Professional Documents
Culture Documents
TECHNICAL SPECIFICATIONS
EXCAVATION AND EARTHWORK
Scope
This Specification describes the general requirements of excavation and earthwork in
different materials, site grading, filling, including filling back around foundations and
plinths, disposal of surplus soil or stacking as directed by The Project Manager and all
operations covered within the intent and purpose of this Specification.
Applicable Codes
The latest revision of the following Indian Standards and Codes, unless otherwise
specified, shall be applicable to all Excavation and Earthwork
Before any blasting is carried out the Contractor shall obtain the written approval of the.
Project Manager and provide the Project Manager with details of the hours of firing
charges,
the nature of the explosives to be used and the precautions taken to ensure complete
safety.
The Contractor shall ensure that all workmen and personnel at Site are excluded from an
area within 200 meters radius from the firing point at least 15 (fifteen) minutes before
firing
time by sounding a warning signal.
Blasting in the vicinity of existing buildings, equipment or any other property shall be
done
under cover and the Contractor shall provide all necessary muffling arrangements.
Covering
shall comprise mild steel plates with adequate dead weight over them. Blasting shall only
be
done with small charges and a trench cut by chiseling prior to the blasting operation
separating the area under blasting from such existing structures.
Firing shall be strictly supervised by the licensed blaster and not more than 6 (six) holes
at a
time shall be set off successively. If blasts do not tally with the number fired the misfired
holes shall be carefully located after half an hour and when located shall be exploded by
drilling a fresh holes alongside the misfired hole, but not nearer than 600 mm from it,
and
by exploding a new charge.
Wooden tamping rods with flat ends shall be used to push cartridges home and metal rods
or hammers shall not be permitted. Charges shall be placed firmly into place and not
rammed or pounded. After a hole is filled to the required depth the balance of the hole
shall
be filled with stemming consisting of sand or stone dust or similar inert material.
CONCRETE WORKS
Scope
This specification describes the general requirements for concrete to be used on projects
using in-situ production facilities including the requirements in regard to the quality,
handling, storage of ingredients, proportioning, batching, mixing and testing of concrete,
the requirements in regard to the quality, storage, bending and fixing of reinforcement
and the transportation of concrete from the mixer to the place of final deposit, placing,
curing, protecting, repairing and finishing.
Applicable Codes and Specifications
The following Standards and Codes are made part of this Specification. All the Standards
and Codes of Practice referred to herein are references to the latest editions including any
and all official amendments and revisions.
Materials
IS 269 Specification for Ordinary, rapid-hardening and low heat Portland cement.
IS 455 Specification for Portland Blast Furnace Slag Cement.
IS
Specification for Portland-Pozzolana Cement.
1489
IS
Method of physical tests for hydraulic cement.
4031
IS 650 Specification for Standard Sand for Testing of Cement.
IS 383 Specification for coarse and fine aggregates from natural sources for concrete.
IS
Methods of tests for aggregates for concrete (Parts I to VIII)
2386
IS 516 Method of tests for strength of concrete.
IS
Method of sampling and analysis of concrete.
1199
IS
Methods of sampling and test (physical and chemical) water used in industry.
3025
(Parts I & II) Specification for mild steel and medium tensile steel bars and
IS 432
hard drawn steel wire for concrete reinforcement.
IS Specification for hot rolled mild steel and medium tensile steel deformed bars
1139 for the concrete reinforcement.
IS Specification for plain hard drawn steel wire (Part I) fabric for concrete
1566 reinforcement.
IS
Specification for plane hard drawn steel wire for pre-stressed concrete.
1785
IS
Specification for cold twisted steel bars for concrete reinforcement.
1786
IS
Specification for high tensile steel bars used in pre-stressed concrete.
2090
IS
Specification for plywood for concrete shuttering work.
4990
Preambles
IS
Specification for integral cement water-proofing compounds.
2645
BS
Cold worked steel bars for the reinforcement of concrete.
4461
IS
Recommended
10262
Equipment
MASONRY
RUBBLE MASONRY
Scope
This specification describes the general requirements of uncovered and covered rubble
masonry on projects.
