Professional Documents
Culture Documents
Hannah Progress
Hannah Progress
INTRODUCTION
Purpose of Report
In response to your June 25, 2023, request, the following is our Third Quarterly Report on the
Project Housing Development (Sub-Urban Areas). The Professional Develop Team, Finance
Team, and Engineers Team are already in the initial phase of our company’s planning,
financing and decision-making for the Housing Development in Sub-Urban Areas. This
Housing Development aims the following:
1. Affordable Housing
2. Safe and Healthy Living Environments
3. Economic Growth and Development
4. Community Revitalization
DISCUSSION
Work Accomplished
In this Third Quarterly Report which are the months of August, and September in the year
2023, we have completed the following:
Budget Tracking:
Shella Geyrozaga (Finance Department) aggregates the amount of the total budget for Phase
2 as Php10 million.
Budget Overview
Land Acquisition
Construction Costs
Infrastructure Development
Landscaping and Outdoor Amenities
Pulte Home Builders Corporation
Page 2
September 25, 2023
V. Variance Analysis
No major budget adjustments have been made to date. The current budget remains
valid.
IX. Reporting
Pulte Home Builders Corporation
Page 3
September 25, 2023
Developed a procurement plan detailing the timing and quantities of materials and equipment
required. Established procurement milestones to track progress. Ms. Tanggaro (Cost
Estimator) detailed the Budget Development. The initial budget estimate for the project was
set at a million. This estimation was accomplished on September 21, 2023. Collaborated with
project architects, engineers, and contractors to create a comprehensive budget.
I. Cost Estimation
Land Acquisition
Construction Costs
Infrastructure Development
Contingency Funds
Developed a procurement plan detailing the timing and quantities of materials and equipment
required. Established procurement milestones to track progress.
Land Acquisition
Procurement Method: Direct purchase from landowners.
Procurement Timeline: Negotiations are to be completed within 3 months.
Construction Contracts
Infrastructure Development
Contingency Funds
Financial Report
This financial report provides an overview of the financial status of the Housing
Development project as of [Reporting Date]. The report includes budget vs. actual
comparisons, cash flow analysis, and explanations for significant variances.
Expenses |
Assets
| Current Assets
| Current Liabilities |
| Equity |
In this example:
Pulte Home Builders Corporation
Page 7
September 25, 2023
The income statement provides details on revenue and expenses for the quarterly ended
September 21, 2023. The project generated a net income of $250,000 during the quarter
The balance sheet reflects the project's financial position as of December 21, 2023. It shows
current assets, property, plant, and equipment, as well as liabilities and equity. The project
has a positive equity of $5,700,000. This was accomplished last September 9, 2023.
Angelica Quilo (Surveyor) attained surveying the site and lining out the exact area where the
project or structures are built. Excavation and grading to prepare the land for building. This
was accomplished last September 15,2023.
Problem Encountered
Cost Overruns: Construction projects often face unexpected expenses due to factors
such as changes in material price fluctuations and labor shortages.
Material Price Fluctuations - Unexpected material price increases
impact construction costs, leading to increased expenses for materials
and transportation, resulting in cost overruns. Extended project
execution may exacerbate these overruns, especially when material
prices continue to rise.
Labor Shortages - affect the quality of workmanship in housing
development projects. When there is a shortage of skilled workers,
contractors may be forced to hire less experienced or unqualified
individuals to fill the gaps. This can result in lower-quality
construction, which may require rework or repairs in the future, further
adding to the overall project costs.
Inadequate Financial Planning: This can pose significant challenges during project
implementation. This includes insufficient forecasting of costs and revenues and a
lack of contingency plans for unexpected events.
Insufficient Forecasting of Costs and Revenues - can increase the risk
of financial distress for the developer. Without a comprehensive and
accurate forecast of costs and revenues, developers may be unable to
accurately assess the financial risks of the project, leading to a higher
risk of financial distress.
Lack of Contingency Plans for Unexpected Events - Without
contingency plans, the housing development program is vulnerable to
unforeseen events such as economic downturns, changes in market
conditions, or unexpected cost escalations. These events can lead to
Pulte Home Builders Corporation
Page 8
September 25, 2023
budget shortfalls, making it difficult to secure additional funding or
complete the project within the planned timeframe
Work Remaining
2. Tax Planning - Involves optimizing financial strategies to minimize the tax liability
associated with property development, ownership, and management. This can
encompass various aspects of taxation, including income taxes, property taxes, and
capital gains taxes. The target date of this task October 20, 2023
3. Landscaping and Outdoor Amenities: We are working with the “Green Paradise
Landscaping’ led by Rinze Ryan Rafael Berza to landscape the outdoor amenities like
Pulte Home Builders Corporation
Page 9
September 25, 2023
parks) playgrounds, and communal spaces. Serve as focal points for community
interaction and recreation.
*Tree Planting
4. Construction: The entire housing unit must be built. This construction comprises the
largest remaining task, Effective project management, quality control, and
coordination among contractors and stakeholders are essential to ensure a successful
transition from construction to occupancy.
Despite the fact that we have only recently begun this project, we have completed
approximately 65% of the work. We developers and financialist can create
sustainable communities that contribute positively to the overall urban landscape.
One of the primary causes of cost overruns is poor planning and budgeting. To
avoid this, project stakeholders must engage in early planning, including defining
project scope, identifying potential risks, and establishing a realistic budget. This
should involve a detailed cost estimation process, taking into account all relevant
factors such as materials, labor, and site conditions.
One way to mitigate the impact of material price fluctuations is by diversifying
suppliers. By sourcing materials from multiple suppliers located in different regions
or countries, businesses can reduce their reliance on a single source. This helps to
minimize the risk of supply disruptions caused by factors such as natural disasters
or political instability. Additionally, having multiple suppliers provides businesses
with more negotiating power, allowing them to secure better pricing terms.
Pulte Home Builders Corporation
Page 10
September 25, 2023
One of the primary causes of the labor shortage is the lack of immigrants to follow
skilled and high-skilled jobs. The U.S. government can increase immigration levels
to address this issue. According to the National Foundation for American Policy,
increasing immigration levels by 50% could help fill the labor shortage and boost
economic growth
One of the primary solutions to inadequate financial planning is the establishment
of a comprehensive budgeting system. Creating a budget allows individuals or
businesses to track their income and expenses, enabling them to identify areas
where they may be overspending or not allocating enough resources. By tracking
expenses, it becomes easier to make informed decisions about spending habits and
prioritize financial goals. Utilizing budgeting tools or apps can simplify the process
and provide real-time updates on financial status.
Advanced analytics techniques, such as machine learning, artificial intelligence, and
predictive modeling, can help businesses forecast costs and revenues more
accurately. These techniques can identify complex patterns and relationships in
data, which can improve forecasting accuracy.
Collaboration among individuals, organizations, and communities is essential for
effective contingency planning. By sharing information, best practices, and lessons
learned from past events, stakeholders can collectively develop comprehensive and
adaptable contingency plans. This can be facilitated through the establishment of
networks, forums, and platforms where individuals and organizations can exchange
knowledge and experiences. Additionally, governments can play a crucial role in
fostering collaboration by providing incentives, resources, and regulatory
frameworks that promote information sharing.
Pulte Home Builders Corporation
Page 11
September 25, 2023
The Percentage chart in Figure 1 determines the status of work done for the Project Housing
Development (Sub-Urban Areas)
Land scaping
Budget tracking
Community Engagement
Tax Planning
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 00%
1