SUMMARY FINAL SETTLEMENT PREPARATION WORKS KRN BIODIESEL PLANT 2 (ON)

QTY UNIT RATE (IDR) AMOUNT (IDR)

NO DESCRIPTION PO Numbers UOM Actual Actual REMARK


Contract Total Contract
PT CAP PT KRN PT CAP PT KRN

A. PREPARATION WORKS 4500216184 / Refinery - KRN (P4M05_ON-PM1183)


Lsm 1,00 0,97 0,97 310.765.527,00 310.765.527,00 302.765.527,00 302.765.527,00

B. FIRE PROTECTION SYSTEM AT BIODIESEL PLANT AREA 4500216184 / Refinery - KRN (P4M05_ON-PM1183)
Lsm 1,00 0,93 0,93 2.976.012.722,80 2.976.012.722,80 2.781.011.588,80 2.781.011.588,80

C. FIRE PROTECTION SYSTEM AT BIODIESEL TANK ELEVASI 7,250


4500216184
M / Refinery - KRN (P4M05_ON-PM1183)
Lsm 1,00 0,98 0,98 3.773.588.645,95 3.773.588.645,95 3.714.946.670,95 3.714.946.670,95

D. FIRE PROTECTION SYSTEM AT BIODIESEL TANK ELEVASI 21,00


4500216184
M / Refinery - KRN (P4M05_ON-PM1183)
Lsm 1,00 1,00 1,00 3.008.820.654,40 3.008.820.654,40 3.008.820.654,40 3.008.820.654,40

E. FIRE PROTECTION SYSTEM AT BIODIESEL TANK ELEVASI 47,500


4500216184
M / Refinery - KRN (P4M05_ON-PM1183)
Lsm 1,00 1,00 1,00 730.812.450,00 730.812.450,00 730.812.450,00 730.812.450,00

100,00% 97,86% 97,86% 10.800.000.000,00 10.538.356.891,15 10.538.356.891,15