Applicable Codes
The latest revision of the following Indian Standards and Codes, unless otherwise
specified, shall be applicable to rubble masonry:
Preambles
IS 1129 (1972) Stone; Dressing
Stone; slabs, stacking and packing for
IS 8348 (1977)
transportation
IS 1805 (1973) Glossary of terms: quarrying and dressing
Compressive, transverse and sheer strength
IS 1121 (1957)
determination
IS 8759 (1977) Maintenance and preservation of stone
IS 4348 (1973) Permeability determination
IS 1122 (1957) Specific gravity and porosity determination
Water transmission rate through natural building
IS 4121 (1967)
stone
IS 1706 (1972) Wear resistance, determination by abrasion method
Un-coursed Random Rubble in Foundations, Plinths and Superstructures
For work below ground level masonry shall be uncoursed random rubble with ordinary
quarry dressed stones for hearting and faced with selected quarry dressed stones.
For work above ground level and in superstructures masonry shall be coursed, well-
bonded random rubble faced with hammer dressed stones with squared quoins at joints
and corners.
Stones shall be of a type and from a single source approved by the Project Manager in
accordance with the samples provided by the Contractor. The Contractor shall provide
evidence to the Project Manager that there are adequate supplies of the approved stones
available at the quarry.
Stones shall be hard, durable rock, close or fine grained and uniform in colour, free from
veins, flaws and other defects and shall conform to IS 1597 (Part I).
Sufficiently wetted stones shall be laid in the mortar specified for the particular type of
work and the thickness of the joints shall not exceed 12 mm.
No stone shall tail into the wall either with a point or to length less than 1.5 times the
height.
Spawls and pinnings shall not show on the face of the wall. Two bond stones each of a
minimum area of 500 square centimetres for every 1 square metre of each wall face shall
be provided. Bond stones shall be through stones in walls 600mm thick and below. In
walls thicker than 600mm the length of bond stones shall be 2/3 the thickness of walls.
Stones for hearting in the wall shall not be less than 150mm in any direction. Chips and
spawls shall be wedged in to avoid thick mortar beds and joints. Wall faces, corners and
joints of openings shall be truly vertical. Quoins shall be of selected stones neatly dressed
with chisels to form the required angles and laid header and stretcher alternately.
Exposed faces of work shall be carefully and neatly pointed with mortar in all joints. On
the other side joints shall be neatly struck with trowel while the mortar is fresh.
Coursed Rubble (First Sort) in Superstructures
For work above ground level and in superstructures masonry shall be coursed, well-
bonded random rubble faced with hammer dressed stones with squared quoins at joints
and corners.
Stones shall be of a type and from a single source approved by the Project Manager in
accordance with the samples provided by the Contractor. The Contractor shall provide
evidence to the Project Manager that there are adequate supplies of the approved stones
available at the quarry.
Preambles
Stones shall be hard, durable rock, free from veins, flaws and other defects and shall
conform to IS 1597 (Part I).
Course heights shall not be less than 150mm. Stones in each course shall be of equal
height and all courses shall be of the same height unless otherwise specified.
Sufficiently wetted stones shall be laid in cement mortar specified for the respective type
work. Bed joints shall be horizontal and side joints vertical and no joint shall be more
than 10mm thick.
Face stones shall be squared on all joints and beds, beds being hammer or chisel dressed
true and square for at least 75mm from the face and joints for at least 40mm. Face of
stones shall be hammer dressed so that bushings do not project more than 40mm.
Spawls or pinnings shall not show on the face of the wall. No face stone shall be less in
breadth than in height or shall tail into the work to a length less than the height and at
least 1/3rd the number of stones shall tail into the work to at least twice their height or 3
times their height in walls over 600mm thick.
Through stones shall be inserted every 1.5 metres to 1.8 metres apart in every course and
shall run right through when the wall is not more than 600mm thick. In walls more than
600mm thick a line of two or more headers shall be laid from face to face and shall
overlap each other by at least 150mm. Headers shall have lengths at least three times the
height.
