batterboards

Learning Objective: After reading the information sheet, you must be able to
understand the concept of Setting Batterboards

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 34 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Introduction
Batter boards are the horizontal boards placed at the corner and at the sides of
the projected building when final layout takes place. The reference for the foundation is
marked on these boards.

Batter-board posts are made from 2 x 4 or 4 x 4 material; corner stakes are made
from 2 x 2s. Batter boards are made from 1 x 4 or 1 x 6 pieces.

Two Types of Batter Boards

1. Batter boards for foundation posts may be either joined by


continuous pieces surrounding the site of foundation or by individual
piece for each foundation.

2. Batter boards for the foundation walls are either single or double
batter boards which are placed at corner.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 35 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
The batter boards should be set as high as the desired height of the foundation. In
constructing with different heights of foundation, the tallest foundation is set as the
height of batter boards.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 36 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
SELF-CHECK 1.2-1

Identification

1. ______________What do you call the horizontal boards placed at the corners and at the
sides of the projected building when final layout takes place?

2. ______________What should be the height of the batter boards?

3-4. _____________, _______________What are the two types of batter boards?

5.________________ In constructing with different heights of foundation posts, what is


the height of the batter boards?

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 37 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
ANSWER KEY

Self-Check 1.2-1

1. Batter boards
2. Height of the foundation

3-4 Batter boards for the foundation posts and batter boards for the foundation wall
5. Tallest foundation

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 38 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Information Sheet 1.2-2
Staking Out Location of Building

Learning Objectives:
After reading the information sheet, you must be able to follow the
procedures in staking-out the location of building lines

Measure the required distance of the building from the reference line. Use string as a
guide for squaring and making the orientation line parallel to the reference line. I

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 39 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 40 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
JOB SHEET 1.2-2

Staking-Out Building Lines

Performance Objectives: Given tools supplies and materials you are going to
perform the steps in staking-out location of building lines.

Tools

1. Push-pull rule
2. Plumb bob
3. Nylon string
4. Sledge hammer
5. Bolo
6. Framing square

Materials:

a. Pegs and stakes


b. Lumber

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 41 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Basing from this Floor and foundation plan, locate and stake-out building lines

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 42 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 43 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Information Sheet 1.2-3
Procedure in Setting Batter Board

Learning Objectives: After reading the information sheet, you must be able to follow .

the procedure in setting batter boards .

Procedure:

1. Determine the height of the foundation at any of the four corners of the proposed
building, preferably where the grade stake is.

2. In this corner, drive a stake as high as the desired height of the foundation.

3. Drive in set of posts for the batter boards 3 or more feet away from the corners and along
the sides. Drive in the posts firmly. Align these posts with a string.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 44 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
4. Move the height of the foundation from the stakes to the corner post of the batter
board. This is done by stretching a string, leveled with plumb level from the stake to the
post.

5. From the mark of this post, stretch out a string going around the corners of the
building and passing at the side of the batter board posts.

6. Level this string with a plumb level. Stretch the string tight. Start leveling from the corner
where the height of the foundation is established. Recheck the level.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 45 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
7. Mark batter board posts along the line just leveled. These marks are placed at the top
of the batter boards.
8. Nail the batter boards in place, the straight side up and at the marks of the posts.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 46 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Job Sheet 1.2-3
Setting A Batter Board

Performance Objectives: Given tools supplies and materials you are going to
set batter board
Tools: Hand saw, Hammer, Plumb-bob,Nylon string, Level hose, framing square,PPE
Materials: Lumber, Nails

Direction: From the given plan, set a batter board that can be conveniently used.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 47 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Performance Criteria Checklist

Competent
PERFORMANCE CRITERIA YES NO NA
1. Batter boards are set away from the building line /
excavation.

2. Batter boards are properly secured with


tolerance for dimension at + 5mm, and levelness /
of + 3mm.

3. Unexpected situations are responded to in line


with company rules and regulations. /

4. Housekeeping is performed according to safety


regulation. /

5. Tools are properly used and taken cared of.


/
6. Personal Protective Equipment are used for
safety. /

Satisfactory
Overall Performance
Unsatisfactory

Trainee’s name: _Mark Josh C. Mendez

Trainer’s comment: ___________________________________________________


___________________________________________________
___________________________________________________

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 48 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Qualification : CARPENTRY NC-II
Unit of Competency : Stake-out Building Lines
Module Title : Staking-out Building Lines
Learning Outcome #3 : Fix building lines

