Contract No.

ADB-301A-2018
Design, Supply, Installation, Testing & Commissioning of 500kV D/C Quad Bundle Transmission Line Nokhar S/s-Lahore North S/S-Lahore HVDC Switching/Convertor Station
(Job# 4185)

DAILY PROGRESS REPORT


August 07, 2023
Section-2
l Cumulative as of Today
Lahore North S/S - HVDC Converter Station
Activity
Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100


CONVENTIONAL
FOUNDATION 97 97 146 146 243 243 100

PILE FOUNDATION 35 35 57 57 92 92.00 100

PILE CAP 35 35 57 57 92 92 100

BACKFILLING 97 97 146 146 243 243 100

TOWER ERECTION 132 132 203 203 335 335 100.00

TOWER INSPECTION 132 132 203 201 335 333 99.40

TOWER PUNCHING 132 125 203 199 335 324 96.72

TOWER WELDING 132 124 203 200 335 324 96.72

TOWER PAINT 132 102 203 200 335 302 90.15

CONDUCTOR PULLING 44.644 38.097 68.374 48.399 113.018 86.496 76.53

DEAD ENDING / HOOK-UP


/ MID SPAN JOINT

CONDUCTOR SAGGING

CONDUCTOR CLIPPING Conductor clipping of T#107& T#110 carried out (Efraheem).

JUMPER INSTALLATION

SHIELDWIRE PULLING
& 44.644 32.933 68.374 38.879 113.018 71.812 63.54
SHIELDWIRE SAGGING
OPGW PULLING
& 44.644 32.933 68.374 38.841 113.018 71.774 63.51
OPGW SAGGING

Remarks. ROW at T#104

Remarks. Conductor pulling activity is suspended due to paddy crops. Remarks. Site activities have been suspended due to paddy crops.

DPR ADB-301A-2018, 07-08-2023