Stones shall break joint at least half the height of the course. Quoins shall be formed of
stones at least 450mm long laid stretcher and header alternately, square in their beds and
which shall be fair dressed to a depth of at least 100mm. Corners shall be chisel dressed
for a width of 25mm.
Work on interior faces shall be precisely the same as on exterior faces unless the work is
to be plastered or rendered in which case side joints need not be truly vertical.
Hearting shall consist of flat bedded stones carefully laid on their proper beds and solidly
bedded in mortar, chips and spawls of stone being wedged in wherever necessary so as to
avoid thick beds or joints of mortar. Care shall be taken to ensure that no dry work or
hollow spaces are left anywhere in the masonry. Faces and backing shall be brought up
evenly but the backing shall not be levelled up at each course by the use of chips.
Protection and Curing
Green work shall be protected from rain by suitable covering. Masonry in cement or
composite mortar shall be kept constantly moist on all faces for a minimum period of 7
(seven) days. Tops of masonry shall be left flooded with water at the end of each working
day. Care shall be taken not to disturb or wash out green mortar.
Curing of masonry shall continue for a minimum of 10 (ten) days. In the case of masonry
in lime mortar curing shall commence two days after laying and shall continue for a
period of 7 (seven) days.
SIZE STONE MASONRY
Size stones shall be of hard granite, basalt or trap stone obtainable from approved quarry.
The stones shall be clean and wetted before they are used.
Height of course, shall not be less than 15cms. and all courses shall be of uniform height.
Unless otherwise instructed the depth of higher courses should not be more than the depth
of lower courses. Bed and sides shall be hammed or chisel dressed from the face 75mm
and 35mm respectively.
No face stone shall be less in depth than in height or shall tail into the work to a length
less than the height. Stones shall break joints at-least half the height of the course. Faces
Preambles
of stones shall be hammer dressed and bushing not be more than 25mm. Thickness of
joints shall not be more than 20mm. Edges of face stones of exposed faces shall be
chiseled true to both longitudinal and vertical lines. Exposed faces of corner stones to be
2 line dressed 50mm wide.
Bond or through stones shall be provided not exceeding 2.0mtr. apart in each course and
shall be staggered. Bond stone shall be from the front to the back of the walls. For wall
upto 60cms thick under, bond stones shall be in one piece and for walls over 60 cms.
thick they shall either be in one piece (if available locally) or be in the series of headers;
each header overlapping the adjoining one by not less than 150mm. Bond or through
stones shall be marked as directed to enable their being easily detected even after having
been built in position. The interior or filling shall be with flat bedded stones laid mortar.
Chips, spalls shall be used to avoid thick mortar joints and shall not exceed 10% of the
quantity of stone masonry. Care is to be taken that no dry work or hollow spaces shall be
left anywhere in the masonry.
MORTAR MIXING
Mixing of mortar shall be done in a mechanical mixer. Hand mixing shall be resorted to
only when specifically permitted by the architect. Cement and sand shall be mixed dry
thoroughly and then water shall be added gradually. Wet mixing shall be continued till
mortar of the consistency of a stiff paste and uniform colour is obtained. Only the
quantity of mortar which can be used within thirty minutes of its mixing shall be prepared
at a time.
Mortar shall be used as soon as possible after mixing and before it has begun to set and in
any case within thirty minutes after the water is added to the dry mixture. Mortar left
unused for more than thirty minutes after mixing shall be rejected and removed from the
site of work.
CURING
Green work shall be protected from rain by suitable covering. Masonry in cement or
composite mortar shall be kept constantly moist on all faces for a minimum period of 7
(seven) days. Tops of masonry shall be left flooded with water at the end of each working
day. Care shall be taken not to disturb or wash out green mortar.
Curing of masonry shall continue for a minimum of 10 (ten) days. In the case of masonry
in lime mortar curing shall commence two days after laying and shall continue for a
period of 7 (seven) days.
SCAFFOLDING
Unless otherwise instructed by the architect, double scaffolding having two sets of
vertical metal supports shall be provided for all building work. The supports shall be
sound, strong and tied together with horizontal pieces over which scaffolding planks shall
be fixed.