Contents:
 Types, functions uses of testing tools
 Laying out/fixing building lines
Assessment Criteria:
 Building lines are squared with end tolerance of ± 3 mm
 Building lines are measured and set
 Appropriate PPE is used according to job requirements

Students/Trainees must be provided with the following:


Tools Equipment Materials

Claw Hammer Personal Protective Plan and working


Equipment drawings

Pencil/marking pen Lumber


Pull-push rule Nails

Nylon String Plywood


Plumb Bob
Steel Square
Try-square
Hand Saw
Chalk Line
METHODOLOGY:
 Modular (self-pace learning)
 Demonstration

ASSESSMENT METHOD:
 Interview (oral/questionnaire)
 Direct Observation
 Demonstration of Practical Skills

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 49 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Learning Experience
LEARNING OUTCOME # 3: Fix Building Lines

Learning Activities Special Instructions


1. Read Information If you have some problem on the content
Sheet No. 1.3-1 on of the information sheet don’t hesitate to
Types, Function and approach your facilitator.
Uses of testing Tools
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
2. Answer Self-Check Compare your answer to the answer key
No. 1.3-1 1.3-1. If you got 100% correct answer in
this self-check, you can now move to the
Operation Sheet. If not review the
information sheet and go over the self-
check again.
3. Read information sheet If you have some problem on the content
1.3-2 on Laying out/fixing of the information sheet don’t hesitate to
building lines approach your facilitator.
If you feel that you are now
knowledgeable on the content of the
information sheet, you can now answer
self check provided in the module.
4. Perform Job Sheet 1.3-2 Compare your work to the checklist and
on laying out/fixing let your trainer check it. If you got 100%
building lines correct answer in this activity, you can
now move to the next information sheet.
If not review the information sheet and
go over the activity again.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 50 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
INFORMATION SHEET 1.3-1

Learning Objectives: After reading the information sheet, you must be able to explain
the types, functions, and uses of testing tools

Types, Functions and Uses of Testing Tools


Good carpentry work demands accuracy in measurement. This could be done only
with the aid of various testing tools to accomplish a precise and quality work.
It is important to know the various testing tools and how to use them properly.
They may cause accidents if proper care and use are not observed. Using proper tools in
the proper job can prolong their use.
Types of Testing Tools and Their Uses

1. Square is a 90o standard right angle sometimes called try square used for testing
and squaring stocks into dimension.

Types of Squares:

A. Try square is a square with blade ranging from 6 inches to 12 inches.

B. Miter square is a square with blade permanently set at 45o.


C. Combined try and meter square is a combination of 45o and 90o in one set.
D. Combined square is similar in appearance to try square only that the head can be slid
and clamped at any desired distance from the blade. It is also provided with a meter
and level guide.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 51 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
E. Framing or steel square is used effectively on various framing works.

F. Sliding T-bevel is like try square with sliding and adjustable blade that could be set
any angle.

G. Bar Level is used for both guiding and testing the work to a vertical or horizontal
position.

H. Plastic hose with water is one of the best and accurate tools for guiding work in
establishing a horizontal level.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 52 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
I. Plumb bob is a cone-shaped metal suspended on a string used to check or obtain
a vertical line.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 53 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
SELF-CHECK 1.3-1

Matching Type

I. Match column A with column B.


Write the letter only.

A B
a
1. A square made of flat steel throughout framing square
2. A square with sliding and adjustable blade b plastic hose
that could be set to any angle.
3. Used for both guiding and testing the work c combination
to a vertical or horizontal position square
d
4. A combination of 45o and 90o in one set tongue
5. The most accurate tool for guiding work in e Bar level
establishing a horizontal level.
6. A square with blades ranging from 6-12” f combined try and
meter square
7. A metal used to check or obtain a vertical g plumb bob
Line
8. A square with blades permanently set at h sliding T-bevel
45o
9. The shorter and narrower part of the i meter square
framing square
10. A square which head can be slided and j body
clamped at any desired distance from the k try square
blade.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 54 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
ANSWER KEY

Self-Check 1.3-1

1. a
2. c
3. e
4. f
5. b
6. k
7. g
8. I
9. d
10. h

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 55 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Information Sheet 1.3-2

Laying Out/fixing Building Lines

Learning Objectives: After reading the information sheet, you must be able to
enumerate the procedures in laying out/ fixing building lines

Introduction
Building lines pertain to lines representing the sides of the building passing
through the center of the foundation posts. The final laying-out is done on the batter
board. Before the builder can start the layout, he has to decide which among the
building lines he is going to use.