The contractor shall be responsible for providing and maintaining sufficiently strong
metal scaffolding so as to withstand all loads likely to come upon it. Wooden scaffolding
shall not be permitted.
The surface shall be completely cleaned of all dirt, dust etc. and made perfectly in one line
without any evenness by supplying a thin coat of plaster as required and made rough by wire brush.
The required water proofing treatment shall be applied before fixing the tiles. The water proofing
treatment shall be paid in the relevant item. The roofing tiles set in cement mortar 1:3. The tiles
shall be laid in perfect slope so that no water can seep under the tiles. The ridge and valleys shall be
provided in such a manner that the junctions are formed properly without disturbing the appearance
and permits easy flows of water. The joint shall be finished in the same colour as the tiles. The
bottom tile shall project about 5cm beyond the slab line. The junction with wall shall be made
carefully and the tile shall be fixed inside the wall by making Jhari about 25 to 50mm deep, so that
no water can percolate from the junction. Cement vata shall be provided on at the junction of the
tiles and the wall and shall be finished in the same colour.
The item includes all materials, including ridges, valley etc and labour complete. It shall be
paid on Smt basis visible work done. The water proofing treatment and cement vata shall be paid
for in the relevant items separately.
Materials;
Top and bottom G.I. tension wire shall be of best quality and of 8 gauge.
Workmanship:
The pits of the size 0.5 x 0.5 x 0.5mm shall first be tension made either in brick work or excavated,
true to line and level to receive the post at 2.5 m. C/C specified by the Architect/Engineer-in-
charge.
Preambles
The pits shall be filled with a layer of 0.15 mm thick with lean concrete 1:5:10 (1 cement : 5
Sand :10 Graded brick bat aggregates 40mm nominal size). The M.S. angle 40mm x 40mm x 6mm
shall be then placed over the concrete in true line and plumb. The remaining portion of block shall
be filled in with cement concrete 1:2:4 and rammed properly so as to form total 0.5mm x 0.5mm
concrete block. The concrete shall be cured for 7 days to allow it to set.
The chain link shall be stretched and fixed as per drawing. The bottom row shall be 1250 mm
above ground. The chain link shall be stretched between adjacent post from top wire of one post to
the bottom wire of second post. The wire shall be fixed to post by means of staples.
The M.S. angle posts shall be painted with 3 coats of oil paint of approved tint and shade over coat
of primer. Chain link shall be applied with silver paint if required.
The work shall be measured in Running meter. The rate is inclusive of all materials mentioned in
description of items including oil painting etc. complete.
12.1 Material:
PVC hand rail shall be of approved colour and make such as calaiplast or equivalent as
approved by the Architect and Engineer in charge.
12.2 Workmanship:
The railing shall be fixed as per the design, drawing with necessary hardware. Work shall
be carried out with best workmanship and specification laid down by the manufacturer.
The item shall be measured and paid in running meter. No hidden measurements shall be measured
and paid. Only actual visible measurement shall be measured and wastage shall not be permitted.
13.1 Materials:
13.2 Workmanship:
Preambles
The maximum spacing of purling shall be 1.6 meters in case of 7mm thick A.C. sheets and
1.4 meters for 6mm thick A.C. sheets.
The sheets shall be laid on the purling and other roof members as per code of practice. The
top bearing surface of all purling and other roof members shall be in one plane so that the sheets
when being fixed shall not be required to be forced down to rest on the purling. The finished roof
shall present uniform slop and the line of corrugation shall be starlight and true. The sheets shall be
laid with smooth side upwards. Corrugated sheets shall be laid starting at the eaves either from left
to right or right to left depending upon the direction of wind. Before actual laying of the sheets in
started, the purlins spacing and the size of sheets shall be checked to ensure that the arrangements
shall provide the laps required and the specified overhang at the eaves. In case the sheets are laid
from tight to left, the first sheet shall be laid uncut but the remaining sheets in the bottom row shall
have the top left hand corners cut or mitered. The sheets in the second and other immediate rows
shall have bottom right hand corner of the first sheet cut. All other sheet shall have only top left
hand corner cut. The last of the top row sheets shall have the bottom right hand corner cut with
exception of the last sheet which shall be left uncut. If the sheets are laid from left to right, the first
sheet shall be laid and cut and the remaining procedure shall be reversed.
The free overhang of the sheets at the eaves shall not exceed 400mm. In case of 7mm thick
sheets and 300mm in case of 6mm thick sheets.
The miter described above is necessary to provide snug fit. Where 4 sheets meet at a lap
the length of meter shall be 150mm and the width of miter shall be equal the width of the side lap.
The cutting may be done with ordinary wood-saw at site.
13.2.3 Laps:
The sheets shall be laid with an end lap of 150mm minimum. In case of roof with a pitch
flatter than 1 vertical to 2.5 horizontal (Approx. 22 degree) or in the case of very exposed situations
appropriate larger laps may be provided. The sheets shall be laid with side lap of half a corrugation.
The Sheets shall be secured to purlins and other roof members by means of 8mm
galvanized iron bolts “J” type hook bolts in case of angle iron purlins and ‘L’ type bolts in case of
R.S. joist, pre-cast concrete, or timber purlins, and nuts bearing galvanized iron washers and
bitumen washers. The grip of ‘J’ or ‘L’ bolts on the side of purlins shall not be less than 25mm.
Each galvanized iron ‘J’ or ‘L’ hook bolts shall have a bitumen washer and galvanized iron washer
paced over the sheets before the nuts is screwed form above. On each purlins there shall be one
hook bolt on the crown adjacent to the side lap on either side bitumen washer shall be of approved
quality. The G.I. flat washer shall be 25mm in diameter and 1.60mm thick and bitumen washer
shall be 35mm in dia and 1.5mm thick with hole to suit the required size of fixing accessory. Each
nut shall be screwed lightly at first. After a dozen or more sheets are laid, the nuts shall be
tightened to ensure to a leak-proof joint and also nuts tightened only to extent so as to prevent
Preambles
damage to the sheets. The length of the ‘J’ bolts or crank bolts shall be 75mm more than the depth
of purlins for single sheet fixing and 90mm more where two sheets overlap or where ridges or other
accessories are to be fixed. The minimum length of cock screw for timber purlins shall be 110mm.
13.2.4 Holes:
The holes for fixing the sheet shall be drilled in the center of end lap of sheets to suit the
purlins i.e. on the center line of the purlins, if these are of timber and square head cock screws are
used, or as close as possible to the back of purlins if ‘J’ or ‘L’ bolts are used with steel angles or
pre-cast concrete or timber purlins. Holes for hook bolts etc. shall be 2mm more than the diameter
of the fixing bolts. No holes shall be nearer than 40mm to any edge of sheet or accessory.
The measurement of the Asbestos Cement sheet root shall be taken for finished work only.
The over lap of the corrugated sheets over valley gutters, roof lights, caves, filler pieces and
underlay of the corrugated sheets below ridges, hips, north light curves, flashing pieces, roof light
sheets and barge board shall be included in the measurement. No deduction shall be made for holes
cutting for extractors or cowl type ventilators. Deductions shall be made for roof light sheets.
T.W. Dasa
The wood shall be of best available Burma teak wood approved by the Architect/Engineer. The
cross sectional area of the dasa shall be up to 75 Sq.cm. It shall be given in the shape as per details
given in the drawings. The turnings shall be made from a single piece of wood joining the upper
and lower dasa in a smooth curve. It shall be properly fixed on the runner of the railing as shown
on the drawings. It shall be finished with warning or enamel painting, in the best workmanship.
The item includes all material, including turning, all labour, painting, varnishing, screws
etc. complete. It shall be paid on running meter basis of work done.
15.1 Workmanship :
The Surface shall be cleaned fully and all dust, dirt or organic or inorganic substances shall
be removed from the surfaces with wire brush. Any major or minor cracks on the surface shall be
opened out to ‘V’ share and cleaned and all loose materials shall be removed by using compressed
air or water jet. The cracks shall be filled with chemical water proofing materials.