Procedure in Laying out/fixing the Foundation Lines:

1. Transfer the oriented line to the top of the batter boards. This is done by hanging a
plumb bob to the oriented line, and by making the corresponding point on the batter
board.

2. Locate the center of the foundation from the orientation line at the opposite batter
boards. Then mark these two points with nails or a saw kerf.

3. Stretch string No. 1 on these two marks. Anchor it to the batter boards. This line
should never be moved during the process of squaring lines.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 56 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
4. Tie a cord to this line to indicate the original corner A. Align this cord to the corner
stake with a plumb bob.

5. Measure the length of the side that falls on line 1, starting from the original corner,
and tie another cord to mark this corner B.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 57 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
6. Stretch line No. 2 square or perpendicular to line 1, passing through the cord tied at
the original corner A. Tie line 2 to nails on the batter boards.

7. From the intersection of lines 1 and 2 at the original corner A. Measure the length of
the side of the building that falls on string 2. Tie another cord to mark this corner C.
8. Through this corner, mark stretch string 3 square to string 2.
9. Measure the length of the side that falls on line 3, and tie a cord to mark corner D.
10. Through corner D, stretch line 4 to the opposite corner B on line
11. Check the square formed by these two lines.

After the four sides of the building are completely laid out there is a need to check
squareness by the use of the diagonal method.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 58 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 59 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Job Sheet 1.3-2 Laying Out/fixing Building Lines

Performance Objectives: Given tools supplies and materials you are going to
lay out/fix building lines to the batter board

Tools: Hand saw, Hammer, Plumb-bob,Nylon string, Level hose, framing square,PPE

Materials: Lumber, Nails

Direction: Given a floor plan, layout/fix building lines to the batter board.

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 60 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Performance Criteria Checklist

Competent
PERFORMANCE CRITERIA YES NO NA
1. Stake-out building lines are properly secured
for references in excavating building
foundation.

2. Marking lines are squared and plumbed from


the batter board lines with tolerance of + 3mm
all measurement.

3. Marking lines are squared and plumbed from


the batter board lines with tolerance of + 3mm
all measurement.

4. Worksite is clean and safe based on


Occupation Safety and Health Condition
regulations.

5. Daily work report is accomplished in


accordance with company rules and
regulations.

Satisfactory
Overall Performance
Unsatisfactory

Trainee’s name: __________________________

Trainer’s comment: ___________________________________________________


___________________________________________________
___________________________________________________

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 61 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
ASSESSMENT PLAN
Evidence Checklist
Carpentry NCII
Competency standard:
Unit of competency: Prepare Stake-out Building Lines
Title of Module Preparing Stake-out Building Lines
Ways in which evidence will be collected: [tick the column]

Demonstr
Questioni
Observati

Written
ation
on
LO1.Prepare materials for Stake-out Building Lines.
1. Appropriate Personal Protective Equipment (PPE) is selected *
and used according to job requirements and Occupational Safety *
and Health Condition (OSHC) standards.
2. Plans and details are correctly interpreted and identified *
according to job requirements.
3. Materials, tools and equipment are identified consistent with *
job requirements.
4. Materials and tools are properly stored and free from defects. *
5. Unexpected situations are responded in line with company
*
rules and regulations.
6. Housekeeping is performed according to safety regulation *
LO2. Set Batter Board
1. Batter boards are set away from the building line excavation * *
2. Batter boards are properly secured with the tolerance for *
dimension at +/-5mm tolerance and levelness of + 3mm
3. Unexpected situations are responded to in line with company
*
rules and regulations.
4. Housekeeping is performed according to safety regulations. *
LO3. Fix Stake-out Building Lines
1. Stake-out building lines are properly secured for reference in
*
excavating building foundations.
2. Marking lines are squared and plumbed from the batter board
*
lines with tolerance of +/-3mm in all measurements.
3. Work site is cleaned and kept in safe state according to
*
Occupational Health and Condition ((OHSC) regulations.
4. Daily work report is accomplished in accordance with
*
company rules and regulations
REMARKS: ___________________________

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 62 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
References/further reading

Lewis, Gaspar., Carpentry

Hernan, Hjorth., Woods, Woodworking

Lubrica, Jose B., Building Construction

Koel, Leonard., Carpentry

Fajardo, Max B., Simplified Methods on Building Construction

Fajardo, Max B., Simplified Construction Estimate

Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 63 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao
Document No.
Date Developed:
May 2011 Issued by:

Carpentry NC I1 Developed by: Page 64 of 44


Romeo A. Baquiran
Manuel N. Calayan Revision #
Ireneo L. Salvador
Celso K. Lumidao

You might also like