One coast of epoxy shall be applied with sufficient thickness to form rigid and water fight
membrane and allowed to dry over night. Second coat shall be applied similarly. After the second
coat is completely dry, the surface shall be tested by filling 15cm of water for 48 hours. No
dampness shall appear below the entire surface. If there is any dampness seen any where the whole
process shall be repeated until the surface below remains completely dry after 48 hours of testing.
Preambles
The contractor shall furnish a bond on stamp paper of Rs.40/- for a period of ten years as
per annexure No.1 no. 1. If there is any water leakage during the guarantee period the contractor
shall have to rectify the defect and any damage at his own lost.
The brick bats shall be form well-burnt bricks. The proprietary water proofing compound shall
conform to IS2645:1975. Before execution of work, waterproofing compound has to be brought
to site from which random sample would be got tested and certificate of its conforming to IS code
should be produced. The proprietary waterproofing compound shall be added at the rate
recommended by the specialist firm but not exceeding 3% by weight of cement.
16.1 The finished surface after water proofing treatment shall have minimum slope of 1 in 60.
At no point shall the thickness of water proofing treatment be less than 65mm.
While treatment of roof surface is done, it shall be ensured that the outlet drainpipes have been
fixed and mouth at the entrance have been eased and rounded off properly for easy flow of water.
The surface where the waterproofing is to be done shall be thoroughly cleaned with wire brushes.
All loose scales shall be removed and dusted off. The surface shall be treated with neat cement
slurry admixed with proprietary water proofing compound to penetrate interstices and fill up all
the porosities in the surface this cement slurry shall be applied to the junction of parapet and
terrace slab by injection process.
After the slurry coat is laid a layer of well burnt brick bat shall be laid in cement mortar of mix as
specified by the specialist firm but not leaner than 1:5 (1 cement: 5 coarse sand) admixed with
proprietary water proofing compound to required gradient and joints filled to half depth. The
brickbat layer shall be rounded at the junction with parapet and tapered towards top for a height
of 300mm. Curing of this layer shall be done for 3 days.
After curing, the surface shall be applied with a coat of cement slurry admixed with proprietary
water proofing compound.
Joints of brick bat layer shall be filled fully with cement mortar of mix as specified by the
specialist firm but not leaner than 1:4 (1 cement: 4 coarse sand) admixed with proprietary water
proofing compound and finally top finished with average 20mm thick layer of same mortar and
finished smooth with cement slurry admixed with proprietary water proofing compound. The
finished surface shall have marking of 300 x 300 mm false squares to gives the appearance of
tiles.
Preambles
Curing of water proofing treatment shall be done for a minimum period of 10 days.
Measurements: The measurement shall be taken along the finished surface of treatment including
the rounded and tapered portion at junction of parapet wall. Length and breadth shall be measured
correct to one centimeter and areas shall be worked out to nearest 0.01 sqm No. deduction in
measurement shall be made for either openings or recess for chimneys, stacks, roof lights and the
likes for areas up to 0.40 Sqm. nor anything shall be paid for forming such opening. For similar
areas exceeding 0.40 Sqm. deductions will be made in measurements for full openings and
nothing extra shall be paid for making such openings.
Rates: The rate shall include the cost of all labour and materials involved in all the operations
described above.
Brickbat aggregate shall be form well with burnt bricks. The proprietary water proofing
compound and the quantity to be used shall be as per Para 15.1
The surface shall be thoroughly cleaned with wire brushes. All loose scales shall be removed and
dusted off. The surface (bottom as well as sides) shall be treated with cement slurry admixed with
proprietary water proofing compound to penetrate interstices and fill up all the porosity in the
surface.
After the slurry coat in laid, a layer of well burnt brick bats/aggregates of about 40mm size shall
be laid in cement mortar of mix as specified by the specialist firm but not leaner than 1:5 (1
cement: 5 coarse sand) admixed with proprietary water proofing compound the mortar being
filled to half the depth of the aggregate. The brick bat/aggregates layer shall be rounded of at
junctions with the beam/wall etc. curing of this layer shall be done for 3days.
After curing, the surface shall be applied with a coat of cement slurry admixed with proprietary
water proofing compound.
Joints of brick bat/aggregate shall be filled fully with cement mortar of mix as specified by the
specialist firm but not leaner than 1:4 (1cement: 4 coarse sand) admixed with proprietary water
proofing compound and top finished with average 20mm thick layer of same mortar. This layer of
mortar shall be continued to the sides of beam/wall, etc. The height up to, which this treatment is
to be extended on the sides shall be as, directed by the Architects. The surface shall be finished
smooth with cement slurry admixed with proprietary water proofing compound.
While the water proofing treatment is done, it shall be ensured that the outlet pipes are properly
filled with brick/stone aggregate and cement mortar admixed with proprietary water proofing
compound and grouted with cement slurry admixed with proprietary water proofing compound
by injection process.
Measurements: Measurements for the floor treatment shall be taken on plan area of floor treated.
Nothing extra shall be paid for founding off at junctions and taking the treatment along the sides
Preambles
of beams and walls for about 100mm. Sides of beam / wall etc.. Where the treatment is only with
mortar shall be measured and paid separately, length and breadth shall be measured correct to one
centimeter and area calculated to 0.01 Sqm.
Rates: The rates shall include the cost of all labour and material involved in all the operations
described above. Base treatment and sides treatment will be paid separately under respective
items.
4. WATER:
a) Recommended tests:
i. P-Alkalinity
ii. M-Alkalinity
iii. Inorganic solids
iv. Sulfates
Preambles
v. Chlorides
vi. Suspended solids
vii. Organic solids
viii. pH value
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references
IS: 456-1978 Code of practice for plain and reinforced concrete
IS: 3025-1986 Methods of sampling and tests (Physical and chemical) for water
and waste water.
Part-1 (1986): Sampling
Part-2 (1983): pH value
Part-15 (1989): Total residue (total solids dissolved and suspended
Part-16 (1989): Total dissolved solids
Part-17 (1989): Total suspended solids
Part-23 (1986): Alkalinity
Part-24 (1986): Sulfates
Part-32 (1988): Chlorides
5. ADMIXTURES:
(Accelerating, retarding, water reducing/workability improvement and air entraining
admixtures)
a) Recommended tests:
i. Water content of concrete with and without admixture
ii. Setting time of concrete with and without admixture
iii. Compressive strength of concrete with and without admixture
iv. Change in length of concrete with and without admixture
v. Bleeding of concrete with and without admixture
vi. Workability of concrete with and without admixture
vii. Aircontent of concrete with and without admixture
viii. Heat of hydration of concrete with and without admixture
ix. Chloride content
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 9103-1979 Specification for admixtures for concrete
IS: 516-1991 Methods of tests for strength of concrete
IS: 6925-1987 Methods of test for determination of water soluble
chlorides in concrete admixtures.
6. FRESH CONCRETE:
a) Recommended tests:
i. Slump/compaction factor/Vee Bee test
ii. Setting time of concrete by penetration method
Preambles
iii. Air content
iv. Analysis for constituents
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 1199-1991 Methods of sampling and analysis of concrete
IS: 8142-1987 Setting time of concrete by penetration resistance
7. HARDENED CONCRETE:
a) Recommended tests:
i. Compressive strength
ii. Accelerated curing
iii. Normal curing
iv. Permeability test
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 456-1978 Code of practice for plain and reinforced concrete
IS: 516-1991 Methods of tests for strength of concrete
IS: 9013-1987 Method of testing of accelerated cured concrete
IS: 3085-1990 Method of test for permeability of cement mortar and concrete.
8. REINFORCING STEEL:
a) Recommended tests:
i. Tensile test on bars welded or otherwise
ii. Bend and re-bend test
iii. Bond test
iv. Chemical analysis
b) Sampling and frequency of sampling:
As per guidelines in relevant Indian Standards.
c) Acceptance criteria:
As per guidelines in relevant Indian Standards.
d) Relevant references:
IS: 1786-1990 Specification of high strength deformed steel bars for concrete
reinforcement.
IS: 1608-1991 Methods of tensile testing of steel products
IS: 228-1987 Methods of chemical analysis of steel
Part-1: Determination of carbon by volumetric method
Part-3: Determination of phosphorous by alkali metric method
Part-9: Determination of sulphur